Henley and Thame
Henley and Thame has 151 MW of clean power (all solar) approved and still not built: enough to supply a year's electricity to 55,000 homes. Britain's grid bottlenecks still add to bills here: about £92 a year per household, £3.6m across the constituency's 39,348 homes. A 100 MW battery was refused planning here in 2025; while discharging it could have supplied about 350,000 homes.
here
The waiting list
Every approved, unbuilt project
| Site | Technology | Enough for | Capacity | Approved | Waiting |
|---|---|---|---|---|---|
| Cornwell Solar Farm | Solar Photovoltaics | 18,000 homes | 49.9 MW | 2021-10 | 4.8 yrs |
| Harlesford Solar Farm | Solar Photovoltaics | 18,000 homes | 49.9 MW | 2021-12 | 4.6 yrs |
| Dodwells Solar Farm | Solar Photovoltaics | 18,000 homes | 49.9 MW | 2023-08 | 2.9 yrs |
| Icknield Road, Ipsden - Solar Array & Battery Storage | Solar Photovoltaics | 500 homes | 1.4 MW | 2022-12 | 3.6 yrs |
| Lucy Switchgear, Howland Road - Solar Panels | Solar Photovoltaics | 100 homes | 0.3 MW | 2023-12 | 2.6 yrs |
| Benson Lane, Crowmarsh - Solar Array | Solar Photovoltaics | — | — MW | 2023-04 | 3.3 yrs |
Plus 3 more approved within the last two years.
Batteries
| Site | Size | Status | While discharging |
|---|---|---|---|
| Lower road, Garsington - Energy Storage System | 100 MW | refused 2025 | could supply ≈350,000 homes |
| Cowley electricity sub-station | 50 MW | 2019 | could supply ≈175,000 homes |
What this page does not show
Smaller wind farms on the local grid are also switched off; national data does not show it, so the £ figure here is a floor, not a zero. Offshore wind is counted nationally, never per seat. The planning database can run a quarter behind reality.
Electricity does not travel from a particular project to particular houses. Everything generated goes into the national grid and everyone draws from that shared pool, so "enough for X homes" is a way of sizing the electricity — not a claim that these homes would be powered by this site. Battery storage is counted separately from generation: it moves power in time rather than making it.
Planning statuses come from the government's planning database (REPD), which records what was decided and when, but not why. Where a project was refused we say so and name the authority; for the reasons, look up the planning reference on that council's own register. How to check any figure on this page →
What has Freddie van Mierlo said about the grid in Parliament? Search Hansard →