Coventry South
Coventry South has no significant clean power approved and waiting to be built, and none running. Britain's grid bottlenecks still add to bills here: about £92 a year per household, £4.0m across the constituency's 43,462 homes.
here
The waiting list
Every approved, unbuilt project
| Site | Technology | Enough for | Capacity | Approved | Waiting |
|---|---|---|---|---|---|
| Sky Dome - Solar Photovoltaics | Solar Photovoltaics | 200 homes | 0.4 MW | 2021-07 | 5.0 yrs |
| Automotive Trim Developments, Priory Mill - Solar Panels | Solar Photovoltaics | 200 homes | 0.4 MW | 2024-06 | 2.2 yrs |
Plus 6 more approved within the last two years.
Batteries
| Site | Size | Status | While discharging |
|---|---|---|---|
| Torrington Avenue Battery Storage Facility | 30 MW | approved, not built 2024 | could supply ≈105,000 homes |
What this page does not show
Smaller wind farms on the local grid are also switched off; national data does not show it, so the £ figure here is a floor, not a zero. Offshore wind is counted nationally, never per seat. The planning database can run a quarter behind reality.
Electricity does not travel from a particular project to particular houses. Everything generated goes into the national grid and everyone draws from that shared pool, so "enough for X homes" is a way of sizing the electricity — not a claim that these homes would be powered by this site. Battery storage is counted separately from generation: it moves power in time rather than making it.
Planning statuses come from the government's planning database (REPD), which records what was decided and when, but not why. Where a project was refused we say so and name the authority; for the reasons, look up the planning reference on that council's own register. How to check any figure on this page →
What has Zarah Sultana said about the grid in Parliament? Search Hansard →