 "pcon24cd": "S14000068",
 "name": "Bathgate and Linlithgow",
 "nation": "Scotland",
 "number1": {
  "visible": false,
  "note": "No big wind farm on the national grid is mapped to this constituency. Smaller wind farms here can still be paid to switch off by the local network, but those payments are not visible in national data \u2014 the \u00a3 figure is a floor.",
  "invisible_wind": {
   "mw": 8.5,
   "sites": 1
  }
 },
 "number2": {
  "stuck_mw": 46.1,
  "stuck_mw_int": 46,
  "stuck_sites": 6,
  "homes_equivalent": 24000,
  "homes_vs_seat_households": 0.57,
  "stuck_mw_12m_cut": 76.0,
  "consented_not_built_mw_any_age": 77.2,
  "operational_mw": 9.8,
  "operational_homes_equivalent": 7900,
  "refused_5y_mw": 0.0,
  "withdrawn_5y_mw": 0.0,
  "median_months_to_decision": 3.0,
  "rank": 150,
  "tech_mix": {
   "solar": 31.1,
   "onshore wind": 15.0
  },
  "tech_summary": "mostly solar",
  "waiting_vs_running": 4.7,
  "projects": [
   {
    "site_name": "Duddingston Solar Farm and Battery Storage",
    "repd_ref_id": 11382,
    "technology": "Solar Photovoltaics",
    "capacity_mw": 29.9,
    "homes_equivalent": 11000,
    "consented": "2024-04-03",
    "months_waiting": 28.0,
    "status": "Awaiting Construction"
   },
   {
    "site_name": "Trinlaymire Farm - Solar farm, Battery storage",
    "repd_ref_id": 11425,
    "technology": "Solar Photovoltaics",
    "capacity_mw": 29.9,
    "homes_equivalent": 11000,
    "consented": "2024-12-20",
    "months_waiting": 19.4,
    "status": "Awaiting Construction"
   },
   {
    "site_name": "Drumduff Wind Farm Extension",
    "repd_ref_id": 13132,
    "technology": "Wind Onshore",
    "capacity_mw": 15.0,
    "homes_equivalent": 13000,
    "consented": "2024-04-25",
    "months_waiting": 27.3,
    "status": "Awaiting Construction"
   },
   {
    "site_name": "Kinneil Kerse Wastewater Treatment Works - Solar PV Array",
    "repd_ref_id": 19807,
    "technology": "Solar Photovoltaics",
    "capacity_mw": 1.2,
    "homes_equivalent": 400,
    "consented": "2026-01-23",
    "months_waiting": 6.3,
    "status": "Awaiting Construction"
   },
   {
    "site_name": "Heartland Terrace, Heartlands - Solar Photovoltaic Panels",
    "repd_ref_id": 12602,
    "technology": "Solar Photovoltaics",
    "capacity_mw": 0.5,
    "homes_equivalent": 200,
    "consented": "2022-12-16",
    "months_waiting": 43.6,
    "status": "Awaiting Construction"
   },
   {
    "site_name": "Blackburn Waste Water Treatrment, Redhouse Road - Solar Panels",
    "repd_ref_id": 12006,
    "technology": "Solar Photovoltaics",
    "capacity_mw": 0.3,
    "homes_equivalent": 100,
    "consented": "2022-09-30",
    "months_waiting": 46.1,
    "status": "Awaiting Construction"
   },
   {
    "site_name": "Bathgate Waste Water Treatment - Solar Panels",
    "repd_ref_id": 12115,
    "technology": "Solar Photovoltaics",
    "capacity_mw": 0.3,
    "homes_equivalent": 100,
    "consented": "2022-10-05",
    "months_waiting": 45.9,
    "status": "Awaiting Construction"
   },
   {
    "site_name": "The Vu, Roscam House - Solar Photovoltaics Array",
    "repd_ref_id": 14424,
    "technology": "Solar Photovoltaics",
    "capacity_mw": null,
    "homes_equivalent": null,
    "consented": "2023-12-05",
    "months_waiting": 31.9,
    "status": "Awaiting Construction"
   }
  ]
 },
 "number3": {
  "applicable": true,
  "per_household_gbp": 91.96,
  "seat_households": 42817,
  "seat_total_gbp": 3900000,
  "framings": {
   "days_of_home_electricity": 51.0
  },
  "note": "National figure: the per-household cost is the same for every GB seat; only the seat total varies with household count."
 },
 "batteries": {
  "operating_mw": 0.0,
  "building_mw": 0.0,
  "approved_mw": 269.9,
  "approved_24m_mw": 20.0,
  "refused_mw": 0.0,
  "submitted_mw": 0.0,
  "sites": [
   {
    "site_name": "Pond Industrial Park, Whitburn Road - Pond Battery Storage",
    "capacity_mw": 200.0,
    "status": "approved",
    "year": 2025,
    "homes_while_discharging": 701000
   },
   {
    "site_name": "Middlerigg - Battery Energy Storage",
    "capacity_mw": 49.9,
    "status": "approved",
    "year": 2025,
    "homes_while_discharging": 175000
   },
   {
    "site_name": "Duddingston Solar Farm and Battery Storage",
    "capacity_mw": 20.0,
    "status": "approved",
    "year": 2024,
    "homes_while_discharging": 70000
   }
  ]
 },
 "pipeline_projects": [
  {
   "site_name": "Pond Industrial Park, Whitburn Road - Pond Battery Storage",
   "repd_ref_id": 13404,
   "technology": "Battery",
   "capacity_mw": 200.0,
   "homes_equivalent": null,
   "status": "Awaiting Construction",
   "consented": "2025-03-24",
   "refused": null,
   "planning_authority": "Scottish Government (S36)",
   "planning_ref": "ECU00004765",
   "operator": "Banks Renewables",
   "reason": {
    "reason": "consented_no_activity",
    "label": "Approved a year ago \u2014 nothing has happened since",
    "who": "the developer and the network company",
    "evidence": {
     "consent_date": "2025-03-24",
     "years_since_consent": 1.4
    },
    "all_matches": [
     "consented_no_activity"
    ]
   },
   "earliest": null,
   "tec": null
  },
  {
   "site_name": "Middlerigg - Battery Energy Storage",
   "repd_ref_id": 16642,
   "technology": "Battery",
   "capacity_mw": 49.9,
   "homes_equivalent": null,
   "status": "Awaiting Construction",
   "consented": "2025-07-22",
   "refused": null,
   "planning_authority": "West Lothian",
   "planning_ref": "0890/FUL/24",
   "operator": "Galileo Green Energy Scotland Limited",
   "reason": {
    "reason": "consented_no_activity",
    "label": "Approved a year ago \u2014 nothing has happened since",
    "who": "the developer and the network company",
    "evidence": {
     "consent_date": "2025-07-22",
     "years_since_consent": 1.0
    },
    "all_matches": [
     "consented_no_activity"
    ]
   },
   "earliest": null,
   "tec": null
  },
  {
   "site_name": "Duddingston Solar Farm and Battery Storage",
   "repd_ref_id": 11382,
   "technology": "Solar Photovoltaics",
   "capacity_mw": 29.9,
   "homes_equivalent": 11000,
   "status": "Awaiting Construction",
   "consented": "2024-04-03",
   "refused": null,
   "planning_authority": "West Lothian",
   "planning_ref": "1016/FUL/23",
   "operator": "Aithrie Net Zero Solar Limited",
   "reason": {
    "reason": "consented_no_activity",
    "label": "Approved 2 years ago \u2014 nothing has happened since",
    "who": "the developer and the network company",
    "evidence": {
     "consent_date": "2024-04-03",
     "years_since_consent": 2.3
    },
    "all_matches": [
     "consented_no_activity"
    ]
   },
   "earliest": null,
   "tec": null
  },
  {
   "site_name": "Trinlaymire Farm - Solar farm, Battery storage",
   "repd_ref_id": 11425,
   "technology": "Solar Photovoltaics",
   "capacity_mw": 29.9,
   "homes_equivalent": 11000,
   "status": "Awaiting Construction",
   "consented": "2024-12-20",
   "refused": null,
   "planning_authority": "West Lothian",
   "planning_ref": "0568/FUL/24",
   "operator": "Trinlaymire Net Zero Solar Limited",
   "reason": {
    "reason": "consented_no_activity",
    "label": "Approved a year ago \u2014 nothing has happened since",
    "who": "the developer and the network company",
    "evidence": {
     "consent_date": "2024-12-20",
     "years_since_consent": 1.6
    },
    "all_matches": [
     "consented_no_activity"
    ]
   },
   "earliest": null,
   "tec": null
  },
  {
   "site_name": "Duddingston Solar Farm and Battery Storage",
   "repd_ref_id": 11383,
   "technology": "Battery",
   "capacity_mw": 20.0,
   "homes_equivalent": null,
   "status": "Awaiting Construction",
   "consented": "2024-04-03",
   "refused": null,
   "planning_authority": "West Lothian",
   "planning_ref": "1016/FUL/23",
   "operator": "Aithrie Net Zero Solar Limited",
   "reason": {
    "reason": "consented_no_activity",
    "label": "Approved 2 years ago \u2014 nothing has happened since",
    "who": "the developer and the network company",
    "evidence": {
     "consent_date": "2024-04-03",
     "years_since_consent": 2.3
    },
    "all_matches": [
     "consented_no_activity"
    ]
   },
   "earliest": null,
   "tec": null
  },
  {
   "site_name": "Heights Road, Blackridge - Woodend Wind Farm",
   "repd_ref_id": 12422,
   "technology": "Wind Onshore",
   "capacity_mw": 19.8,
   "homes_equivalent": 17000,
   "status": "Application Submitted",
   "consented": null,
   "refused": null,
   "planning_authority": "West Lothian",
   "planning_ref": "0434/FUL/23",
   "operator": "Wind Estate (UK) Ltd",
   "reason": {
    "reason": "planning_overdue",
    "label": "Waiting 3.1 years for a planning decision",
    "who": "West Lothian Council",
    "evidence": {
     "submitted": "2023-06-16",
     "months_waiting": 38
    },
    "all_matches": [
     "planning_overdue"
    ]
   },
   "earliest": null,
   "tec": null
  },
  {
   "site_name": "Drumduff Wind Farm Extension",
   "repd_ref_id": 13132,
   "technology": "Wind Onshore",
   "capacity_mw": 15.0,
   "homes_equivalent": 13000,
   "status": "Awaiting Construction",
   "consented": "2024-04-25",
   "refused": null,
   "planning_authority": "West Lothian",
   "planning_ref": "0504/FUL/23",
   "operator": "Green Power (International) Limited",
   "reason": {
    "reason": "consented_no_activity",
    "label": "Approved 2 years ago \u2014 nothing has happened since",
    "who": "the developer and the network company",
    "evidence": {
     "consent_date": "2024-04-25",
     "years_since_consent": 2.3
    },
    "all_matches": [
     "consented_no_activity"
    ]
   },
   "earliest": null,
   "tec": null
  },
  {
   "site_name": "Southrigg 3 - Wind Turbine",
   "repd_ref_id": 12506,
   "technology": "Wind Onshore",
   "capacity_mw": 4.2,
   "homes_equivalent": 3700,
   "status": "Application Submitted",
   "consented": null,
   "refused": null,
   "planning_authority": "West Lothian",
   "planning_ref": "23/00286/FUL",
   "operator": "SR Wind Limited",
   "reason": {
    "reason": "planning_overdue",
    "label": "Waiting 3.4 years for a planning decision",
    "who": "West Lothian Council",
    "evidence": {
     "submitted": "2023-03-10",
     "months_waiting": 41
    },
    "all_matches": [
     "planning_overdue"
    ]
   },
   "earliest": null,
   "tec": null
  },
  {
   "site_name": "Kinneil Kerse Wastewater Treatment Works - Solar PV Array",
   "repd_ref_id": 19807,
   "technology": "Solar Photovoltaics",
   "capacity_mw": 1.2,
   "homes_equivalent": 400,
   "status": "Awaiting Construction",
   "consented": "2026-01-23",
   "refused": null,
   "planning_authority": "West Lothian",
   "planning_ref": "P/25/0457/FUL",
   "operator": "Scottish Water",
   "reason": {
    "reason": "consented_no_activity",
    "label": "Approved less than a year ago \u2014 nothing has happened since",
    "who": "the developer and the network company",
    "evidence": {
     "consent_date": "2026-01-23",
     "years_since_consent": 0.5
    },
    "all_matches": [
     "consented_no_activity"
    ]
   },
   "earliest": null,
   "tec": null
  }
 ],
 "projects_withheld_unreferenced": 0,
 "neighbours": [
  "S14000095",
  "S14000063",
  "S14000083",
  "S14000082",
  "S14000064"
 ],
 "flags": [
  "curtailment_not_visible"
 ],
 "windows": {
  "curtailment": [
   "2025-08-01",
   "2026-07-31"
  ],
  "repd_as_of": "2026-08-03"
 }
}