East Surrey
East Surrey has 11 MW of clean power (all solar) approved and still not built: enough to supply a year's electricity to 4,000 homes. Britain's grid bottlenecks still add to bills here: about £92 a year per household, £3.7m across the constituency's 39,976 homes.
here
The waiting list
Every approved, unbuilt project
| Site | Technology | Enough for | Capacity | Approved | Waiting |
|---|---|---|---|---|---|
| Gaywood Solar Farm | Solar Photovoltaics | 3,900 homes | 10.7 MW | 2024-01 | 2.5 yrs |
| East Hill - Solar Panels | Solar Photovoltaics | 100 homes | 0.2 MW | 2023-06 | 3.1 yrs |
| Sewage Disposal Works, Eden Vale - Ground Mounted Solar Panels | Solar Photovoltaics | 100 homes | 0.2 MW | 2023-06 | 3.1 yrs |
Batteries
| Site | Size | Status | While discharging |
|---|---|---|---|
| Caterham Bypass - Battery Energy Storage | 12 MW | approved, not built 2024 | could supply ≈42,000 homes |
What this page does not show
Smaller wind farms on the local grid are also switched off; national data does not show it, so the £ figure here is a floor, not a zero. Offshore wind is counted nationally, never per seat. The planning database can run a quarter behind reality.
Electricity does not travel from a particular project to particular houses. Everything generated goes into the national grid and everyone draws from that shared pool, so "enough for X homes" is a way of sizing the electricity — not a claim that these homes would be powered by this site. Battery storage is counted separately from generation: it moves power in time rather than making it.
Planning statuses come from the government's planning database (REPD), which records what was decided and when, but not why. Where a project was refused we say so and name the authority; for the reasons, look up the planning reference on that council's own register. How to check any figure on this page →