No.9 OF 650 · APPROVED, NOT BUILT MP: Mr Angus MacDonald (Liberal Democrat) Scotland

Inverness, Skye and West Ross-shire

Inverness, Skye and West Ross-shire was paid £41m last year to switch off its wind farms, because the wires south were full. That would cover every local household's electricity for about 1.3 years. A further 453 MW of approved clean power (almost all onshore wind) is still waiting to be built here: enough to supply a year's electricity to 398,000 homes. A 200 MW battery approved at Knocknagael, Essich in 2026 would store power that is currently wasted; it has not been built. A 50 MW battery was refused planning here in 2024; while discharging it could have supplied about 175,000 homes.

£41m
paid to wind farms here not to generate in the last year — enough to pay for every household here's electricity for about 1.3 years.
Elexon balancing data, 12 months to 31 Jul 2026 · No.1 of 19 seats with visible switch-offs · how we worked this out
453 MW
of clean power — almost all onshore wind — approved and still not built, enough to supply a year's electricity to 398,000 homes — 8 times every household in this constituency. Approved at least two years ago; waiting on the grid, not on planning. That is 0.4× the renewable capacity actually running here.
16 projects · 443 MW onshore wind, 8.7 MW hydro, 1 MW solar · planning database (REPD), July 2026 · how we worked this out
£4.6m
is what the grid gap costs this constituency's 50,093 households in a year between them — £92 each, about 51 days of one home's electricity.
The £92 per household is a national figure — identical in every GB seat. Only the seat total varies, with the number of households · NESO · how we worked this out

The waiting list

6 of 16 waiting projects · years since approval
Glen Ullinish Wind Farm 50 MW
11.4 YRS
Aberarder Wind Farm 50 MW
9.3 YRS
Bhlaraidh Wind Farm Extension 84 MW
3.9 YRS
Cloiche Wind Farm 125 MW
2.7 YRS
Corriegarth 2 67 MW
2.6 YRS
Bunloinn Wind Farm 67 MW
2.3 YRS

Every approved, unbuilt project

approved 24+ months ago, still not generating · planning database, July 2026
SiteTechnologyEnough forCapacityApprovedWaiting
Cloiche Wind FarmWind Onshore109,000 homes125.0 MW2023-112.7 yrs
Bhlaraidh Wind Farm ExtensionWind Onshore73,000 homes84.0 MW2022-083.9 yrs
Corriegarth 2Wind Onshore59,000 homes67.2 MW2023-122.6 yrs
Bunloinn Wind FarmWind Onshore58,000 homes66.6 MW2024-042.3 yrs
Aberarder Wind FarmWind Onshore44,000 homes49.9 MW2017-049.3 yrs
Glen Ullinish Wind FarmWind Onshore44,000 homes49.9 MW2015-0311.4 yrs
Allt na MoineSmall Hydro2,300 homes2.0 MW2014-0712.0 yrs
Lochaber Hydro Development (Scheme 3)Small Hydro2,300 homes2.0 MW2019-037.4 yrs
Gaineamhach Hydro Scheme PowerhouseSmall Hydro2,300 homes2.0 MW2023-102.8 yrs
Allt Garaidh Ghualaich Hydro Scheme PowerhouseSmall Hydro1,300 homes1.1 MW2018-038.3 yrs
Lochaber Hydro Development (Scheme 2)Small Hydro1,300 homes1.1 MW2019-037.4 yrs
Longman Pumping Station, Longman Drive - Photovoltaic PanelsSolar Photovoltaics200 homes0.7 MW2024-062.1 yrs
Gorthleck - Wind turbineWind Onshore400 homes0.5 MW2024-032.4 yrs
Allt an t-Sidhein Hydro SchemeSmall Hydro600 homes0.5 MW2019-106.8 yrs
Feed Millakin - Solar PanelsSolar Photovoltaics100 homes0.3 MW2023-073.0 yrs
Raigmore Hospital, Old Perth Road - Solar CanopySolar Photovoltaics— MW2023-112.7 yrs

Plus 2 more approved within the last two years.

Batteries

projects of 10 MW and above · planning database, July 2026 · what batteries do →
SiteSizeStatusWhile discharging
Knocknagael, Essich - Battery Energy Storage System200 MWapproved, not built 2026could supply ≈701,000 homes
Beinneun II Windfarm160 MWcould supply ≈561,000 homes
Glen Ullinish II - Wind Farm120 MWcould supply ≈420,000 homes
Clune Wind Farm - Battery Energy Storage100 MWcould supply ≈350,000 homes
Lynemore Wind Farm50 MWcould supply ≈175,000 homes
Tomchrasky Estate Wind farm50 MWapproved, not built 2025could supply ≈175,000 homes
Fairways Business Park - Battery Storage50 MWrefused 2024could supply ≈175,000 homes
Torrdhuin, Auchteraw Battery Storage Facility50 MWoperating 2021could supply ≈175,000 homes
Highland Wind Farm - Battery Storage30 MWcould supply ≈105,000 homes
Abhainn Dubh Wind Farm30 MWcould supply ≈105,000 homes
Kyllachy Wind Farm - BESS22 MWcould supply ≈77,000 homes
Ben Aketil Wind Farm - Repowered & Extended20 MWcould supply ≈70,000 homes

Wind farms paid to switch off

12 months to 31 Jul 2026 · mapping confidence shown · mapping file
SitePaid, 12 monthsEnergy lostConfidence
Stronelairg Wind Farm£14ma year of 64,000 homes' electricityhigh
Bhlaraidh (previously Balmacaan)£7.8ma year of 37,000 homes' electricityhigh
Dunmaglass Wind Farm£5.2ma year of 23,000 homes' electricityhigh
Glen Kyllachy Wind Farm£4.0ma year of 32,000 homes' electricityhigh
Corriegarth£3.2ma year of 16,000 homes' electricityhigh
Edinbane Wind Farm£2.1ma year of 7,600 homes' electricityhigh
Farr Wind Farm£1.8ma year of 7,900 homes' electricityhigh
Moy Wind Farm (2nd Application)£1.6ma year of 6,700 homes' electricityhigh
Beinneun£1.2ma year of 4,700 homes' electricityhigh
Beinneun Windfarm Extension£330ka year of 1,300 homes' electricityhigh

What this page does not show

The switch-off figure covers the big wind farms on the national grid only; smaller farms on the local grid are switched off invisibly, so it is a floor. Offshore wind is counted nationally, never per seat. The planning database can run a quarter behind reality.

Electricity does not travel from a particular project to particular houses. Everything generated goes into the national grid and everyone draws from that shared pool, so "enough for X homes" is a way of sizing the electricity — not a claim that these homes would be powered by this site. Battery storage is counted separately from generation: it moves power in time rather than making it.

Planning statuses come from the government's planning database (REPD), which records what was decided and when, but not why. Where a project was refused we say so and name the authority; for the reasons, look up the planning reference on that council's own register. How to check any figure on this page →

Read the full method, including everything we cannot see →