CONSTITUENCY BRIEFING · ENERGYMAP.APP

Bangor Aberconwy

MP: Claire Hughes (Labour) Wales Data to July 2026

Bangor Aberconwy has 18 MW of clean power (almost all onshore wind) approved and still not built: enough to supply a year's electricity to 15,000 homes. When the wires are too full to carry the power, Britain pays wind farms to switch off instead. No wind farm here is paid that way — almost all of it goes to wind farms in Scotland. That cost is shared across every bill in Britain, so households here pay for it too: about £92 a year per household, £3.7m across the constituency's 40,182 homes. There is also 182 MW of wind running here on the local network. If that gets switched off, no national record shows it.

Ranks 205 of 650 for clean power approved and not built.

What is stuck, and why

Project and developerTechSizeWhy it is stuck
Pant y MaenGresham House Onshore wind 15,000 homes
18 MW
Approved 9 years ago — nothing has happened sinceWho can move it: the developer and the network company

What else is in the briefing