| Site | Technology | Enough for | Capacity | Approved | Waiting |
|---|---|---|---|---|---|
| Chamber House | Solar Photovoltaics | 1,400 homes | 4.0 MW | 2020-08 | 6.0 yrs |
| Tesco Distribution Centre, Stakehill Industrial Estate - Solar Panels | Solar Photovoltaics | 400 homes | 1.0 MW | 2024-04 | 2.3 yrs |
| David Lloyd Health Club, Heywood Old Road - Solar Panel | Solar Photovoltaics | 200 homes | 0.6 MW | 2023-11 | 2.7 yrs |
| Norden Community School - Solar PV Systems | Solar Photovoltaics | 100 homes | 0.2 MW | 2021-08 | 4.9 yrs |
| Heywood Sports Village - Solar Panels | Solar Photovoltaics | 100 homes | 0.1 MW | 2021-08 | 5.0 yrs |
Plus 4 more approved within the last two years.
Batteries
| Site | Size | Status | While discharging |
|---|---|---|---|
| The Rake, Lower Jowkin Lane - Battery Energy Storage | 57 MW | approved, not built 2024 | could supply ≈200,000 homes |
| Astra Centre, Royal Barn Road - Energy Storage | 40 MW | being built 2021 | could supply ≈140,000 homes |
| Gipsy Lane | 20 MW | being built 2020 | could supply ≈70,000 homes |
What this page does not show
Smaller wind farms on the local grid are also switched off; national data does not show it, so the £ figure here is a floor, not a zero. Offshore wind is counted nationally, never per seat. The planning database can run a quarter behind reality.
Electricity does not travel from a particular project to particular houses. Everything generated goes into the national grid and everyone draws from that shared pool, so "enough for X homes" is a way of sizing the electricity — not a claim that these homes would be powered by this site. Battery storage is counted separately from generation: it moves power in time rather than making it.
Planning statuses come from the government's planning database (REPD), which records what was decided and when, but not why. Where a project was refused we say so and name the authority; for the reasons, look up the planning reference on that council's own register. How to check any figure on this page →
What has Mrs Elsie Blundell said about the grid in Parliament? Search Hansard →