No.76 of 650 · approved, not built MP: Lola McEvoy (Labour) England

Darlington

Darlington has 84 MW of clean power (all solar) approved and still not built: enough to supply a year's electricity to 31,000 homes. Britain's grid bottlenecks still add to bills here: about £92 a year per household, £4.1m across the constituency's 44,411 homes.

Not visible
here
No big wind farm on the national grid is mapped to this constituency, so no switch-off payments show here in national data. Smaller wind farms on the local grid can still be paid to switch off — invisibly. The £ figure for this seat is a floor, not a zero.
84 MW
of clean power — all solar — approved and still not built, enough to supply a year's electricity to 31,000 homes. Approved at least two years ago; waiting on the grid, not on planning. That is 13.6× the renewable capacity actually running here.
6 projects · planning database (REPD), July 2026 · how we worked this out
£4.1m
is what the grid gap costs this constituency's 44,411 households in a year between them — £92 each, about 51 days of one home's electricity.
The £92 per household is a national figure — identical in every GB seat. Only the seat total varies, with the number of households · NESO · how we worked this out

The waiting list

6 of 6 waiting projects · years since approval
Park Lane Solar panels 0.4 MW
4.6 YRS
Morrisons - Solar PV system 0.7 MW
4.3 YRS
Whinfield Solar Farm 33 MW
3.8 YRS
Burtree Lane - Solar farm 50 MW
3.6 YRS
Longfield Academy Of Sport - Solar Panels 0.3 MW
2.7 YRS
The Rydal Academy, Rydal Road - Solar Panels 0.2 MW
2.4 YRS

Every approved, unbuilt project

approved 24+ months ago, still not generating · planning database, July 2026
SiteTechnologyEnough forCapacityApprovedWaiting
Burtree Lane - Solar farmSolar Photovoltaics18,000 homes49.9 MW2023-013.6 yrs
Whinfield Solar FarmSolar Photovoltaics12,000 homes33.0 MW2022-103.8 yrs
Morrisons - Solar PV systemSolar Photovoltaics300 homes0.7 MW2022-044.3 yrs
Park Lane Solar panelsSolar Photovoltaics100 homes0.4 MW2022-014.6 yrs
Longfield Academy Of Sport - Solar PanelsSolar Photovoltaics100 homes0.3 MW2023-112.7 yrs
The Rydal Academy, Rydal Road - Solar PanelsSolar Photovoltaics100 homes0.2 MW2024-032.4 yrs

Plus 5 more approved within the last two years.

What this page does not show

Smaller wind farms on the local grid are also switched off; national data does not show it, so the £ figure here is a floor, not a zero. Offshore wind is counted nationally, never per seat. The planning database can run a quarter behind reality.

Electricity does not travel from a particular project to particular houses. Everything generated goes into the national grid and everyone draws from that shared pool, so "enough for X homes" is a way of sizing the electricity — not a claim that these homes would be powered by this site. Battery storage is counted separately from generation: it moves power in time rather than making it.

Planning statuses come from the government's planning database (REPD), which records what was decided and when, but not why. Where a project was refused we say so and name the authority; for the reasons, look up the planning reference on that council's own register. How to check any figure on this page →

Read the full method, including everything we cannot see →

What has Lola McEvoy said about the grid in Parliament? Search Hansard →

See the full league table Data (JSON)