Hyndburn has 12 MW of clean power (mostly onshore wind) approved and still not built: enough to supply a year's electricity to 8,600 homes. When the wires are too full to carry the power, Britain pays wind farms to switch off instead. No wind farm here is paid that way — almost all of it goes to wind farms in Scotland. That cost is shared across every bill in Britain, so households here pay for it too: about £92 a year per household, £3.7m across the constituency's 39,738 homes. There is also 24 MW of wind running here on the local network. If that gets switched off, no national record shows it.

Ranks 217 of 650 for clean power approved and not built.

What is stuck, and why

Project and developerTechSizeWhy it is stuck
Knuzden Moss Farm, Oswaldtwistle - Battery Energy StRoot Power (North) Limited Battery
60 MW
Approved less than a year ago — nothing has happened sinceWho can move it: the developer and the network company
Ramsclough Farm, Haslingden Old Road - Solar FarmAbei Energy Limited Solar 9,600 homes
26 MW
Applied in 2026, still waiting for a decisionWho can move it: Hyndburn Council
Hyndburn Wind Farm ExtensionEnergiekontor UK Onshore wind 7,200 homes
8.2 MW
Approved 11 years ago — nothing has happened sinceWho can move it: the developer and the network company