No.253 of 650 · approved, not built MP: Alex McIntyre (Labour) England

Gloucester

Gloucester has 7.2 MW of clean power (all solar) approved and still not built: enough to supply a year's electricity to 2,600 homes. Britain's grid bottlenecks still add to bills here: about £116 a year per household, £5.6m across the constituency's 48,790 homes.

Not visible
here
No big wind farm on the national grid is mapped to this constituency, so no switch-off payments show here in national data. Smaller wind farms on the local grid can still be paid to switch off — invisibly. The £ figure for this seat is a floor, not a zero.
7.2 MW
of clean power — all solar — approved and still not built, enough to supply a year's electricity to 2,600 homes. Approved at least two years ago; waiting on the grid, not on planning.
10 projects · planning database (REPD), July 2026 · how we worked this out
£5.6m
is what the grid gap costs this constituency's 48,790 households in a year between them — £116 each, about 65 days of one home's electricity.
The £116 per household is a national figure — identical in every GB seat. Only the seat total varies, with the number of households · NESO · how we worked this out

The waiting list

6 of 10 waiting projects · years since approval
Quayside House - Solar Panels
5.5 YRS
Gloucester Academy 0.2 MW
5.5 YRS
Gloucester Royal Hospital - Solar Panels 0.2 MW
5.4 YRS
Arlingham House, Quedgeley - Solar Panels 0.3 MW
5.0 YRS
Gloucestershire College - Photovoltaic Solar Panels 0.6 MW
4.5 YRS
Francis And Lewis International, Waterwells Drive - Solar Panels 0.2 MW
4.0 YRS

Every approved, unbuilt project

approved 24+ months ago, still not generating · planning database, July 2026
SiteTechnologyEnough forCapacityApprovedWaiting
Unilever UK, Corinium Avenue - Solar PanelsUnilever UK Corinium AvenueSolar Photovoltaics1,300 homes3.5 MW2024-052.5 yrs
Hempsted Lane - Solar ArrayHempsted Waste Management Site, GloucesterSolar Photovoltaics700 homes2.0 MW2023-083.2 yrs
Gloucestershire College - Photovoltaic Solar PanelsGloucestershire College, Llanthony Road, GloucesterSolar Photovoltaics200 homes0.6 MW2022-054.5 yrs
Arlingham House, Quedgeley - Solar PanelsArlingham House, Falcon Close, Quedgeley, GloucesterSolar Photovoltaics100 homes0.3 MW2021-115.0 yrs
Tenpin Centre, Severn Barnwood Link Road - Solar PanelsTenpin Centre Severn Barnwood Link RoadSolar Photovoltaics100 homes0.2 MW2023-103.1 yrs
Gloucester AcademyPainswick Road, Gloucester, GloucestershireSolar Photovoltaics100 homes0.2 MW2021-055.5 yrs
Francis And Lewis International, Waterwells Drive - Solar PanelsFrancis And Lewis International Waterwells DriveSolar Photovoltaics100 homes0.2 MW2022-114.0 yrs
Gloucester Royal Hospital - Solar PanelsGloucester Royal Hospital, Great Western Road, GloucesterSolar Photovoltaics100 homes0.2 MW2021-075.4 yrs
Quayside House - Solar PanelsSite Of The Former Quayside House Quay Street Gloucester GloucestershireSolar Photovoltaics—— MW2021-055.5 yrs
Morrisons Supermarket, Glevum Way - Solar PanelsMorrisons Supermarket, Glevum Way, GloucesterSolar Photovoltaics—— MW2023-103.1 yrs

Plus 5 more approved within the last two years.

Batteries

projects of 10 MW and above · planning database, July 2026 · what batteries do →
SiteSizeStatusWhile discharging
Sudmeadow Road, Hempsted - Battery Energy Storage System50 MWapproved, not built 2025could supply ≈175,000 homes

What this page does not show

Smaller wind farms on the local grid are also switched off; national data does not show it, so the £ figure here is a floor, not a zero. Offshore wind is counted nationally, never per seat. The planning database can run a quarter behind reality.

Electricity does not travel from a particular project to particular houses. Everything generated goes into the national grid and everyone draws from that shared pool, so "enough for X homes" is a way of sizing the electricity — not a claim that these homes would be powered by this site. Battery storage is counted separately from generation: it moves power in time rather than making it.

Planning statuses come from the government's planning database (REPD), which records what was decided and when, but not why. Where a project was refused we say so and name the authority; for the reasons, look up the planning reference on that council's own register. How to check any figure on this page →

Read the full method, including everything we cannot see →