No.357 of 650 · approved, not built MP: Dame Caroline Dinenage (Conservative) England

Gosport

Gosport has 2 MW of clean power (all solar) approved and still not built: enough to supply a year's electricity to 700 homes. Britain's grid bottlenecks still add to bills here: about £116 a year per household, £4.9m across the constituency's 41,985 homes.

Not visible
here
No big wind farm on the national grid is mapped to this constituency, so no switch-off payments show here in national data. Smaller wind farms on the local grid can still be paid to switch off — invisibly. The £ figure for this seat is a floor, not a zero.
2 MW
of clean power — all solar — approved and still not built, enough to supply a year's electricity to 700 homes. Approved at least two years ago; waiting on the grid, not on planning. That is 0.1× the renewable capacity actually running here.
5 projects · planning database (REPD), July 2026 · how we worked this out
£4.9m
is what the grid gap costs this constituency's 41,985 households in a year between them — £116 each, about 65 days of one home's electricity.
The £116 per household is a national figure — identical in every GB seat. Only the seat total varies, with the number of households · NESO · how we worked this out

The waiting list

5 of 5 waiting projects · years since approval
Walpole Road - Solar Panels 0.2 MW
3.9 YRS
Qinetiq Haslar, Haslar Road - Solar Panels 0.7 MW
3.4 YRS
Immigration Removal Centre, Dolphin Way - Solar panels 0.2 MW
2.6 YRS
Range Superstore, Gunners Way - Solar panels 0.4 MW
2.2 YRS
Range Superstore, Gunners Way - Solar Panels 0.4 MW
2.2 YRS

Every approved, unbuilt project

approved 24+ months ago, still not generating · planning database, July 2026
SiteTechnologyEnough forCapacityApprovedWaiting
Qinetiq Haslar, Haslar Road - Solar PanelsQinetiq Haslar Haslar RoadSolar Photovoltaics300 homes0.7 MW2023-063.4 yrs
Range Superstore, Gunners Way - Solar panelsRange Superstore, Gunners Way, GosportSolar Photovoltaics200 homes0.4 MW2024-082.2 yrs
Range Superstore, Gunners Way - Solar PanelsRange Superstore Gunners WaySolar Photovoltaics200 homes0.4 MW2024-082.2 yrs
Immigration Removal Centre, Dolphin Way - Solar panelsImmigration Removal Centre, 2 Dolphin Way, GosportSolar Photovoltaics100 homes0.2 MW2024-032.6 yrs
Walpole Road - Solar Panels15 Walpole Road, GosportSolar Photovoltaics100 homes0.2 MW2022-123.9 yrs

Batteries

projects of 10 MW and above · planning database, July 2026 · what batteries do →
SiteSizeStatusWhile discharging
Newlands Farm Battery Storage Facility Phase 240 MWoperating 2021could supply ≈140,000 homes
Tanners Lane - Battery Energy Storage Facility (Phase One)40 MWapproved, not built 2019could supply ≈140,000 homes

What this page does not show

Smaller wind farms on the local grid are also switched off; national data does not show it, so the £ figure here is a floor, not a zero. Offshore wind is counted nationally, never per seat. The planning database can run a quarter behind reality.

Electricity does not travel from a particular project to particular houses. Everything generated goes into the national grid and everyone draws from that shared pool, so "enough for X homes" is a way of sizing the electricity — not a claim that these homes would be powered by this site. Battery storage is counted separately from generation: it moves power in time rather than making it.

Planning statuses come from the government's planning database (REPD), which records what was decided and when, but not why. Where a project was refused we say so and name the authority; for the reasons, look up the planning reference on that council's own register. How to check any figure on this page →

Read the full method, including everything we cannot see →

What has Dame Caroline Dinenage said about the grid in Parliament? Search Hansard →

See the full league table Data (JSON)