 "pcon24cd": "W07000098",
 "name": "Llanelli",
 "nation": "Wales",
 "number1": {
  "visible": false,
  "note": "No big wind farm on the national grid is mapped to this constituency. Smaller wind farms here can still be paid to switch off by the local network, but those payments are not visible in national data \u2014 the \u00a3 figure is a floor.",
  "invisible_wind": {
   "mw": 0.0,
   "sites": 0
  }
 },
 "number2": {
  "stuck_mw": 106.3,
  "stuck_mw_int": 106,
  "stuck_sites": 4,
  "homes_equivalent": 39000,
  "homes_vs_seat_households": 0.95,
  "stuck_mw_12m_cut": 115.9,
  "consented_not_built_mw_any_age": 116.9,
  "operational_mw": 43.6,
  "operational_homes_equivalent": 16000,
  "refused_5y_mw": 1.8,
  "withdrawn_5y_mw": 0.0,
  "median_months_to_decision": 7.5,
  "rank": 61,
  "tech_mix": {
   "solar": 106.3
  },
  "tech_summary": "all solar",
  "waiting_vs_running": 2.4,
  "projects": [
   {
    "site_name": "Tycroes Solar Farm",
    "repd_ref_id": 7469,
    "technology": "Solar Photovoltaics",
    "capacity_mw": 40.0,
    "homes_equivalent": 15000,
    "consented": "2021-08-12",
    "months_waiting": 59.7,
    "status": "Awaiting Construction"
   },
   {
    "site_name": "Brynrhyd Solar Farm",
    "repd_ref_id": 9977,
    "technology": "Solar Photovoltaics",
    "capacity_mw": 36.0,
    "homes_equivalent": 13000,
    "consented": "2023-06-20",
    "months_waiting": 37.5,
    "status": "Awaiting Construction"
   },
   {
    "site_name": "Llangennech Solar",
    "repd_ref_id": 6795,
    "technology": "Solar Photovoltaics",
    "capacity_mw": 29.9,
    "homes_equivalent": 11000,
    "consented": "2021-07-23",
    "months_waiting": 60.3,
    "status": "Awaiting Construction"
   },
   {
    "site_name": "Glyngwernen Farm, Uchaf Fawr -  Solar Farm",
    "repd_ref_id": 16838,
    "technology": "Solar Photovoltaics",
    "capacity_mw": 8.4,
    "homes_equivalent": 3000,
    "consented": "2025-02-17",
    "months_waiting": 17.5,
    "status": "Awaiting Construction"
   },
   {
    "site_name": "Pembrey Road - Ground Mounted Solar Panels",
    "repd_ref_id": 14022,
    "technology": "Solar Photovoltaics",
    "capacity_mw": 1.0,
    "homes_equivalent": 400,
    "consented": "2025-11-25",
    "months_waiting": 8.2,
    "status": "Awaiting Construction"
   },
   {
    "site_name": "Y Tyddyn Teg, Heol Y Nant - Solar Farm",
    "repd_ref_id": 16617,
    "technology": "Solar Photovoltaics",
    "capacity_mw": 1.0,
    "homes_equivalent": 400,
    "consented": "2025-01-29",
    "months_waiting": 18.1,
    "status": "Awaiting Construction"
   },
   {
    "site_name": "Morrisons Supermarket, -Solar Panels",
    "repd_ref_id": 12593,
    "technology": "Solar Photovoltaics",
    "capacity_mw": 0.4,
    "homes_equivalent": 100,
    "consented": "2022-12-21",
    "months_waiting": 43.4,
    "status": "Awaiting Construction"
   },
   {
    "site_name": "Sandy Road - Solar Panels & Biomass Boiler",
    "repd_ref_id": 13397,
    "technology": "Solar Photovoltaics",
    "capacity_mw": 0.2,
    "homes_equivalent": 100,
    "consented": "2025-03-03",
    "months_waiting": 17.0,
    "status": "Awaiting Construction"
   },
   {
    "site_name": "Ty Cwm Gwendraeth, Gwalia Mynydd Mawr - Solar Panels",
    "repd_ref_id": 20410,
    "technology": "Solar Photovoltaics",
    "capacity_mw": null,
    "homes_equivalent": null,
    "consented": "2026-02-13",
    "months_waiting": 5.6,
    "status": "Awaiting Construction"
   }
  ]
 },
 "number3": {
  "applicable": true,
  "per_household_gbp": 91.96,
  "seat_households": 40821,
  "seat_total_gbp": 3800000,
  "framings": {
   "days_of_home_electricity": 51.0
  },
  "note": "National figure: the per-household cost is the same for every GB seat; only the seat total varies with household count."
 },
 "batteries": {
  "operating_mw": 0.0,
  "building_mw": 0.0,
  "approved_mw": 27.8,
  "approved_24m_mw": 0.0,
  "refused_mw": 0.0,
  "submitted_mw": 0.6,
  "sites": [
   {
    "site_name": "Heol Aur, Dafen Industrial Estate - Battery Storage System",
    "capacity_mw": 25.0,
    "status": "approved",
    "year": 2026,
    "homes_while_discharging": 88000
   },
   {
    "site_name": "Glyngwernen Farm, Uchaf Fawr - Battery Storage",
    "capacity_mw": 2.0,
    "status": "approved",
    "year": 2025,
    "homes_while_discharging": 7000
   },
   {
    "site_name": "Dafen Inn Row And Exchange Row - Energy Storage System",
    "capacity_mw": 0.2,
    "status": "approved",
    "year": 2025,
    "homes_while_discharging": 700
   },
   {
    "site_name": "Heol Parc Mawr Workshops, Cross Hands - Micro Energy Storage",
    "capacity_mw": 0.2,
    "status": "approved",
    "year": 2025,
    "homes_while_discharging": 700
   },
   {
    "site_name": "Parc Y Scarlets, Pemberton Athletics Track - Micro Energy Storage",
    "capacity_mw": 0.2,
    "status": "approved",
    "year": 2025,
    "homes_while_discharging": 700
   },
   {
    "site_name": "Andrew Street - Micro Energy Storage",
    "capacity_mw": 0.2,
    "status": "submitted",
    "year": null,
    "homes_while_discharging": 700
   },
   {
    "site_name": "The Beacon Enterprise Centre, Heol Aur -  Micro Battery Storage",
    "capacity_mw": 0.2,
    "status": "approved",
    "year": 2026,
    "homes_while_discharging": 700
   },
   {
    "site_name": "Lower Trostre Road - Micro Battery Storage",
    "capacity_mw": 0.2,
    "status": "submitted",
    "year": null,
    "homes_while_discharging": 700
   },
   {
    "site_name": "North Avenue, Llanelli Workshops -Micro Energy Storage",
    "capacity_mw": 0.2,
    "status": "submitted",
    "year": null,
    "homes_while_discharging": 700
   }
  ]
 },
 "pipeline_projects": [
  {
   "site_name": "Tycroes Solar Farm",
   "repd_ref_id": 7469,
   "technology": "Solar Photovoltaics",
   "capacity_mw": 40.0,
   "homes_equivalent": 15000,
   "status": "Awaiting Construction",
   "consented": "2021-08-12",
   "refused": null,
   "planning_authority": "Welsh Government (NSIP)",
   "planning_ref": "DNS/3227364",
   "operator": "Spring Dev 2",
   "reason": {
    "reason": "consented_no_activity",
    "label": "Approved 5 years ago \u2014 nothing has happened since",
    "who": "the developer and the network company",
    "evidence": {
     "consent_date": "2021-08-12",
     "years_since_consent": 5.0
    },
    "all_matches": [
     "consented_no_activity"
    ]
   },
   "earliest": null,
   "tec": null
  },
  {
   "site_name": "Brynrhyd Solar Farm",
   "repd_ref_id": 9977,
   "technology": "Solar Photovoltaics",
   "capacity_mw": 36.0,
   "homes_equivalent": 13000,
   "status": "Awaiting Construction",
   "consented": "2023-06-20",
   "refused": null,
   "planning_authority": "Welsh Government (NSIP)",
   "planning_ref": "DNS/3260565",
   "operator": "Capital Dynamics Limited",
   "reason": {
    "reason": "consented_no_activity",
    "label": "Approved 3 years ago \u2014 nothing has happened since",
    "who": "the developer and the network company",
    "evidence": {
     "consent_date": "2023-06-20",
     "years_since_consent": 3.1
    },
    "all_matches": [
     "consented_no_activity"
    ]
   },
   "earliest": null,
   "tec": null
  },
  {
   "site_name": "Pencoed Ganol Farm, Pendderi Road - Solar Panels",
   "repd_ref_id": 18181,
   "technology": "Solar Photovoltaics",
   "capacity_mw": 35.0,
   "homes_equivalent": 13000,
   "status": "Application Submitted",
   "consented": null,
   "refused": null,
   "planning_authority": "Welsh Government (NSIP)",
   "planning_ref": "CAS-04012-T8Y8D2",
   "operator": "Windel Solar 11 Limited",
   "reason": {
    "reason": "in_planning",
    "label": "Applied in 2025, still waiting for a decision",
    "who": "the Welsh Government (it decides big energy projects)",
    "evidence": {
     "submitted": "2025-11-11",
     "months_waiting": 9
    },
    "all_matches": [
     "in_planning"
    ]
   },
   "earliest": null,
   "tec": null
  },
  {
   "site_name": "Llangennech Solar",
   "repd_ref_id": 6795,
   "technology": "Solar Photovoltaics",
   "capacity_mw": 29.9,
   "homes_equivalent": 11000,
   "status": "Awaiting Construction",
   "consented": "2021-07-23",
   "refused": null,
   "planning_authority": "Welsh Government (NSIP)",
   "planning_ref": "DNS/3213164",
   "operator": "Voltalia UK",
   "reason": {
    "reason": "consented_no_activity",
    "label": "Approved 5 years ago \u2014 nothing has happened since",
    "who": "the developer and the network company",
    "evidence": {
     "consent_date": "2021-07-23",
     "years_since_consent": 5.0
    },
    "all_matches": [
     "consented_no_activity"
    ]
   },
   "earliest": null,
   "tec": null
  },
  {
   "site_name": "Heol Aur, Dafen Industrial Estate - Battery Storage System",
   "repd_ref_id": 18991,
   "technology": "Battery",
   "capacity_mw": 25.0,
   "homes_equivalent": null,
   "status": "Awaiting Construction",
   "consented": "2026-02-26",
   "refused": null,
   "planning_authority": "Carmarthenshire",
   "planning_ref": "PL/09340",
   "operator": "Westfa Limited",
   "reason": {
    "reason": "consented_no_activity",
    "label": "Approved less than a year ago \u2014 nothing has happened since",
    "who": "the developer and the network company",
    "evidence": {
     "consent_date": "2026-02-26",
     "years_since_consent": 0.4
    },
    "all_matches": [
     "consented_no_activity"
    ]
   },
   "earliest": null,
   "tec": null
  },
  {
   "site_name": "Glyngwernen Farm, Uchaf Fawr -  Solar Farm",
   "repd_ref_id": 16838,
   "technology": "Solar Photovoltaics",
   "capacity_mw": 8.4,
   "homes_equivalent": 3000,
   "status": "Awaiting Construction",
   "consented": "2025-02-17",
   "refused": null,
   "planning_authority": "Carmarthenshire",
   "planning_ref": "PL/08017",
   "operator": "Bartypower Limited",
   "reason": {
    "reason": "consented_no_activity",
    "label": "Approved a year ago \u2014 nothing has happened since",
    "who": "the developer and the network company",
    "evidence": {
     "consent_date": "2025-02-17",
     "years_since_consent": 1.5
    },
    "all_matches": [
     "consented_no_activity"
    ]
   },
   "earliest": null,
   "tec": null
  },
  {
   "site_name": "Glyngwernen Farm, Uchaf Fawr - Battery Storage",
   "repd_ref_id": 16839,
   "technology": "Battery",
   "capacity_mw": 2.0,
   "homes_equivalent": null,
   "status": "Awaiting Construction",
   "consented": "2025-02-17",
   "refused": null,
   "planning_authority": "Carmarthenshire",
   "planning_ref": "PL/08017",
   "operator": "Bartypower Limited",
   "reason": {
    "reason": "consented_no_activity",
    "label": "Approved a year ago \u2014 nothing has happened since",
    "who": "the developer and the network company",
    "evidence": {
     "consent_date": "2025-02-17",
     "years_since_consent": 1.5
    },
    "all_matches": [
     "consented_no_activity"
    ]
   },
   "earliest": null,
   "tec": null
  },
  {
   "site_name": "Morfa Pingett Solar Farm",
   "repd_ref_id": 9517,
   "technology": "Solar Photovoltaics",
   "capacity_mw": 1.6,
   "homes_equivalent": 600,
   "status": "Application Refused",
   "consented": null,
   "refused": "2021-10-04",
   "planning_authority": "Carmarthenshire",
   "planning_ref": "PL/02407",
   "operator": "Richard Thomas and Co (Hydro) Limited",
   "reason": {
    "reason": "refused",
    "label": "Refused by Carmarthenshire Council in 2021",
    "who": "Carmarthenshire Council",
    "evidence": {
     "refusal_date": "2021-10-04"
    },
    "all_matches": [
     "refused"
    ]
   },
   "earliest": null,
   "tec": null
  },
  {
   "site_name": "Pembrey Road - Ground Mounted Solar Panels",
   "repd_ref_id": 14022,
   "technology": "Solar Photovoltaics",
   "capacity_mw": 1.0,
   "homes_equivalent": 400,
   "status": "Awaiting Construction",
   "consented": "2025-11-25",
   "refused": null,
   "planning_authority": "Carmarthenshire",
   "planning_ref": "PL/05836",
   "operator": "Gravells Limited",
   "reason": {
    "reason": "consented_no_activity",
    "label": "Approved less than a year ago \u2014 nothing has happened since",
    "who": "the developer and the network company",
    "evidence": {
     "consent_date": "2025-11-25",
     "years_since_consent": 0.7
    },
    "all_matches": [
     "consented_no_activity"
    ]
   },
   "earliest": null,
   "tec": null
  },
  {
   "site_name": "Y Tyddyn Teg, Heol Y Nant - Solar Farm",
   "repd_ref_id": 16617,
   "technology": "Solar Photovoltaics",
   "capacity_mw": 1.0,
   "homes_equivalent": 400,
   "status": "Awaiting Construction",
   "consented": "2025-01-29",
   "refused": null,
   "planning_authority": "Carmarthenshire",
   "planning_ref": "PL/07775",
   "operator": "Power on Demand Limited",
   "reason": {
    "reason": "consented_no_activity",
    "label": "Approved a year ago \u2014 nothing has happened since",
    "who": "the developer and the network company",
    "evidence": {
     "consent_date": "2025-01-29",
     "years_since_consent": 1.5
    },
    "all_matches": [
     "consented_no_activity"
    ]
   },
   "earliest": null,
   "tec": null
  }
 ],
 "projects_withheld_unreferenced": 0,
 "neighbours": [
  "W07000097",
  "W07000087"
 ],
 "flags": [
  "curtailment_not_visible"
 ],
 "windows": {
  "curtailment": [
   "2025-08-01",
   "2026-07-31"
  ],
  "repd_as_of": "2026-08-03"
 }
}