No.115 of 650 · approved, not built MP: Joani Reid (Labour) Scotland

East Kilbride and Strathaven

East Kilbride and Strathaven was paid £3.2m last year to switch off its wind farms, because the wires south were full. That would cover every local household's electricity for 42 days. A further 58 MW of approved clean power (almost all onshore wind) is still waiting to be built here: enough to supply a year's electricity to 50,000 homes. A 55 MW battery approved at East Rogerton Cottage, Markethill Road in 2026 would store power that is currently wasted; it has not been built. A 40 MW battery was refused planning here in 2025; while discharging it could have supplied about 140,000 homes.

£3.2m
paid to wind farms here not to generate in the last year — enough to pay for every household here's electricity for 42 days.
Elexon balancing data, 2025-11-01 to 2026-10-31 · No.12 of 19 seats with visible switch-offs · how we worked this out
58 MW
of clean power — almost all onshore wind — approved and still not built, enough to supply a year's electricity to 50,000 homes — about as many homes as this constituency has. Approved at least two years ago; waiting on the grid, not on planning. That is 0.2× the renewable capacity actually running here.
7 projects · 56 MW onshore wind, 1.6 MW solar · planning database (REPD), July 2026 · how we worked this out
£4.9m
is what the grid gap costs this constituency's 42,774 households in a year between them — £116 each, about 65 days of one home's electricity.
The £116 per household is a national figure — identical in every GB seat. Only the seat total varies, with the number of households · NESO · how we worked this out

The waiting list

6 of 7 waiting projects · years since approval
Police Training And Recruitment Centre, Eaglesham Road - Solar PV Panels 0.4 MW
3.7 YRS
Tennant Avenue College, East Kilbride - Solar Panels 0.9 MW
3.5 YRS
Manson Place, Kelvin Industrial Estate - Solar Panels 0.2 MW
3.4 YRS
Reynolds Building, Scottish Enterprise Technology Park- Solar Panles 0.2 MW
3.2 YRS
Mill Rig Wind Farm 36 MW
2.6 YRS
Logoch Windfarm, East Kilbride - Wind turbine 0.5 MW
2.6 YRS

Every approved, unbuilt project

approved 24+ months ago, still not generating · planning database, July 2026
SiteTechnologyEnough forCapacityApprovedWaiting
Mill Rig Wind FarmMill Rig Wind Farm, Nw/O Muirkirk And Se/O Darvel, StrathavenWind Onshore31,000 homes36.0 MW2024-032.6 yrs
Low Drumclog Farm, Drumclog - 3 Wind TurbinesLow Drumclog Farm C136 Drumclog Highway Drumclog StrathavenWind Onshore17,000 homes20.0 MW2024-102.0 yrs
Tennant Avenue College, East Kilbride - Solar Panels1 Tennant Avenue College Milton Industrial Estate East KilbrideSolar Photovoltaics300 homes0.9 MW2023-053.5 yrs
Logoch Windfarm, East Kilbride - Wind turbineLogoch Windfarm Ardochrig Highway East Kilbride GlasgowWind Onshore400 homes0.5 MW2024-032.6 yrs
Police Training And Recruitment Centre, Eaglesham Road - Solar PV PanelsPolice Training And Recruitment Centre Eaglesham Road JacktonSolar Photovoltaics100 homes0.4 MW2023-033.7 yrs
Manson Place, Kelvin Industrial Estate - Solar Panels1-4 Manson Place, Kelvin Industrial Estate, East Kilbride, GlasgowSolar Photovoltaics100 homes0.2 MW2023-063.4 yrs
Reynolds Building, Scottish Enterprise Technology Park- Solar PanlesReynolds Building, Reynolds Avenue, Scottish Enterprise Technology Park, East Kilbride, GlasgowSolar Photovoltaics100 homes0.2 MW2023-083.2 yrs

Plus 4 more approved within the last two years.

Batteries

projects of 10 MW and above · planning database, July 2026 · what batteries do →
SiteSizeStatusWhile discharging
East Rogerton Cottage, Markethill Road - Battery Storage Facility55 MWapproved, not built 2026could supply ≈193,000 homes
Whitelee Wind Farm Battery Storage Extension50 MWoperating 2019could supply ≈175,000 homes
Gilbertfield Farm, Gilbertfield Road - Battery Storage Facility40 MWrefused 2025could supply ≈140,000 homes
Langlands Gate, East Kilbride - Battery Energy Storage30 MWapproved, not built 2026could supply ≈105,000 homes
Crutherland Farm, Crutherland Highway - Battery Energy Storage23 MWrefused 2024could supply ≈80,000 homes

Wind farms paid to switch off

2025-11-01 to 2026-10-31 · mapping confidence shown · mapping file
SitePaid, 12 monthsEnergy lostConfidence
Kype Muir Wind Farm£1.9ma year of 19,000 homes' electricityhigh
Kype Muir Wind Farm Extension£1.4ma year of 19,000 homes' electricityhigh

What this page does not show

The switch-off figure covers the big wind farms on the national grid only; smaller farms on the local grid are switched off invisibly, so it is a floor. Offshore wind is counted nationally, never per seat. The planning database can run a quarter behind reality.

Electricity does not travel from a particular project to particular houses. Everything generated goes into the national grid and everyone draws from that shared pool, so "enough for X homes" is a way of sizing the electricity — not a claim that these homes would be powered by this site. Battery storage is counted separately from generation: it moves power in time rather than making it.

Planning statuses come from the government's planning database (REPD), which records what was decided and when, but not why. Where a project was refused we say so and name the authority; for the reasons, look up the planning reference on that council's own register. How to check any figure on this page →

Read the full method, including everything we cannot see →

What has Joani Reid said about the grid in Parliament? Search Hansard →

See the full league table Data (JSON)