 "pcon24cd": "S14000066",
 "name": "Arbroath and Broughty Ferry",
 "nation": "Scotland",
 "number1": {
  "visible": false,
  "note": "No big wind farm on the national grid is mapped to this constituency. Smaller wind farms here can still be paid to switch off by the local network, but those payments are not visible in national data \u2014 the \u00a3 figure is a floor.",
  "invisible_wind": {
   "mw": 5.0,
   "sites": 2
  }
 },
 "number2": {
  "stuck_mw": 95.9,
  "stuck_mw_int": 96,
  "stuck_sites": 7,
  "homes_equivalent": 35000,
  "homes_vs_seat_households": 0.76,
  "stuck_mw_12m_cut": 219.2,
  "consented_not_built_mw_any_age": 219.5,
  "operational_mw": 30.0,
  "operational_homes_equivalent": 13000,
  "refused_5y_mw": 30.8,
  "withdrawn_5y_mw": 0.0,
  "median_months_to_decision": 4.2,
  "rank": 70,
  "tech_mix": {
   "solar": 95.9
  },
  "tech_summary": "all solar",
  "waiting_vs_running": 3.2,
  "projects": [
   {
    "site_name": "Tealing Solar Energy Park - Phase 2",
    "repd_ref_id": 14543,
    "technology": "Solar Photovoltaics",
    "capacity_mw": 110.0,
    "homes_equivalent": 40000,
    "consented": "2025-03-25",
    "months_waiting": 16.3,
    "status": "Awaiting Construction"
   },
   {
    "site_name": "Montreathmont Moor Forest - Solar Farm & Battery Storage",
    "repd_ref_id": 10963,
    "technology": "Solar Photovoltaics",
    "capacity_mw": 42.0,
    "homes_equivalent": 15000,
    "consented": "2022-12-16",
    "months_waiting": 43.6,
    "status": "Awaiting Construction"
   },
   {
    "site_name": "Wellbank - Solar Farm",
    "repd_ref_id": 11365,
    "technology": "Solar Photovoltaics",
    "capacity_mw": 25.0,
    "homes_equivalent": 9100,
    "consented": "2024-02-15",
    "months_waiting": 29.6,
    "status": "Awaiting Construction"
   },
   {
    "site_name": "Parkhill Farm, Letham Grange - Solar Farm",
    "repd_ref_id": 12495,
    "technology": "Solar Photovoltaics",
    "capacity_mw": 18.0,
    "homes_equivalent": 6500,
    "consented": "2023-12-19",
    "months_waiting": 31.5,
    "status": "Awaiting Construction"
   },
   {
    "site_name": "Denfield -  Solar Farm",
    "repd_ref_id": 17328,
    "technology": "Solar Photovoltaics",
    "capacity_mw": 12.5,
    "homes_equivalent": 4500,
    "consented": "2025-02-14",
    "months_waiting": 17.6,
    "status": "Awaiting Construction"
   },
   {
    "site_name": "Kinnell Farm, Kinnell - Solar Farm & Battery Energy Storage",
    "repd_ref_id": 12632,
    "technology": "Solar Photovoltaics",
    "capacity_mw": 10.0,
    "homes_equivalent": 3600,
    "consented": "2023-11-20",
    "months_waiting": 32.4,
    "status": "Awaiting Construction"
   },
   {
    "site_name": "Peasiehill Road, Elliot Industrial Estate - Solar Panels",
    "repd_ref_id": 19110,
    "technology": "Solar Photovoltaics",
    "capacity_mw": 0.8,
    "homes_equivalent": 300,
    "consented": "2025-07-23",
    "months_waiting": 12.4,
    "status": "Awaiting Construction"
   },
   {
    "site_name": "Leisure Centre, Ethiebeaton Park - Solar Panels",
    "repd_ref_id": 14980,
    "technology": "Solar Photovoltaics",
    "capacity_mw": 0.4,
    "homes_equivalent": 100,
    "consented": "2024-02-12",
    "months_waiting": 29.7,
    "status": "Awaiting Construction"
   },
   {
    "site_name": "Lossie Seafoods, Sir William Smith Road - Solar PV Panels",
    "repd_ref_id": 19524,
    "technology": "Solar Photovoltaics",
    "capacity_mw": 0.3,
    "homes_equivalent": 100,
    "consented": "2025-09-26",
    "months_waiting": 10.2,
    "status": "Awaiting Construction"
   },
   {
    "site_name": "Sir William Smith Road, Kirkton Industrial Estate - Solar Panels",
    "repd_ref_id": 13686,
    "technology": "Solar Photovoltaics",
    "capacity_mw": 0.3,
    "homes_equivalent": 100,
    "consented": "2023-06-27",
    "months_waiting": 37.2,
    "status": "Awaiting Construction"
   },
   {
    "site_name": "Police Station, Balunie Drive - Solar PV Array",
    "repd_ref_id": 12592,
    "technology": "Solar Photovoltaics",
    "capacity_mw": 0.2,
    "homes_equivalent": 100,
    "consented": "2023-01-25",
    "months_waiting": 42.2,
    "status": "Awaiting Construction"
   }
  ]
 },
 "number3": {
  "applicable": true,
  "per_household_gbp": 91.96,
  "seat_households": 45808,
  "seat_total_gbp": 4200000,
  "framings": {
   "days_of_home_electricity": 51.0
  },
  "note": "National figure: the per-household cost is the same for every GB seat; only the seat total varies with household count."
 },
 "batteries": {
  "operating_mw": 35.0,
  "building_mw": 0.0,
  "approved_mw": 206.8,
  "approved_24m_mw": 100.0,
  "refused_mw": 49.9,
  "submitted_mw": 0.0,
  "sites": [
   {
    "site_name": "Tealing  Battery Energy Storage Farm",
    "capacity_mw": 80.0,
    "status": "approved",
    "year": 2023,
    "homes_while_discharging": 280000
   },
   {
    "site_name": "Bankhead, Arbirlot - Battery Energy Storage",
    "capacity_mw": 49.9,
    "status": "approved",
    "year": 2024,
    "homes_while_discharging": 175000
   },
   {
    "site_name": "Bindwells Battery Storage Facility",
    "capacity_mw": 49.9,
    "status": "approved",
    "year": 2026,
    "homes_while_discharging": 175000
   },
   {
    "site_name": "Pitkerro Road -  Battery Energy Storage",
    "capacity_mw": 49.9,
    "status": "refused",
    "year": 2025,
    "homes_while_discharging": 175000
   },
   {
    "site_name": "Arbroath Battery Storage",
    "capacity_mw": 35.0,
    "status": "operating",
    "year": 2019,
    "homes_while_discharging": 123000
   },
   {
    "site_name": "Denfield Farm",
    "capacity_mw": 20.0,
    "status": "approved",
    "year": 2024,
    "homes_while_discharging": 70000
   },
   {
    "site_name": "Denfield - Battery Storage Facility",
    "capacity_mw": 7.0,
    "status": "approved",
    "year": 2025,
    "homes_while_discharging": 25000
   }
  ]
 },
 "pipeline_projects": [
  {
   "site_name": "Tealing Solar Energy Park - Phase 2",
   "repd_ref_id": 14543,
   "technology": "Solar Photovoltaics",
   "capacity_mw": 110.0,
   "homes_equivalent": 40000,
   "status": "Awaiting Construction",
   "consented": "2025-03-25",
   "refused": null,
   "planning_authority": "Scottish Government (S36)",
   "planning_ref": "ECU00004882",
   "operator": "Sirius EcoDev Limited",
   "reason": {
    "reason": "connection_date",
    "label": "Cannot connect to the grid until 2027, 2 years after it was approved",
    "who": "the grid operator (NESO) and SSEN Transmission",
    "evidence": {
     "project": "Tealing Solar & Storage",
     "connection_date": "2027-10-31",
     "mw": 80.0,
     "stage": null,
     "source": "NESO TEC register"
    },
    "all_matches": [
     "connection_date",
     "consented_no_activity"
    ]
   },
   "earliest": "2027",
   "tec": {
    "project": "Tealing Solar & Storage",
    "connection_date": "2027-10-31",
    "connection_year": 2027,
    "mw": 80.0,
    "stage": null,
    "who": "the grid operator (NESO) and SSEN Transmission",
    "gate2_outcome": null,
    "source": "NESO TEC register"
   }
  },
  {
   "site_name": "Tealing  Battery Energy Storage Farm",
   "repd_ref_id": 11097,
   "technology": "Battery",
   "capacity_mw": 80.0,
   "homes_equivalent": null,
   "status": "Awaiting Construction",
   "consented": "2023-12-13",
   "refused": null,
   "planning_authority": "Scottish Government (S36)",
   "planning_ref": "ECU00003354",
   "operator": "Sirius EcoDev Limited",
   "reason": {
    "reason": "consented_no_activity",
    "label": "Approved 3 years ago \u2014 nothing has happened since",
    "who": "the developer and the network company",
    "evidence": {
     "consent_date": "2023-12-13",
     "years_since_consent": 2.6
    },
    "all_matches": [
     "consented_no_activity"
    ]
   },
   "earliest": null,
   "tec": null
  },
  {
   "site_name": "Bankhead, Arbirlot - Battery Energy Storage",
   "repd_ref_id": 14985,
   "technology": "Battery",
   "capacity_mw": 49.9,
   "homes_equivalent": null,
   "status": "Awaiting Construction",
   "consented": "2024-09-19",
   "refused": null,
   "planning_authority": "Angus",
   "planning_ref": "24/00178/FULM",
   "operator": "Ecocel Energy Storage Limited",
   "reason": {
    "reason": "consented_no_activity",
    "label": "Approved a year ago \u2014 nothing has happened since",
    "who": "the developer and the network company",
    "evidence": {
     "consent_date": "2024-09-19",
     "years_since_consent": 1.9
    },
    "all_matches": [
     "consented_no_activity"
    ]
   },
   "earliest": null,
   "tec": null
  },
  {
   "site_name": "Bonnyknox Solar Farm",
   "repd_ref_id": 16666,
   "technology": "Solar Photovoltaics",
   "capacity_mw": 49.9,
   "homes_equivalent": 18000,
   "status": "Application Submitted",
   "consented": null,
   "refused": null,
   "planning_authority": "Angus",
   "planning_ref": "25/00339/FULM",
   "operator": "Renewable Energy Systems (RES)",
   "reason": {
    "reason": "planning_overdue",
    "label": "Waiting 13 months for a planning decision",
    "who": "Angus Council",
    "evidence": {
     "submitted": "2025-07-01",
     "months_waiting": 13
    },
    "all_matches": [
     "planning_overdue"
    ]
   },
   "earliest": null,
   "tec": null
  },
  {
   "site_name": "Bindwells Battery Storage Facility",
   "repd_ref_id": 18013,
   "technology": "Battery",
   "capacity_mw": 49.9,
   "homes_equivalent": null,
   "status": "Awaiting Construction",
   "consented": "2026-02-04",
   "refused": null,
   "planning_authority": "Angus",
   "planning_ref": "25/00249/FULM",
   "operator": "OPDE UK Limted",
   "reason": {
    "reason": "consented_no_activity",
    "label": "Approved less than a year ago \u2014 nothing has happened since",
    "who": "the developer and the network company",
    "evidence": {
     "consent_date": "2026-02-04",
     "years_since_consent": 0.5
    },
    "all_matches": [
     "consented_no_activity"
    ]
   },
   "earliest": null,
   "tec": null
  },
  {
   "site_name": "Pitkerro Road -  Battery Energy Storage",
   "repd_ref_id": 18163,
   "technology": "Battery",
   "capacity_mw": 49.9,
   "homes_equivalent": null,
   "status": "Application Refused",
   "consented": null,
   "refused": "2025-08-18",
   "planning_authority": "Dundee City",
   "planning_ref": "24/00813/FULM",
   "operator": "Vital Energi Utilities Limited",
   "reason": {
    "reason": "refused",
    "label": "Refused by Dundee City Council in 2025",
    "who": "Dundee City Council",
    "evidence": {
     "refusal_date": "2025-08-18"
    },
    "all_matches": [
     "refused"
    ]
   },
   "earliest": null,
   "tec": null
  },
  {
   "site_name": "Montreathmont Moor Forest - Solar Farm & Battery Storage",
   "repd_ref_id": 10963,
   "technology": "Solar Photovoltaics",
   "capacity_mw": 42.0,
   "homes_equivalent": 15000,
   "status": "Awaiting Construction",
   "consented": "2022-12-16",
   "refused": null,
   "planning_authority": "Angus",
   "planning_ref": "22/00460/FULM",
   "operator": "Renewable Connections Developments Limited",
   "reason": {
    "reason": "connection_date",
    "label": "Cannot connect to the grid until 2029, 7 years after it was approved",
    "who": "the grid operator (NESO) and SSEN Transmission",
    "evidence": {
     "project": "Montreathmont Moor Forest",
     "connection_date": "2029-10-08",
     "mw": 34.38,
     "stage": null,
     "source": "NESO TEC register"
    },
    "all_matches": [
     "connection_date",
     "consented_no_activity"
    ]
   },
   "earliest": "2029",
   "tec": {
    "project": "Montreathmont Moor Forest",
    "connection_date": "2029-10-08",
    "connection_year": 2029,
    "mw": 34.38,
    "stage": null,
    "who": "the grid operator (NESO) and SSEN Transmission",
    "gate2_outcome": null,
    "source": "NESO TEC register"
   }
  },
  {
   "site_name": "Hillend Of Lownie - Forfar Solar farm",
   "repd_ref_id": 11284,
   "technology": "Solar Photovoltaics",
   "capacity_mw": 30.0,
   "homes_equivalent": 11000,
   "status": "Application Refused",
   "consented": null,
   "refused": "2024-06-12",
   "planning_authority": "Angus",
   "planning_ref": "23/00393/FULM",
   "operator": "Industria Resources Llp",
   "reason": {
    "reason": "refused",
    "label": "Refused by Angus Council in 2024",
    "who": "Angus Council",
    "evidence": {
     "refusal_date": "2024-06-12"
    },
    "all_matches": [
     "refused"
    ]
   },
   "earliest": null,
   "tec": null
  },
  {
   "site_name": "Wellbank - Solar Farm",
   "repd_ref_id": 11365,
   "technology": "Solar Photovoltaics",
   "capacity_mw": 25.0,
   "homes_equivalent": 9100,
   "status": "Awaiting Construction",
   "consented": "2024-02-15",
   "refused": null,
   "planning_authority": "Angus",
   "planning_ref": "23/00424/FULM",
   "operator": "Greentech",
   "reason": {
    "reason": "connection_date",
    "label": "Its grid connection date of 2024 has passed and it is still not generating",
    "who": "the grid operator (NESO) and SSEN Transmission",
    "evidence": {
     "project": "Wellbank Solar Farm",
     "connection_date": "2024-03-01",
     "mw": 25.0,
     "stage": null,
     "source": "NESO TEC register"
    },
    "all_matches": [
     "connection_date",
     "consented_no_activity"
    ]
   },
   "earliest": "2024",
   "tec": {
    "project": "Wellbank Solar Farm",
    "connection_date": "2024-03-01",
    "connection_year": 2024,
    "mw": 25.0,
    "stage": null,
    "who": "the grid operator (NESO) and SSEN Transmission",
    "gate2_outcome": null,
    "source": "NESO TEC register"
   }
  },
  {
   "site_name": "Denfield Farm",
   "repd_ref_id": 14341,
   "technology": "Battery",
   "capacity_mw": 20.0,
   "homes_equivalent": null,
   "status": "Awaiting Construction",
   "consented": "2024-01-05",
   "refused": null,
   "planning_authority": "Angus",
   "planning_ref": "23/00285/FULL",
   "operator": "Seahills Properties Limited",
   "reason": {
    "reason": "consented_no_activity",
    "label": "Approved 3 years ago \u2014 nothing has happened since",
    "who": "the developer and the network company",
    "evidence": {
     "consent_date": "2024-01-05",
     "years_since_consent": 2.6
    },
    "all_matches": [
     "consented_no_activity"
    ]
   },
   "earliest": null,
   "tec": null
  },
  {
   "site_name": "Parkhill Farm, Letham Grange - Solar Farm",
   "repd_ref_id": 12495,
   "technology": "Solar Photovoltaics",
   "capacity_mw": 18.0,
   "homes_equivalent": 6500,
   "status": "Awaiting Construction",
   "consented": "2023-12-19",
   "refused": null,
   "planning_authority": "Angus",
   "planning_ref": "23/00272/FULL",
   "operator": "AlphaReal",
   "reason": {
    "reason": "consented_no_activity",
    "label": "Approved 3 years ago \u2014 nothing has happened since",
    "who": "the developer and the network company",
    "evidence": {
     "consent_date": "2023-12-19",
     "years_since_consent": 2.6
    },
    "all_matches": [
     "consented_no_activity"
    ]
   },
   "earliest": null,
   "tec": null
  },
  {
   "site_name": "Denfield -  Solar Farm",
   "repd_ref_id": 17328,
   "technology": "Solar Photovoltaics",
   "capacity_mw": 12.5,
   "homes_equivalent": 4500,
   "status": "Awaiting Construction",
   "consented": "2025-02-14",
   "refused": null,
   "planning_authority": "Angus",
   "planning_ref": "24/00589/FULL",
   "operator": "Peter J Stirling Limited",
   "reason": {
    "reason": "consented_no_activity",
    "label": "Approved a year ago \u2014 nothing has happened since",
    "who": "the developer and the network company",
    "evidence": {
     "consent_date": "2025-02-14",
     "years_since_consent": 1.5
    },
    "all_matches": [
     "consented_no_activity"
    ]
   },
   "earliest": null,
   "tec": null
  },
  {
   "site_name": "Baldovie Industrial Estate (Forties Road)",
   "repd_ref_id": 6171,
   "technology": "EfW Incineration",
   "capacity_mw": 10.0,
   "homes_equivalent": null,
   "status": "Under Construction",
   "consented": "2017-03-21",
   "refused": null,
   "planning_authority": "Dundee City",
   "planning_ref": "16/00916/FULM",
   "operator": "MVV Environment",
   "reason": {
    "reason": "building",
    "label": "Under construction",
    "who": "the developer",
    "evidence": {},
    "all_matches": [
     "building"
    ]
   },
   "earliest": "2027 (in construction)",
   "tec": null
  },
  {
   "site_name": "Kinnell Farm, Kinnell - Solar Farm & Battery Energy Storage",
   "repd_ref_id": 12632,
   "technology": "Solar Photovoltaics",
   "capacity_mw": 10.0,
   "homes_equivalent": 3600,
   "status": "Awaiting Construction",
   "consented": "2023-11-20",
   "refused": null,
   "planning_authority": "Angus",
   "planning_ref": "23/00484/FULL",
   "operator": "One Planet Developments Limited",
   "reason": {
    "reason": "consented_no_activity",
    "label": "Approved 3 years ago \u2014 nothing has happened since",
    "who": "the developer and the network company",
    "evidence": {
     "consent_date": "2023-11-20",
     "years_since_consent": 2.7
    },
    "all_matches": [
     "consented_no_activity"
    ]
   },
   "earliest": null,
   "tec": null
  },
  {
   "site_name": "Denfield - Battery Storage Facility",
   "repd_ref_id": 17329,
   "technology": "Battery",
   "capacity_mw": 7.0,
   "homes_equivalent": null,
   "status": "Awaiting Construction",
   "consented": "2025-02-14",
   "refused": null,
   "planning_authority": "Angus",
   "planning_ref": "24/00589/FULL",
   "operator": "Peter J Stirling Limited",
   "reason": {
    "reason": "consented_no_activity",
    "label": "Approved a year ago \u2014 nothing has happened since",
    "who": "the developer and the network company",
    "evidence": {
     "consent_date": "2025-02-14",
     "years_since_consent": 1.5
    },
    "all_matches": [
     "consented_no_activity"
    ]
   },
   "earliest": null,
   "tec": null
  }
 ],
 "projects_withheld_unreferenced": 0,
 "neighbours": [
  "S14000075",
  "S14000065"
 ],
 "flags": [
  "curtailment_not_visible"
 ],
 "windows": {
  "curtailment": [
   "2025-08-01",
   "2026-07-31"
  ],
  "repd_as_of": "2026-08-03"
 }
}