No.378 of 650 · approved, not built MP: Peter Lamb (Labour) England

Crawley

Crawley has 1.6 MW of clean power (all solar) approved and still not built: enough to supply a year's electricity to 600 homes. Britain's grid bottlenecks still add to bills here: about £116 a year per household, £5.3m across the constituency's 45,502 homes.

Not visible
here
No big wind farm on the national grid is mapped to this constituency, so no switch-off payments show here in national data. Smaller wind farms on the local grid can still be paid to switch off — invisibly. The £ figure for this seat is a floor, not a zero.
1.6 MW
of clean power — all solar — approved and still not built, enough to supply a year's electricity to 600 homes. Approved at least two years ago; waiting on the grid, not on planning.
5 projects · planning database (REPD), July 2026 · how we worked this out
£5.3m
is what the grid gap costs this constituency's 45,502 households in a year between them — £116 each, about 65 days of one home's electricity.
The £116 per household is a national figure — identical in every GB seat. Only the seat total varies, with the number of households · NESO · how we worked this out

The waiting list

5 of 5 waiting projects · years since approval
Unit 2, Hollywood Bowl, Crawley Leisure Park - Solar Array 0.2 MW
4.5 YRS
Welland Medical, Hydehurst Lane - Solar Panels 0.9 MW
4.1 YRS
Vodafone UK, Newton Road - Solar Panels 0.3 MW
3.8 YRS
Boeing House, Crawley Business Quarter - Solar Panels
2.4 YRS
Yodel, County Oak Way - Solar Panels 0.2 MW
2.3 YRS

Every approved, unbuilt project

approved 24+ months ago, still not generating · planning database, July 2026
SiteTechnologyEnough forCapacityApprovedWaiting
Welland Medical, Hydehurst Lane - Solar PanelsWelland Medical Limited, Hydehurst Lane, Northgate, CrawleySolar Photovoltaics300 homes0.9 MW2022-104.1 yrs
Vodafone UK, Newton Road - Solar PanelsVodafone UK Limited, 2 Newton Road, Northgate, CrawleySolar Photovoltaics100 homes0.3 MW2023-013.8 yrs
Unit 2, Hollywood Bowl, Crawley Leisure Park - Solar ArrayUnit 2, Hollywood Bowl, Crawley Leisure Park, London Road, West Green, CrawleySolar Photovoltaics100 homes0.2 MW2022-054.5 yrs
Yodel, County Oak Way - Solar PanelsYodel, County Oak Way, Langley Green, CrawleySolar Photovoltaics100 homes0.2 MW2024-082.3 yrs
Boeing House, Crawley Business Quarter - Solar PanelsBOEING HOUSE, CRAWLEY BUSINESS QUARTER, NORTHGATESolar Photovoltaics—— MW2024-062.4 yrs

Plus 4 more approved within the last two years.

What this page does not show

Smaller wind farms on the local grid are also switched off; national data does not show it, so the £ figure here is a floor, not a zero. Offshore wind is counted nationally, never per seat. The planning database can run a quarter behind reality.

Electricity does not travel from a particular project to particular houses. Everything generated goes into the national grid and everyone draws from that shared pool, so "enough for X homes" is a way of sizing the electricity — not a claim that these homes would be powered by this site. Battery storage is counted separately from generation: it moves power in time rather than making it.

Planning statuses come from the government's planning database (REPD), which records what was decided and when, but not why. Where a project was refused we say so and name the authority; for the reasons, look up the planning reference on that council's own register. How to check any figure on this page →