Corby and East Northamptonshire
Corby and East Northamptonshire has 52 MW of clean power (all solar) approved and still not built: enough to supply a year's electricity to 19,000 homes. Britain's grid bottlenecks still add to bills here: about £92 a year per household, £4.3m across the constituency's 47,039 homes.
here
The waiting list
Every approved, unbuilt project
| Site | Technology | Enough for | Capacity | Approved | Waiting |
|---|---|---|---|---|---|
| Brigstock Solar Farm | Solar Photovoltaics | 18,000 homes | 49.9 MW | 2022-01 | 4.5 yrs |
| Oakland International, Eismann Way - Solar Panels | Solar Photovoltaics | 200 homes | 0.6 MW | 2022-10 | 3.8 yrs |
| Jacksons Bakery - Solar Panels | Solar Photovoltaics | 200 homes | 0.6 MW | 2022-07 | 4.1 yrs |
| Ceva Logistics, Earlstrees Road - Solar Panels | Solar Photovoltaics | 200 homes | 0.5 MW | 2023-03 | 3.4 yrs |
Plus 6 more approved within the last two years.
What this page does not show
Smaller wind farms on the local grid are also switched off; national data does not show it, so the £ figure here is a floor, not a zero. Offshore wind is counted nationally, never per seat. The planning database can run a quarter behind reality.
Electricity does not travel from a particular project to particular houses. Everything generated goes into the national grid and everyone draws from that shared pool, so "enough for X homes" is a way of sizing the electricity — not a claim that these homes would be powered by this site. Battery storage is counted separately from generation: it moves power in time rather than making it.
Planning statuses come from the government's planning database (REPD), which records what was decided and when, but not why. Where a project was refused we say so and name the authority; for the reasons, look up the planning reference on that council's own register. How to check any figure on this page →