CONSTITUENCY BRIEFING · ENERGYMAP.APP

Fylde

MP: Mr Andrew Snowden (Conservative) England Data to July 2026

Fylde has 26 MW of clean power (all solar) approved and still not built: enough to supply a year's electricity to 9,500 homes. Britain's grid bottlenecks still add to bills here: about £92 a year per household, £4.1m across the constituency's 44,588 homes.

Ranks 179 of 650 for clean power approved and not built.

What is stuck, and why

Project and developerTechSizeWhy it is stuck
Lowland Farm, Peel Road - Battery Energy Storage FacMax Design Consultancy Battery
100 MW
Waiting 1.1 years for a planning decisionWho can move it: Fylde Council
Clifton Marsh Farm, Preston New Road - Solar FarmVattenfall Solar 18,000 homes
50 MW
Waiting 2.0 years for a planning decisionWho can move it: Fylde Council
Smithy Lane, Staining - Solar PV Panels & BESSBoom Power Limited Solar 15,000 homes
40 MW
Applied in 2026, still waiting for a decisionWho can move it: Fylde Council

What else is in the briefing

No account needed for any of this: the full seat page with every figure, the method and sources, and this constituency's raw data. The account covers the packaged briefing only.