No.59 of 650 · approved, not built MP: Harriet Cross (Conservative) Scotland

Gordon and Buchan

Gordon and Buchan was paid £120k last year to switch off its wind farms, because the wires south were full. That would cover every local household's electricity for 39 hours. A further 107 MW of approved clean power (mostly onshore wind) is still waiting to be built here: enough to supply a year's electricity to 83,000 homes. A 300 MW battery approved at Kintore Battery Energy Storage Project in 2025 would store power that is currently wasted; it has not been built. A 50 MW battery was refused planning here in 2026; while discharging it could have supplied about 175,000 homes.

£120k
paid to wind farms here not to generate in the last year — enough to pay for every household here's electricity for 39 hours.
Elexon balancing data, 12 months to 31 Jul 2026 · No.19 of 19 seats with visible switch-offs · how we worked this out
107 MW
of clean power — mostly onshore wind — approved and still not built, enough to supply a year's electricity to 83,000 homes — 2 times every household in this constituency. Approved at least two years ago; waiting on the grid, not on planning. That is 0.6× the renewable capacity actually running here.
7 projects · 85 MW onshore wind, 22 MW solar · planning database (REPD), July 2026 · how we worked this out
£3.7m
is what the grid gap costs this constituency's 40,108 households in a year between them — £92 each, about 51 days of one home's electricity.
The £92 per household is a national figure — identical in every GB seat. Only the seat total varies, with the number of households · NESO · how we worked this out

The waiting list

6 of 7 waiting projects · years since approval
Land to the north west of Hill of Petty 3.6 MW
10.5 YRS
Kincraig - Solar Farm and battery storage system 21 MW
3.8 YRS
Oeg offshore, Tofthills Way - Solar Panels 0.2 MW
3.1 YRS
Clashindarroch 2 77 MW
3.0 YRS
Meikleton of Ardonald 1 MW
2.8 YRS
Cairnbrogie Farm, Oldmeldrum - Wind Farm 3.6 MW
2.6 YRS

Every approved, unbuilt project

approved 24+ months ago, still not generating · planning database, July 2026
SiteTechnologyEnough forCapacityApprovedWaiting
Clashindarroch 2Wind Onshore67,000 homes77.0 MW2023-083.0 yrs
Kincraig - Solar Farm and battery storage systemSolar Photovoltaics7,600 homes21.0 MW2022-103.8 yrs
Land to the north west of Hill of PettyWind Onshore3,100 homes3.6 MW2016-0210.5 yrs
Cairnbrogie Farm, Oldmeldrum - Wind FarmWind Onshore3,100 homes3.6 MW2023-122.6 yrs
Meikleton of ArdonaldWind Onshore900 homes1.0 MW2023-102.8 yrs
Donald Russell, Carnie Road - Solar PV PanelsSolar Photovoltaics300 homes0.8 MW2024-012.5 yrs
Oeg offshore, Tofthills Way - Solar PanelsSolar Photovoltaics100 homes0.2 MW2023-063.1 yrs

Plus 3 more approved within the last two years.

Batteries

projects of 10 MW and above · planning database, July 2026 · what batteries do →
SiteSizeStatusWhile discharging
Abbotshaugh Battery Storage500 MWcould supply ≈1,752,000 homes
Rothienorman, Middleton of Blackhills - BESS500 MWcould supply ≈1,752,000 homes
Kintore Battery Energy Storage Project300 MWapproved, not built 2025could supply ≈1,051,000 homes
Womblehill Farm, Kintore - Battery Energy Storage System200 MWcould supply ≈701,000 homes
Kinmuck Battery Energy Storage105 MWapproved, not built 2025could supply ≈368,000 homes
Clashindarroch Wind Farm Extension50 MWapproved, not built 2025could supply ≈175,000 homes
Fordtown Energy Storage50 MWapproved, not built 2021could supply ≈175,000 homes
Rothienorman - Battery Storage50 MWapproved, not built 2022could supply ≈175,000 homes
South Leylodge Farmhouse, Kintore - Battery Energy Storage System50 MWapproved, not built 2023could supply ≈175,000 homes
Overhill Farm, Rothienorman - Battery Energy Storage50 MWbeing built 2023could supply ≈175,000 homes
Kintore Substation, Leylodge - Battery Energy Storage50 MWapproved, not built 2024could supply ≈175,000 homes
Fairfield - Battery Energy Storage System50 MWrefused 2026could supply ≈175,000 homes

Wind farms paid to switch off

12 months to 31 Jul 2026 · mapping confidence shown · mapping file
SitePaid, 12 monthsEnergy lostConfidence
Glens of Foudland£120ka year of 400 homes' electricityhigh

What this page does not show

The switch-off figure covers the big wind farms on the national grid only; smaller farms on the local grid are switched off invisibly, so it is a floor. Offshore wind is counted nationally, never per seat. The planning database can run a quarter behind reality.

Electricity does not travel from a particular project to particular houses. Everything generated goes into the national grid and everyone draws from that shared pool, so "enough for X homes" is a way of sizing the electricity — not a claim that these homes would be powered by this site. Battery storage is counted separately from generation: it moves power in time rather than making it.

Planning statuses come from the government's planning database (REPD), which records what was decided and when, but not why. Where a project was refused we say so and name the authority; for the reasons, look up the planning reference on that council's own register. How to check any figure on this page →

Read the full method, including everything we cannot see →

What has Harriet Cross said about the grid in Parliament? Search Hansard →