Belfast West
Belfast West has no significant clean power approved and waiting to be built, and none running. Northern Ireland is on the all-Ireland grid, so Britain's grid bottlenecks do not reach bills here in the same way.
Ranks 569 of 650 for clean power approved and not built.
What is stuck, and why
| Project and developer | Tech | Size | Why it is stuck |
|---|---|---|---|
| Colinglen Road BatteryHannahstown BESS | Battery | 50 MW |
Waiting 6.0 years for a planning decisionWho can move it: Belfast Council |
What else is in the briefing
- All 1 projects, each with its planning reference and the organisation that holds the next decision
- Every approval a project still needs, and which of them the public can see
- What building them would mean here — community payments, business rates and construction work
- How Belfast West compares with its neighbouring constituencies
- Drafted parliamentary questions and letters, filled in with this seat's figures
- 1 story angles for local reporting
- A two-page PDF, and a newsroom edition with the references and who to call