Blaenau Gwent and Rhymney
Blaenau Gwent and Rhymney has 66 MW of clean power (onshore wind and solar) approved and still not built: enough to supply a year's electricity to 42,000 homes. When the wires are too full to carry the power, Britain pays wind farms to switch off instead. No wind farm here is paid that way — almost all of it goes to wind farms in Scotland. That cost is shared across every bill in Britain, so households here pay for it too: about £92 a year per household, £3.9m across the constituency's 42,525 homes.
here
The waiting list
Every approved, unbuilt project
| Site | Technology | Enough for | Capacity | Approved | Waiting |
|---|---|---|---|---|---|
| Mynydd Carn Wind Farm | Wind Onshore | 30,000 homes | 34.0 MW | 2024-03 | 2.4 yrs |
| Wauntysswg Farm, near Tredagar | Solar Photovoltaics | 11,000 homes | 30.0 MW | 2019-08 | 7.0 yrs |
| Rassau Industrial Estate | Wind Onshore | 1,300 homes | 1.5 MW | 2019-07 | 7.0 yrs |
| Tafarnaubach Industrial Estate | Solar Photovoltaics | 300 homes | 0.9 MW | 2019-04 | 7.3 yrs |
| Pen-Yr-Heol Farm, Hollybush | Wind Onshore | — | — MW | 2021-05 | 5.2 yrs |
| Roseheyworth Business Park - Solar Array & Battery Storage | Solar Photovoltaics | — | — MW | 2022-03 | 4.4 yrs |
| Rassau Industrial Estate, Rassau - Battery Energy Storage | Solar Photovoltaics | — | — MW | 2023-07 | 3.0 yrs |
Plus 1 more approved within the last two years.
What this page does not show
Smaller wind farms on the local grid are also switched off; national data does not show it, so the £ figure here is a floor, not a zero. Offshore wind is counted nationally, never per seat. The planning database can run a quarter behind reality.
Electricity does not travel from a particular project to particular houses. Everything generated goes into the national grid and everyone draws from that shared pool, so "enough for X homes" is a way of sizing the electricity — not a claim that these homes would be powered by this site. Battery storage is counted separately from generation: it moves power in time rather than making it.
Planning statuses come from the government's planning database (REPD), which records what was decided and when, but not why. Where a project was refused we say so and name the authority; for the reasons, look up the planning reference on that council's own register. How to check any figure on this page →