No.100 of 650 · approved, not built MP: Nigel Huddleston (Conservative) England

Droitwich and Evesham

Droitwich and Evesham has 67 MW of clean power (all solar) approved and still not built: enough to supply a year's electricity to 24,000 homes. When the wires are too full to carry the power, Britain pays wind farms to switch off instead. No wind farm here is paid that way — almost all of it goes to wind farms in Scotland. That cost is shared across every bill in Britain, so households here pay for it too: about £92 a year per household, £4.0m across the constituency's 43,897 homes.

Not visible
here
No big wind farm on the national grid is mapped to this constituency, so no switch-off payments show here in national data. Smaller wind farms on the local grid can still be paid to switch off — invisibly. The £ figure for this seat is a floor, not a zero.
67 MW
of clean power — all solar — approved and still not built, enough to supply a year's electricity to 24,000 homes. Approved at least two years ago; waiting on the grid, not on planning. That is 0.5× the renewable capacity actually running here.
10 projects · planning database (REPD), July 2026 · how we worked this out
£4.0m
is what the grid gap costs this constituency's 43,897 households in a year between them — £92 each, about 51 days of one home's electricity.
The £92 per household is a national figure — identical in every GB seat. Only the seat total varies, with the number of households · NESO · how we worked this out

The waiting list

6 of 10 waiting projects · years since approval
Primafruit Limited - Solar Panels
4.8 YRS
Bishampton Solar Farm 30 MW
4.7 YRS
Bramley Drive - Solar Panels 0.2 MW
4.1 YRS
Hyde Farm, Worcester Road - Solar Array 0.1 MW
3.3 YRS
J And J Bannister Evesham, Newtown - Solar Panels 0.2 MW
3.0 YRS
David Lloyd Leisure, Warriors Way - Solar Panels 0.4 MW
2.9 YRS

Every approved, unbuilt project

approved 24+ months ago, still not generating · planning database, July 2026
SiteTechnologyEnough forCapacityApprovedWaiting
Mount Farm, Mount Pleasant - Solar FarmSolar Photovoltaics13,000 homes35.0 MW2024-062.2 yrs
Bishampton Solar FarmSolar Photovoltaics11,000 homes30.0 MW2021-114.7 yrs
David Lloyd Leisure, Warriors Way - Solar PanelsSolar Photovoltaics200 homes0.4 MW2023-092.9 yrs
Clayfield Road, Worcester Six Business Park - Solar PanelsSolar Photovoltaics200 homes0.4 MW2024-072.1 yrs
J And J Bannister Evesham, Newtown - Solar PanelsSolar Photovoltaics100 homes0.2 MW2023-073.0 yrs
Harvey & Brockless Limited, Millennium Way - Solar PanelsSolar Photovoltaics100 homes0.2 MW2024-052.2 yrs
Bramley Drive - Solar PanelsSolar Photovoltaics100 homes0.2 MW2022-064.1 yrs
Woodbury Lane, Norton - Solar PanelsSolar Photovoltaics100 homes0.2 MW2024-042.3 yrs
Hyde Farm, Worcester Road - Solar ArraySolar Photovoltaics100 homes0.1 MW2023-043.3 yrs
Primafruit Limited - Solar PanelsSolar Photovoltaics— MW2021-104.8 yrs

Plus 5 more approved within the last two years.

Batteries

projects of 10 MW and above · planning database, July 2026 · what batteries do →
SiteSizeStatusWhile discharging
Doverdale - Solar Farm & Battery Storage50 MWoperating 2022could supply ≈175,000 homes
Pershore Lane, Tibberton - Battery Energy Storage System14 MWapproved, not built 2023could supply ≈49,000 homes

What this page does not show

Smaller wind farms on the local grid are also switched off; national data does not show it, so the £ figure here is a floor, not a zero. Offshore wind is counted nationally, never per seat. The planning database can run a quarter behind reality.

Electricity does not travel from a particular project to particular houses. Everything generated goes into the national grid and everyone draws from that shared pool, so "enough for X homes" is a way of sizing the electricity — not a claim that these homes would be powered by this site. Battery storage is counted separately from generation: it moves power in time rather than making it.

Planning statuses come from the government's planning database (REPD), which records what was decided and when, but not why. Where a project was refused we say so and name the authority; for the reasons, look up the planning reference on that council's own register. How to check any figure on this page →

Read the full method, including everything we cannot see →

What has Nigel Huddleston said about the grid in Parliament? Search Hansard →

See the full league table Data (JSON)