 "pcon24cd": "W07000106",
 "name": "Pontypridd",
 "nation": "Wales",
 "number1": {
  "visible": false,
  "note": "No big wind farm on the national grid is mapped to this constituency. Smaller wind farms here can still be paid to switch off by the local network, but those payments are not visible in national data \u2014 the \u00a3 figure is a floor.",
  "invisible_wind": {
   "mw": 22.9,
   "sites": 3
  }
 },
 "number2": {
  "stuck_mw": 41.3,
  "stuck_mw_int": 41,
  "stuck_sites": 4,
  "homes_equivalent": 15000,
  "homes_vs_seat_households": 0.35,
  "stuck_mw_12m_cut": 42.6,
  "consented_not_built_mw_any_age": 42.6,
  "operational_mw": 41.5,
  "operational_homes_equivalent": 27000,
  "refused_5y_mw": 0.0,
  "withdrawn_5y_mw": 0.0,
  "median_months_to_decision": 3.4,
  "rank": 158,
  "tech_mix": {
   "solar": 41.3
  },
  "tech_summary": "all solar",
  "waiting_vs_running": 1.0,
  "projects": [
   {
    "site_name": "Maes Mawr Solar",
    "repd_ref_id": 9981,
    "technology": "Solar Photovoltaics",
    "capacity_mw": 30.0,
    "homes_equivalent": 11000,
    "consented": "2023-12-21",
    "months_waiting": 31.4,
    "status": "Under Construction"
   },
   {
    "site_name": "Talbot Green, Llantrisant - Solar Farm",
    "repd_ref_id": 9772,
    "technology": "Solar Photovoltaics",
    "capacity_mw": 9.9,
    "homes_equivalent": 3600,
    "consented": "2024-04-25",
    "months_waiting": 27.3,
    "status": "Awaiting Construction"
   },
   {
    "site_name": "Whitehall Farm, Llanharry Road - Solar PV Panels",
    "repd_ref_id": 14356,
    "technology": "Solar Photovoltaics",
    "capacity_mw": 1.3,
    "homes_equivalent": 500,
    "consented": "2024-09-17",
    "months_waiting": 22.5,
    "status": "Under Construction"
   },
   {
    "site_name": "Midway Retail Park -  Solar Photovoltaic Panels",
    "repd_ref_id": 16304,
    "technology": "Solar Photovoltaics",
    "capacity_mw": 0.9,
    "homes_equivalent": 300,
    "consented": "2024-06-20",
    "months_waiting": 25.4,
    "status": "Awaiting Construction"
   },
   {
    "site_name": "Rhiwfelin Fach Farm, Ynysmaerdy - Solar Photovoltaic Panels",
    "repd_ref_id": 10306,
    "technology": "Solar Photovoltaics",
    "capacity_mw": 0.5,
    "homes_equivalent": 200,
    "consented": "2022-03-21",
    "months_waiting": 52.4,
    "status": "Awaiting Construction"
   }
  ]
 },
 "number3": {
  "applicable": true,
  "per_household_gbp": 91.96,
  "seat_households": 43273,
  "seat_total_gbp": 4000000,
  "framings": {
   "days_of_home_electricity": 51.0
  },
  "note": "National figure: the per-household cost is the same for every GB seat; only the seat total varies with household count."
 },
 "batteries": {
  "operating_mw": 20.0,
  "building_mw": 0.0,
  "approved_mw": 0.0,
  "approved_24m_mw": 0.0,
  "refused_mw": 0.0,
  "submitted_mw": 430.2,
  "sites": [
   {
    "site_name": "National Road, Cilfynydd - Battery Energy Storage System",
    "capacity_mw": 200.0,
    "status": "submitted",
    "year": null,
    "homes_while_discharging": 701000
   },
   {
    "site_name": "Pound Farm Lane - Battery Storage",
    "capacity_mw": 200.0,
    "status": "submitted",
    "year": null,
    "homes_while_discharging": 701000
   },
   {
    "site_name": "Llanwonno - Wind Farm",
    "capacity_mw": 30.0,
    "status": "submitted",
    "year": null,
    "homes_while_discharging": 105000
   },
   {
    "site_name": "Energy Centre Royal Mint",
    "capacity_mw": 20.0,
    "status": "operating",
    "year": 2020,
    "homes_while_discharging": 70000
   },
   {
    "site_name": "Coedcae Industrial Estate, Talbot Green - Micro Energy Storage Systems",
    "capacity_mw": 0.2,
    "status": "submitted",
    "year": null,
    "homes_while_discharging": 700
   }
  ]
 },
 "pipeline_projects": [
  {
   "site_name": "National Road, Cilfynydd - Battery Energy Storage System",
   "repd_ref_id": 19201,
   "technology": "Battery",
   "capacity_mw": 200.0,
   "homes_equivalent": null,
   "status": "Application Submitted",
   "consented": null,
   "refused": null,
   "planning_authority": "Rhondda Cynon Taf",
   "planning_ref": "25/0604/FUL",
   "operator": "Rewe 2 Limited",
   "reason": {
    "reason": "planning_overdue",
    "label": "Waiting 14 months for a planning decision",
    "who": "Rhondda Cynon Taf Council",
    "evidence": {
     "submitted": "2025-06-16",
     "months_waiting": 14
    },
    "all_matches": [
     "planning_overdue"
    ]
   },
   "earliest": null,
   "tec": null
  },
  {
   "site_name": "Pound Farm Lane - Battery Storage",
   "repd_ref_id": 20012,
   "technology": "Battery",
   "capacity_mw": 200.0,
   "homes_equivalent": null,
   "status": "Application Submitted",
   "consented": null,
   "refused": null,
   "planning_authority": "Rhondda Cynon Taf",
   "planning_ref": "25/1231/FUL",
   "operator": "Pulse Clean Energy",
   "reason": {
    "reason": "in_planning",
    "label": "Applied in 2025, still waiting for a decision",
    "who": "Rhondda Cynon Taf Council",
    "evidence": {
     "submitted": "2025-11-28",
     "months_waiting": 8
    },
    "all_matches": [
     "in_planning"
    ]
   },
   "earliest": null,
   "tec": null
  },
  {
   "site_name": "Glyntaff Solar Farm, Bryntail Road - Solar Array",
   "repd_ref_id": 15563,
   "technology": "Solar Photovoltaics",
   "capacity_mw": 39.9,
   "homes_equivalent": 14000,
   "status": "Application Submitted",
   "consented": null,
   "refused": null,
   "planning_authority": "Welsh Government (NSIP)",
   "planning_ref": "CAS-03147-D7S9P8",
   "operator": "Renantis Falck Renewables Limited",
   "reason": {
    "reason": "planning_overdue",
    "label": "Waiting 15 months for a planning decision",
    "who": "the Welsh Government (it decides big energy projects)",
    "evidence": {
     "submitted": "2025-05-09",
     "months_waiting": 15
    },
    "all_matches": [
     "planning_overdue"
    ]
   },
   "earliest": null,
   "tec": null
  },
  {
   "site_name": "Llanwonno - Wind Farm",
   "repd_ref_id": 18568,
   "technology": "Solar Photovoltaics",
   "capacity_mw": 30.7,
   "homes_equivalent": 11000,
   "status": "Application Submitted",
   "consented": null,
   "refused": null,
   "planning_authority": "Welsh Government (NSIP)",
   "planning_ref": "CAS-02125-Q0T5P0",
   "operator": "Cenin Renewables Limited",
   "reason": {
    "reason": "planning_overdue",
    "label": "Waiting 17 months for a planning decision",
    "who": "the Welsh Government (it decides big energy projects)",
    "evidence": {
     "submitted": "2025-03-11",
     "months_waiting": 17
    },
    "all_matches": [
     "planning_overdue"
    ]
   },
   "earliest": null,
   "tec": null
  },
  {
   "site_name": "Llanwonno - Wind Farm",
   "repd_ref_id": 17480,
   "technology": "Wind Onshore",
   "capacity_mw": 30.4,
   "homes_equivalent": 27000,
   "status": "Application Submitted",
   "consented": null,
   "refused": null,
   "planning_authority": "Welsh Government (NSIP)",
   "planning_ref": "CAS-02125-Q0T5P0",
   "operator": "Cenin Renewables Limited",
   "reason": {
    "reason": "planning_overdue",
    "label": "Waiting 17 months for a planning decision",
    "who": "the Welsh Government (it decides big energy projects)",
    "evidence": {
     "submitted": "2025-03-11",
     "months_waiting": 17
    },
    "all_matches": [
     "planning_overdue"
    ]
   },
   "earliest": null,
   "tec": null
  },
  {
   "site_name": "Maes Mawr Solar",
   "repd_ref_id": 9981,
   "technology": "Solar Photovoltaics",
   "capacity_mw": 30.0,
   "homes_equivalent": 11000,
   "status": "Under Construction",
   "consented": "2023-12-21",
   "refused": null,
   "planning_authority": "Welsh Government (NSIP)",
   "planning_ref": "DNS/3282038",
   "operator": "Elgin Energy EsCo Ltd",
   "reason": {
    "reason": "building",
    "label": "Under construction",
    "who": "the developer",
    "evidence": {},
    "all_matches": [
     "building"
    ]
   },
   "earliest": "2027 (in construction)",
   "tec": null
  },
  {
   "site_name": "Llanwonno - Wind Farm",
   "repd_ref_id": 18569,
   "technology": "Battery",
   "capacity_mw": 30.0,
   "homes_equivalent": null,
   "status": "Application Submitted",
   "consented": null,
   "refused": null,
   "planning_authority": "Welsh Government (NSIP)",
   "planning_ref": "CAS-02125-Q0T5P0",
   "operator": "Cenin Renewables Limited",
   "reason": {
    "reason": "planning_overdue",
    "label": "Waiting 17 months for a planning decision",
    "who": "the Welsh Government (it decides big energy projects)",
    "evidence": {
     "submitted": "2025-03-11",
     "months_waiting": 17
    },
    "all_matches": [
     "planning_overdue"
    ]
   },
   "earliest": null,
   "tec": null
  },
  {
   "site_name": "Talbot Green, Llantrisant - Solar Farm",
   "repd_ref_id": 9772,
   "technology": "Solar Photovoltaics",
   "capacity_mw": 9.9,
   "homes_equivalent": 3600,
   "status": "Awaiting Construction",
   "consented": "2024-04-25",
   "refused": null,
   "planning_authority": "Rhondda Cynon Taf",
   "planning_ref": "22/1413/10",
   "operator": "Windel Energy",
   "reason": {
    "reason": "consented_no_activity",
    "label": "Approved 2 years ago \u2014 nothing has happened since",
    "who": "the developer and the network company",
    "evidence": {
     "consent_date": "2024-04-25",
     "years_since_consent": 2.3
    },
    "all_matches": [
     "consented_no_activity"
    ]
   },
   "earliest": null,
   "tec": null
  },
  {
   "site_name": "Dyffryn Farm, Ynysmaerdy - Solar Panels",
   "repd_ref_id": 18881,
   "technology": "Solar Photovoltaics",
   "capacity_mw": 9.9,
   "homes_equivalent": 3600,
   "status": "Application Submitted",
   "consented": null,
   "refused": null,
   "planning_authority": "Rhondda Cynon Taf",
   "planning_ref": "25/1280/FUL",
   "operator": "Windel Solar 8 Limited",
   "reason": {
    "reason": "in_planning",
    "label": "Applied in 2025, still waiting for a decision",
    "who": "Rhondda Cynon Taf Council",
    "evidence": {
     "submitted": "2025-12-23",
     "months_waiting": 7
    },
    "all_matches": [
     "in_planning"
    ]
   },
   "earliest": null,
   "tec": null
  },
  {
   "site_name": "Whitehall Farm, Llanharry Road - Solar PV Panels",
   "repd_ref_id": 14356,
   "technology": "Solar Photovoltaics",
   "capacity_mw": 1.3,
   "homes_equivalent": 500,
   "status": "Under Construction",
   "consented": "2024-09-17",
   "refused": null,
   "planning_authority": "Rhondda Cynon Taf",
   "planning_ref": "24/0630/FUL",
   "operator": "Mccarthy Contractors (Bridgend) Limited",
   "reason": {
    "reason": "building",
    "label": "Under construction",
    "who": "the developer",
    "evidence": {},
    "all_matches": [
     "building"
    ]
   },
   "earliest": "2027 (in construction)",
   "tec": null
  }
 ],
 "projects_withheld_unreferenced": 0,
 "neighbours": [
  "W07000110",
  "W07000092",
  "W07000086",
  "W07000090",
  "W07000088",
  "W07000107",
  "W07000099"
 ],
 "flags": [
  "curtailment_not_visible"
 ],
 "windows": {
  "curtailment": [
   "2025-08-01",
   "2026-07-31"
  ],
  "repd_as_of": "2026-08-03"
 }
}