No.243 of 650 · approved, not built MP: Mohammad Yasin (Labour) England

Bedford

Bedford has 7 MW of clean power (all solar) approved and still not built: enough to supply a year's electricity to 2,600 homes. Britain's grid bottlenecks still add to bills here: about £92 a year per household, £4.1m across the constituency's 44,851 homes.

Not visible
here
No big wind farm on the national grid is mapped to this constituency, so no switch-off payments show here in national data. Smaller wind farms on the local grid can still be paid to switch off — invisibly. The £ figure for this seat is a floor, not a zero.
7 MW
of clean power — all solar — approved and still not built, enough to supply a year's electricity to 2,600 homes. Approved at least two years ago; waiting on the grid, not on planning.
5 projects · planning database (REPD), July 2026 · how we worked this out
£4.1m
is what the grid gap costs this constituency's 44,851 households in a year between them — £92 each, about 51 days of one home's electricity.
The £92 per household is a national figure — identical in every GB seat. Only the seat total varies, with the number of households · NESO · how we worked this out

The waiting list

5 of 5 waiting projects · years since approval
Elstow Landfill Site 5.5 MW
5.7 YRS
Systems House 0.2 MW
4.8 YRS
Bedford Academy, Mile Road - Solar Panels 0.1 MW
4.1 YRS
Unit 8, Hudson Road - Solar Panels 0.9 MW
3.6 YRS
Atlas Converting Equipment Limited, Wolseley Road - Solar Panels 0.3 MW
2.4 YRS

Every approved, unbuilt project

approved 24+ months ago, still not generating · planning database, July 2026
SiteTechnologyEnough forCapacityApprovedWaiting
Elstow Landfill SiteSolar Photovoltaics2,000 homes5.5 MW2020-115.7 yrs
Unit 8, Hudson Road - Solar PanelsSolar Photovoltaics300 homes0.9 MW2022-123.6 yrs
Atlas Converting Equipment Limited, Wolseley Road - Solar PanelsSolar Photovoltaics100 homes0.3 MW2024-032.4 yrs
Systems HouseSolar Photovoltaics100 homes0.2 MW2021-104.8 yrs
Bedford Academy, Mile Road - Solar PanelsSolar Photovoltaics100 homes0.1 MW2022-064.1 yrs

Plus 4 more approved within the last two years.

What this page does not show

Smaller wind farms on the local grid are also switched off; national data does not show it, so the £ figure here is a floor, not a zero. Offshore wind is counted nationally, never per seat. The planning database can run a quarter behind reality.

Electricity does not travel from a particular project to particular houses. Everything generated goes into the national grid and everyone draws from that shared pool, so "enough for X homes" is a way of sizing the electricity — not a claim that these homes would be powered by this site. Battery storage is counted separately from generation: it moves power in time rather than making it.

Planning statuses come from the government's planning database (REPD), which records what was decided and when, but not why. Where a project was refused we say so and name the authority; for the reasons, look up the planning reference on that council's own register. How to check any figure on this page →

Read the full method, including everything we cannot see →

What has Mohammad Yasin said about the grid in Parliament? Search Hansard →

See the full league table Data (JSON)