Dwyfor Meirionnydd
Dwyfor Meirionnydd has 1.9 MW of clean power (all solar) approved and still not built: enough to supply a year's electricity to 700 homes. When the wires are too full to carry the power, Britain pays wind farms to switch off instead. No wind farm here is paid that way — almost all of it goes to wind farms in Scotland. That cost is shared across every bill in Britain, so households here pay for it too: about £92 a year per household, £3.9m across the constituency's 42,488 homes. A 100 MW battery was refused planning here in 2026; while discharging it could have supplied about 350,000 homes.
here
The waiting list
Every approved, unbuilt project
| Site | Technology | Enough for | Capacity | Approved | Waiting |
|---|---|---|---|---|---|
| Rehau Plastics, Pencefn Road - Solar Panels | Solar Photovoltaics | 400 homes | 1.0 MW | 2024-03 | 2.4 yrs |
| Tyfos, Pen Y Geulan - Solar Array | Solar Photovoltaics | 200 homes | 0.6 MW | 2023-08 | 3.0 yrs |
| Nanhoron Home Farm, Nanhoron - Solar Panels | Solar Photovoltaics | 100 homes | 0.2 MW | 2022-08 | 4.0 yrs |
Batteries
| Site | Size | Status | While discharging |
|---|---|---|---|
| Tyddyn Forgan, Llanddeiniolen - Energy Storage System | 100 MW | approved, not built 2026 | could supply ≈350,000 homes |
| Seion, Pentir - Battery Energy Storage System | 100 MW | refused 2026 | could supply ≈350,000 homes |
| Pentir Substation, Pentir - Battery Energy Storage | 57 MW | approved, not built 2024 | could supply ≈200,000 homes |
What this page does not show
Smaller wind farms on the local grid are also switched off; national data does not show it, so the £ figure here is a floor, not a zero. Offshore wind is counted nationally, never per seat. The planning database can run a quarter behind reality.
Electricity does not travel from a particular project to particular houses. Everything generated goes into the national grid and everyone draws from that shared pool, so "enough for X homes" is a way of sizing the electricity — not a claim that these homes would be powered by this site. Battery storage is counted separately from generation: it moves power in time rather than making it.
Planning statuses come from the government's planning database (REPD), which records what was decided and when, but not why. Where a project was refused we say so and name the authority; for the reasons, look up the planning reference on that council's own register. How to check any figure on this page →