CONSTITUENCY BRIEFING · ENERGYMAP.APP

Airdrie and Shotts

MP: Kenneth Stevenson (Labour) Scotland Data to July 2026

Airdrie and Shotts was paid £2.3m last year to switch off its wind farms, because the wires south were full. That would cover every local household's electricity for 31 days. A further 24 MW of approved clean power (almost all onshore wind) is still waiting to be built here: enough to supply a year's electricity to 20,000 homes. A 300 MW battery approved at Newarthill Energy Park in 2025 would store power that is currently wasted; it has not been built.

Ranks 185 of 650 for clean power approved and not built; 14 of 19 among seats with visible switch-off payments.

What is stuck, and why

Project and developerTechSizeWhy it is stuck
Newarthill Energy ParkGeocore Limited Battery
300 MW
Cleared the grid queue review, so it now has a firm connection dateWho can move it: the grid operator (NESO)
North Lanrigg Energy StorageNorth Lanrigg Battery Storage Limited Battery
200 MW
Cannot connect to the grid until 2028, 3 years after it was approvedWho can move it: the grid operator (NESO) and SP Transmission
Fernishaw Solar Farm & Battery Energy Storage FaciliElgin Energy (EEB67) Solar 27,000 homes
75 MW
Approved a year ago — nothing has happened sinceWho can move it: the developer and the network company

What else is in the briefing

No account needed for any of this: the full seat page with every figure, the method and sources, and this constituency's raw data. The account covers the packaged briefing only.