Dunfermline and Dollar has 36 MW of clean power (almost all solar) approved and still not built: enough to supply a year's electricity to 13,000 homes. When the wires are too full to carry the power, Britain pays wind farms to switch off instead. No wind farm here is paid that way — almost all of it goes to wind farms in Scotland. That cost is shared across every bill in Britain, so households here pay for it too: about £92 a year per household, £3.9m across the constituency's 42,688 homes.
Ranks 164 of 650 for clean power approved and not built.
What is stuck, and why
| Project and developer | Tech | Size | Why it is stuck |
|---|---|---|---|
| Kincardine Grid Services Complex - Energy Storage FaAmp Energy | Battery | 400 MW |
Approved 5 years ago — nothing has happened sinceWho can move it: the developer and the network company |
| Kincardine Battery StorageGresham House Devco Pipeline Limited | Battery | 342 MW |
Approved a year ago — nothing has happened sinceWho can move it: the developer and the network company |
| Nettly Burn Renewable Energy ParkGrupotec Solar UK 4 Ltd | Solar | 29,000 homes 80 MW |
Approved less than a year ago — nothing has happened sinceWho can move it: the developer and the network company |
What else is in the briefing
- All 9 projects, each with its planning reference and the organisation that holds the next decision
- Every approval a project still needs, and which of them the public can see
- What building them would mean here — community payments, business rates and construction work
- How Dunfermline and Dollar compares with its neighbouring constituencies
- Drafted parliamentary questions and letters, filled in with this seat's figures
- 3 story angles for local reporting
- A two-page PDF, and a newsroom edition with the references and who to call