No.112 of 650 · approved, not built MP: Sir Roger Gale (Conservative) England

Herne Bay and Sandwich

Herne Bay and Sandwich has 62 MW of clean power (all solar) approved and still not built: enough to supply a year's electricity to 23,000 homes. Britain's grid bottlenecks still add to bills here: about £116 a year per household, £5.0m across the constituency's 43,337 homes.

Not visible
here
No big wind farm on the national grid is mapped to this constituency, so no switch-off payments show here in national data. Smaller wind farms on the local grid can still be paid to switch off — invisibly. The £ figure for this seat is a floor, not a zero.
62 MW
of clean power — all solar — approved and still not built, enough to supply a year's electricity to 23,000 homes. Approved at least two years ago; waiting on the grid, not on planning. That is 0.5× the renewable capacity actually running here.
5 projects · planning database (REPD), July 2026 · how we worked this out
£5.0m
is what the grid gap costs this constituency's 43,337 households in a year between them — £116 each, about 65 days of one home's electricity.
The £116 per household is a national figure — identical in every GB seat. Only the seat total varies, with the number of households · NESO · how we worked this out

The waiting list

5 of 5 waiting projects · years since approval
Richborough Solar Farm - Solar Farm 30 MW
4.5 YRS
hanet Earth, Barrow Man Road - Solar Panel Array 1 MW
4.1 YRS
Watson Yard, Monkton - Solar PV Panels 0.2 MW
3.7 YRS
Richborough Energy Park, Ramsgate Road - Solar Panels 1 MW
3.1 YRS
Hengrove Farm, Shottendane Road - Solar Farm 30 MW
2.2 YRS

Every approved, unbuilt project

approved 24+ months ago, still not generating · planning database, July 2026
SiteTechnologyEnough forCapacityApprovedWaiting
Richborough Solar Farm - Solar FarmTo The S/O River Stour, Ramsgate Road, SandwichSolar Photovoltaics11,000 homes30.0 MW2022-054.5 yrs
Hengrove Farm, Shottendane Road - Solar FarmE And W/O Hengrove Farm, Shottendane Road, MargateSolar Photovoltaics11,000 homes30.0 MW2024-082.2 yrs
hanet Earth, Barrow Man Road - Solar Panel ArrayThanet Earth Barrow Man Road BirchingtonSolar Photovoltaics400 homes1.0 MW2022-104.1 yrs
Richborough Energy Park, Ramsgate Road - Solar PanelsRichborough Energy Park, Sandwich Road, SandwichSolar Photovoltaics400 homes1.0 MW2023-093.1 yrs
Watson Yard, Monkton - Solar PV PanelsUnit 1, Watson Yard, Monkton, RamsgateSolar Photovoltaics100 homes0.2 MW2023-023.7 yrs

Plus 7 more approved within the last two years.

Batteries

projects of 10 MW and above · planning database, July 2026 · what batteries do →
SiteSizeStatusWhile discharging
Richborough Energy Park - Phase 3 (Sheaf)249 MWbeing built 2022could supply ≈872,000 homes
Woodlands Farm, Calcott Hill - Battery Energy Storage228 MWapproved, not built 2026could supply ≈797,000 homes
Richborough Energy Park - Phase 250 MWoperating 2021could supply ≈176,000 homes
Owls Hatch Road, Thanet Way - Battery Energy Storage Facility50 MWapproved, not built 2025could supply ≈175,000 homes
Richborough Energy Park50 MWoperating 2021could supply ≈175,000 homes
Harrington Franklin, Richborough Energy Park - Battery Storage50 MWbeing built 2022could supply ≈175,000 homes
Ebbsfleet Lane - Battery Storage System50 MWapproved, not built 2026could supply ≈175,000 homes
Wharf Road, Discovery Park - Battery Energy Storage10 MWapproved, not built 2024could supply ≈35,000 homes

What this page does not show

Smaller wind farms on the local grid are also switched off; national data does not show it, so the £ figure here is a floor, not a zero. Offshore wind is counted nationally, never per seat. The planning database can run a quarter behind reality.

Electricity does not travel from a particular project to particular houses. Everything generated goes into the national grid and everyone draws from that shared pool, so "enough for X homes" is a way of sizing the electricity — not a claim that these homes would be powered by this site. Battery storage is counted separately from generation: it moves power in time rather than making it.

Planning statuses come from the government's planning database (REPD), which records what was decided and when, but not why. Where a project was refused we say so and name the authority; for the reasons, look up the planning reference on that council's own register. How to check any figure on this page →