Filton and Bradley Stoke has 8.7 MW of clean power (all solar) approved and still not built: enough to supply a year's electricity to 3,100 homes. Britain's grid bottlenecks still add to bills here: about £92 a year per household, £3.9m across the constituency's 42,325 homes.
here
The waiting list
Every approved, unbuilt project
| Site | Technology | Enough for | Capacity | Approved | Waiting |
|---|---|---|---|---|---|
| Airbus UK Industrial Complex - Solar panels | Solar Photovoltaics | 1,100 homes | 3.1 MW | 2024-04 | 2.3 yrs |
| Folly Brook Road, Emersons Green - Solar Panels | Solar Photovoltaics | 400 homes | 1.0 MW | 2022-10 | 3.8 yrs |
| Abbey Wood Retail Park, Filton - Solar Panels | Solar Photovoltaics | 300 homes | 0.9 MW | 2023-10 | 2.8 yrs |
| Iaaps, Newlands Lane - Solar Panels & Hydrogen Storage | Solar Photovoltaics | 300 homes | 0.7 MW | 2022-10 | 3.8 yrs |
| Sainsburys Supermarkets Limited, The Village - Solar Panels | Solar Photovoltaics | 200 homes | 0.5 MW | 2024-03 | 2.4 yrs |
| DPD Bristol, Emersons Green - Solar Panels | Solar Photovoltaics | 200 homes | 0.5 MW | 2024-03 | 2.4 yrs |
| Cribbs Causeway, Merlin Road - Solar Panels | Solar Photovoltaics | 200 homes | 0.4 MW | 2022-10 | 3.8 yrs |
| Bradley Stoke Leisure Centre, Fiddlers Wood Lane - Solar Panels | Solar Photovoltaics | 100 homes | 0.4 MW | 2023-06 | 3.1 yrs |
| Abbey Wood Retail Park, Station Road - Solar Panels | Solar Photovoltaics | 100 homes | 0.3 MW | 2023-10 | 2.8 yrs |
| David Lloyd Leisure Club, Willowherb Road - Solar Panels | Solar Photovoltaics | 100 homes | 0.3 MW | 2023-09 | 2.9 yrs |
| Emerald Park, Emersons Green - Solar Panels | Solar Photovoltaics | 100 homes | 0.2 MW | 2023-05 | 3.2 yrs |
| Dunelm, Centaurus Road - Solar Panels | Solar Photovoltaics | 100 homes | 0.2 MW | 2023-05 | 3.2 yrs |
| Carshop Bristol, Bolingbroke Way - Solar Panels | Solar Photovoltaics | 100 homes | 0.1 MW | 2023-05 | 3.2 yrs |
| Morrison Supermarket, Lysander Road - Solar Panels | Solar Photovoltaics | — | — MW | 2022-12 | 3.7 yrs |
Plus 2 more approved within the last two years.
What this page does not show
Smaller wind farms on the local grid are also switched off; national data does not show it, so the £ figure here is a floor, not a zero. Offshore wind is counted nationally, never per seat. The planning database can run a quarter behind reality.
Electricity does not travel from a particular project to particular houses. Everything generated goes into the national grid and everyone draws from that shared pool, so "enough for X homes" is a way of sizing the electricity — not a claim that these homes would be powered by this site. Battery storage is counted separately from generation: it moves power in time rather than making it.
Planning statuses come from the government's planning database (REPD), which records what was decided and when, but not why. Where a project was refused we say so and name the authority; for the reasons, look up the planning reference on that council's own register. How to check any figure on this page →
What has Claire Hazelgrove said about the grid in Parliament? Search Hansard →