Edinburgh West
Edinburgh West has 12 MW of clean power (all solar) approved and still not built: enough to supply a year's electricity to 4,500 homes. Britain's grid bottlenecks still add to bills here: about £92 a year per household, £4.0m across the constituency's 44,012 homes.
here
The waiting list
Every approved, unbuilt project
| Site | Technology | Enough for | Capacity | Approved | Waiting |
|---|---|---|---|---|---|
| Main Terminal 1 Edinburgh Airport - Solar Farm | Solar Photovoltaics | 3,300 homes | 9.0 MW | 2021-10 | 4.8 yrs |
| Chariot Drive, Newbridge Road - Solar Panels | Solar Photovoltaics | 400 homes | 1.2 MW | 2022-11 | 3.7 yrs |
| Newbridge - Ground mounted solar Pv panels | Solar Photovoltaics | 400 homes | 1.0 MW | 2022-08 | 4.0 yrs |
| Sainsburys, Craigleith Road - Solar Array | Solar Photovoltaics | 200 homes | 0.7 MW | 2024-02 | 2.5 yrs |
| Queen Anne Drive - Roof Mounted Solar PV Panels | Solar Photovoltaics | 200 homes | 0.6 MW | 2023-10 | 2.8 yrs |
Plus 1 more approved within the last two years.
What this page does not show
Smaller wind farms on the local grid are also switched off; national data does not show it, so the £ figure here is a floor, not a zero. Offshore wind is counted nationally, never per seat. The planning database can run a quarter behind reality.
Electricity does not travel from a particular project to particular houses. Everything generated goes into the national grid and everyone draws from that shared pool, so "enough for X homes" is a way of sizing the electricity — not a claim that these homes would be powered by this site. Battery storage is counted separately from generation: it moves power in time rather than making it.
Planning statuses come from the government's planning database (REPD), which records what was decided and when, but not why. Where a project was refused we say so and name the authority; for the reasons, look up the planning reference on that council's own register. How to check any figure on this page →
What has Christine Jardine said about the grid in Parliament? Search Hansard →