Bedford
Bedford has 7 MW of clean power (all solar) approved and still not built: enough to supply a year's electricity to 2,600 homes. Britain's grid bottlenecks still add to bills here: about £92 a year per household, £4.1m across the constituency's 44,851 homes.
here
The waiting list
Every approved, unbuilt project
| Site | Technology | Enough for | Capacity | Approved | Waiting |
|---|---|---|---|---|---|
| Elstow Landfill Site | Solar Photovoltaics | 2,000 homes | 5.5 MW | 2020-11 | 5.7 yrs |
| Unit 8, Hudson Road - Solar Panels | Solar Photovoltaics | 300 homes | 0.9 MW | 2022-12 | 3.6 yrs |
| Atlas Converting Equipment Limited, Wolseley Road - Solar Panels | Solar Photovoltaics | 100 homes | 0.3 MW | 2024-03 | 2.4 yrs |
| Systems House | Solar Photovoltaics | 100 homes | 0.2 MW | 2021-10 | 4.8 yrs |
| Bedford Academy, Mile Road - Solar Panels | Solar Photovoltaics | 100 homes | 0.1 MW | 2022-06 | 4.1 yrs |
Plus 4 more approved within the last two years.
What this page does not show
Smaller wind farms on the local grid are also switched off; national data does not show it, so the £ figure here is a floor, not a zero. Offshore wind is counted nationally, never per seat. The planning database can run a quarter behind reality.
Electricity does not travel from a particular project to particular houses. Everything generated goes into the national grid and everyone draws from that shared pool, so "enough for X homes" is a way of sizing the electricity — not a claim that these homes would be powered by this site. Battery storage is counted separately from generation: it moves power in time rather than making it.
Planning statuses come from the government's planning database (REPD), which records what was decided and when, but not why. Where a project was refused we say so and name the authority; for the reasons, look up the planning reference on that council's own register. How to check any figure on this page →