Braintree
Braintree has 51 MW of clean power (all solar) approved and still not built: enough to supply a year's electricity to 18,000 homes. Britain's grid bottlenecks still add to bills here: about £92 a year per household, £4.0m across the constituency's 43,166 homes.
here
The waiting list
Every approved, unbuilt project
| Site | Technology | Enough for | Capacity | Approved | Waiting |
|---|---|---|---|---|---|
| Felsted School Road - Solar Photovoltaic Farm & Battery storage | Solar Photovoltaics | 18,000 homes | 49.9 MW | 2023-09 | 2.9 yrs |
| Four Elms, Bardfield Road - Solar Array | Solar Photovoltaics | 100 homes | 0.3 MW | 2023-01 | 3.6 yrs |
| Hedingham School, Christmas Field - Solar Panels | Solar Photovoltaics | 100 homes | 0.2 MW | 2024-03 | 2.4 yrs |
| Antislip Antiwear Treads International, Swinbourne Drive - Solar Panels | Solar Photovoltaics | 100 homes | 0.1 MW | 2023-10 | 2.8 yrs |
Plus 4 more approved within the last two years.
Batteries
| Site | Size | Status | While discharging |
|---|---|---|---|
| Braintree Road, Cressing - Battery Storage | 57 MW | being built 2023 | could supply ≈200,000 homes |
| Surmer Hall, Church Walk - Solar Farm & Battery Storage | 22 MW | approved, not built 2024 | could supply ≈77,000 homes |
| Claredown Farm | 20 MW | 2017 | could supply ≈70,000 homes |
| Slamseys Energy Storage | 10 MW | being built 2017 | could supply ≈35,000 homes |
What this page does not show
Smaller wind farms on the local grid are also switched off; national data does not show it, so the £ figure here is a floor, not a zero. Offshore wind is counted nationally, never per seat. The planning database can run a quarter behind reality.
Electricity does not travel from a particular project to particular houses. Everything generated goes into the national grid and everyone draws from that shared pool, so "enough for X homes" is a way of sizing the electricity — not a claim that these homes would be powered by this site. Battery storage is counted separately from generation: it moves power in time rather than making it.
Planning statuses come from the government's planning database (REPD), which records what was decided and when, but not why. Where a project was refused we say so and name the authority; for the reasons, look up the planning reference on that council's own register. How to check any figure on this page →
What has Sir James Cleverly said about the grid in Parliament? Search Hansard →