CONSTITUENCY BRIEFING · ENERGYMAP.APP

Hartlepool

MP: Mr Jonathan Brash (Labour) England Data to July 2026

Hartlepool has 51 MW of clean power (all solar) approved and still not built: enough to supply a year's electricity to 19,000 homes. When the wires are too full to carry the power, Britain pays wind farms to switch off instead. No wind farm here is paid that way — almost all of it goes to wind farms in Scotland. That cost is shared across every bill in Britain, so households here pay for it too: about £92 a year per household, £3.8m across the constituency's 40,930 homes.

Ranks 126 of 650 for clean power approved and not built.

What is stuck, and why

Project and developerTechSizeWhy it is stuck
Worset Lane - Battery Energy Storage SystemClearstone Energy Battery
200 MW
Approved 4 years ago — nothing has happened sinceWho can move it: the developer and the network company
Whelley Hill Farm, Worset Lane - Battery Energy StorReliance Energy Limited Battery
50 MW
Approved 3 years ago — nothing has happened sinceWho can move it: the developer and the network company
Worset Lane - Solar FarmCanadian Solar UK Solar 18,000 homes
50 MW
Approved 5 years ago — nothing has happened sinceWho can move it: the developer and the network company

What else is in the briefing

No account needed for any of this: the full seat page with every figure, the method and sources, and this constituency's raw data. The account covers the packaged briefing only.