 "pcon24cd": "S14000064",
 "name": "Alloa and Grangemouth",
 "nation": "Scotland",
 "number1": {
  "visible": false,
  "note": "No big wind farm on the national grid is mapped to this constituency. Smaller wind farms here can still be paid to switch off by the local network, but those payments are not visible in national data \u2014 the \u00a3 figure is a floor.",
  "invisible_wind": {
   "mw": 60.8,
   "sites": 4
  }
 },
 "number2": {
  "stuck_mw": 1.7,
  "stuck_mw_int": 2,
  "stuck_sites": 3,
  "homes_equivalent": 600,
  "homes_vs_seat_households": 0.01,
  "stuck_mw_12m_cut": 2.0,
  "consented_not_built_mw_any_age": 2.0,
  "operational_mw": 65.8,
  "operational_homes_equivalent": 55000,
  "refused_5y_mw": 0.0,
  "withdrawn_5y_mw": 0.0,
  "median_months_to_decision": 1.8,
  "rank": 357,
  "tech_mix": {
   "solar": 1.7
  },
  "tech_summary": "all solar",
  "waiting_vs_running": 0.0,
  "projects": [
   {
    "site_name": "Alloa Wastewater Treatment Works, Bowhouse Road - Solar Panels",
    "repd_ref_id": 13537,
    "technology": "Solar Photovoltaics",
    "capacity_mw": 0.9,
    "homes_equivalent": 300,
    "consented": "2023-07-03",
    "months_waiting": 37.0,
    "status": "Awaiting Construction"
   },
   {
    "site_name": "West Carron Works, Stenhouse Road - Solar Array",
    "repd_ref_id": 13759,
    "technology": "Solar Photovoltaics",
    "capacity_mw": 0.6,
    "homes_equivalent": 200,
    "consented": "2023-06-16",
    "months_waiting": 37.6,
    "status": "Awaiting Construction"
   },
   {
    "site_name": "Whyte and Mackay - Solar Panels",
    "repd_ref_id": 17008,
    "technology": "Solar Photovoltaics",
    "capacity_mw": 0.2,
    "homes_equivalent": 100,
    "consented": "2024-10-18",
    "months_waiting": 21.5,
    "status": "Awaiting Construction"
   },
   {
    "site_name": "Forth Valley Royal Hospital, Stirling Road - Solar Array",
    "repd_ref_id": 14351,
    "technology": "Solar Photovoltaics",
    "capacity_mw": 0.2,
    "homes_equivalent": 100,
    "consented": "2023-08-04",
    "months_waiting": 36.0,
    "status": "Awaiting Construction"
   },
   {
    "site_name": "Carrongrange Park - Hydro Powerhouse",
    "repd_ref_id": 17722,
    "technology": "Small Hydro",
    "capacity_mw": null,
    "homes_equivalent": null,
    "consented": "2025-02-07",
    "months_waiting": 17.8,
    "status": "Under Construction"
   },
   {
    "site_name": "Central Boulevard, Central Park - Solar Panels",
    "repd_ref_id": 18324,
    "technology": "Solar Photovoltaics",
    "capacity_mw": null,
    "homes_equivalent": null,
    "consented": "2025-04-04",
    "months_waiting": 16.0,
    "status": "Awaiting Construction"
   }
  ]
 },
 "number3": {
  "applicable": true,
  "per_household_gbp": 91.96,
  "seat_households": 43681,
  "seat_total_gbp": 4000000,
  "framings": {
   "days_of_home_electricity": 51.0
  },
  "note": "National figure: the per-household cost is the same for every GB seat; only the seat total varies with household count."
 },
 "batteries": {
  "operating_mw": 0.0,
  "building_mw": 500.0,
  "approved_mw": 25.2,
  "approved_24m_mw": 25.0,
  "refused_mw": 0.0,
  "submitted_mw": 35.0,
  "sites": [
   {
    "site_name": "Devilla Energy Storage Facility",
    "capacity_mw": 500.0,
    "status": "building",
    "year": 2023,
    "homes_while_discharging": 1752000
   },
   {
    "site_name": "Windburn Wind Farm",
    "capacity_mw": 35.0,
    "status": "submitted",
    "year": null,
    "homes_while_discharging": 123000
   },
   {
    "site_name": "Bankhead Farm - Energy Storage System",
    "capacity_mw": 25.0,
    "status": "approved",
    "year": 2024,
    "homes_while_discharging": 88000
   },
   {
    "site_name": "Abbotsinch Road - Micro Energy Storage Facility",
    "capacity_mw": 0.2,
    "status": "approved",
    "year": 2025,
    "homes_while_discharging": 700
   }
  ]
 },
 "pipeline_projects": [
  {
   "site_name": "Devilla Energy Storage Facility",
   "repd_ref_id": 9248,
   "technology": "Battery",
   "capacity_mw": 500.0,
   "homes_equivalent": null,
   "status": "Under Construction",
   "consented": "2023-12-13",
   "refused": null,
   "planning_authority": "Scottish Government (S36)",
   "planning_ref": "ECU00003469",
   "operator": "Alcemi Storage Development Limited",
   "reason": {
    "reason": "gate2",
    "label": "Cleared the grid queue review, so it now has a firm connection date",
    "who": "the grid operator (NESO)",
    "evidence": {
     "project": "Alcemi Devilla Battery Energy Storage Facility",
     "gate2_outcome": "Cleared the grid queue review, so it now has a firm connection date"
    },
    "all_matches": [
     "gate2",
     "connection_date",
     "building"
    ]
   },
   "earliest": "2027",
   "tec": {
    "project": "Alcemi Devilla Battery Energy Storage Facility",
    "connection_date": "2027-10-30",
    "connection_year": 2027,
    "mw": 500.0,
    "stage": null,
    "who": "the grid operator (NESO) and SP Transmission",
    "gate2_outcome": "Cleared the grid queue review, so it now has a firm connection date",
    "source": "NESO TEC register"
   }
  },
  {
   "site_name": "BOC Limited, Wholeflats Road - Green Hydrogen Electrolyser Plant",
   "repd_ref_id": 17066,
   "technology": "Hydrogen",
   "capacity_mw": 200.0,
   "homes_equivalent": null,
   "status": "Application Submitted",
   "consented": null,
   "refused": null,
   "planning_authority": "Falkirk",
   "planning_ref": "P/25/0544/PPP",
   "operator": "RWE Generation UK Plc",
   "reason": {
    "reason": "in_planning",
    "label": "Applied in 2025, still waiting for a decision",
    "who": "Falkirk Council",
    "evidence": {
     "submitted": "2025-12-19",
     "months_waiting": 7
    },
    "all_matches": [
     "in_planning"
    ]
   },
   "earliest": null,
   "tec": null
  },
  {
   "site_name": "Windburn Wind Farm",
   "repd_ref_id": 13625,
   "technology": "Wind Onshore",
   "capacity_mw": 65.0,
   "homes_equivalent": 57000,
   "status": "Application Submitted",
   "consented": null,
   "refused": null,
   "planning_authority": "Scottish Government (S36)",
   "planning_ref": "ECU00004782",
   "operator": "Octopus Energy / Wind 2 Limited",
   "reason": {
    "reason": "planning_overdue",
    "label": "Waiting 14 months for a planning decision",
    "who": "the Scottish Government (it decides big energy projects)",
    "evidence": {
     "submitted": "2025-06-05",
     "months_waiting": 14
    },
    "all_matches": [
     "planning_overdue",
     "gate2",
     "connection_date"
    ]
   },
   "earliest": "2034",
   "tec": {
    "project": "Windburn Wind Farm",
    "connection_date": "2034-10-01",
    "connection_year": 2034,
    "mw": 75.0,
    "stage": null,
    "who": "the grid operator (NESO) and SP Transmission",
    "gate2_outcome": "Still in the grid queue review \u2014 no firm connection date yet",
    "source": "NESO TEC register"
   }
  },
  {
   "site_name": "Windburn Wind Farm",
   "repd_ref_id": 13626,
   "technology": "Battery",
   "capacity_mw": 35.0,
   "homes_equivalent": null,
   "status": "Application Submitted",
   "consented": null,
   "refused": null,
   "planning_authority": "Scottish Government (S36)",
   "planning_ref": "ECU00004782",
   "operator": "Octopus Energy / Wind 2 Limited",
   "reason": {
    "reason": "planning_overdue",
    "label": "Waiting 14 months for a planning decision",
    "who": "the Scottish Government (it decides big energy projects)",
    "evidence": {
     "submitted": "2025-06-05",
     "months_waiting": 14
    },
    "all_matches": [
     "planning_overdue"
    ]
   },
   "earliest": null,
   "tec": null
  },
  {
   "site_name": "Bankhead Farm - Energy Storage System",
   "repd_ref_id": 14450,
   "technology": "Battery",
   "capacity_mw": 25.0,
   "homes_equivalent": null,
   "status": "Awaiting Construction",
   "consented": "2024-05-02",
   "refused": null,
   "planning_authority": "Clackmannanshire",
   "planning_ref": "24/00001/FULL",
   "operator": "Low Carbon Storage",
   "reason": {
    "reason": "connection_date",
    "label": "Cannot connect to the grid until 2030, 6 years after it was approved",
    "who": "the grid operator (NESO) and SP Transmission",
    "evidence": {
     "project": "Bankhead 25MW BESS",
     "connection_date": "2030-04-30",
     "mw": 25.0,
     "stage": null,
     "source": "NESO TEC register"
    },
    "all_matches": [
     "connection_date",
     "consented_no_activity"
    ]
   },
   "earliest": "2030",
   "tec": {
    "project": "Bankhead 25MW BESS",
    "connection_date": "2030-04-30",
    "connection_year": 2030,
    "mw": 25.0,
    "stage": null,
    "who": "the grid operator (NESO) and SP Transmission",
    "gate2_outcome": null,
    "source": "NESO TEC register"
   }
  },
  {
   "site_name": "Caledon Green - Gas Powered Electricity Generation Facility",
   "repd_ref_id": 8795,
   "technology": "Landfill Gas",
   "capacity_mw": 22.5,
   "homes_equivalent": null,
   "status": "Awaiting Construction",
   "consented": "2021-06-14",
   "refused": null,
   "planning_authority": "Falkirk",
   "planning_ref": "P/21/0062/FUL",
   "operator": "Claverhouse Generation Limited",
   "reason": {
    "reason": "consented_no_activity",
    "label": "Approved 5 years ago \u2014 nothing has happened since",
    "who": "the developer and the network company",
    "evidence": {
     "consent_date": "2021-06-14",
     "years_since_consent": 5.1
    },
    "all_matches": [
     "consented_no_activity"
    ]
   },
   "earliest": null,
   "tec": null
  },
  {
   "site_name": "CalaChem Fine Chemicals (Grangemouth)",
   "repd_ref_id": 5352,
   "technology": "EfW Incineration",
   "capacity_mw": 21.5,
   "homes_equivalent": null,
   "status": "Under Construction",
   "consented": "2017-01-18",
   "refused": null,
   "planning_authority": "Falkirk",
   "planning_ref": "P/16/0321/FUL",
   "operator": "Earls Gate Energy Centre",
   "reason": {
    "reason": "building",
    "label": "Under construction",
    "who": "the developer",
    "evidence": {},
    "all_matches": [
     "building"
    ]
   },
   "earliest": "2027 (in construction)",
   "tec": null
  }
 ],
 "projects_withheld_unreferenced": 0,
 "neighbours": [
  "S14000068",
  "S14000083",
  "S14000105",
  "S14000076"
 ],
 "flags": [
  "curtailment_not_visible"
 ],
 "windows": {
  "curtailment": [
   "2025-08-01",
   "2026-07-31"
  ],
  "repd_as_of": "2026-08-03"
 }
}