 "pcon24cd": "E14001579",
 "name": "West Worcestershire",
 "nation": "England",
 "number1": {
  "visible": false,
  "note": "No big wind farm on the national grid is mapped to this constituency. Smaller wind farms here can still be paid to switch off by the local network, but those payments are not visible in national data \u2014 the \u00a3 figure is a floor.",
  "invisible_wind": {
   "mw": 1.2,
   "sites": 1
  }
 },
 "number2": {
  "stuck_mw": 5.8,
  "stuck_mw_int": 6,
  "stuck_sites": 4,
  "homes_equivalent": 2100,
  "homes_vs_seat_households": 0.05,
  "stuck_mw_12m_cut": 31.0,
  "consented_not_built_mw_any_age": 31.0,
  "operational_mw": 95.1,
  "operational_homes_equivalent": 35000,
  "refused_5y_mw": 70.9,
  "withdrawn_5y_mw": 0.0,
  "median_months_to_decision": 4.3,
  "rank": 252,
  "tech_mix": {
   "solar": 5.8
  },
  "tech_summary": "all solar",
  "waiting_vs_running": 0.1,
  "projects": [
   {
    "site_name": "Home Farm",
    "repd_ref_id": 14304,
    "technology": "Solar Photovoltaics",
    "capacity_mw": 25.0,
    "homes_equivalent": 9100,
    "consented": "2025-05-16",
    "months_waiting": 14.6,
    "status": "Awaiting Construction"
   },
   {
    "site_name": "Stockton Court farm",
    "repd_ref_id": 5713,
    "technology": "Solar Photovoltaics",
    "capacity_mw": 5.0,
    "homes_equivalent": 1800,
    "consented": "2017-04-05",
    "months_waiting": 111.9,
    "status": "Awaiting Construction"
   },
   {
    "site_name": "Vamix Factory, Martley Road - Solar Panels",
    "repd_ref_id": 13964,
    "technology": "Solar Photovoltaics",
    "capacity_mw": 0.4,
    "homes_equivalent": 100,
    "consented": "2023-07-10",
    "months_waiting": 36.8,
    "status": "Awaiting Construction"
   },
   {
    "site_name": "Holdsworth Distribution Centre, Hinton On The Green - Solar Panels",
    "repd_ref_id": 14334,
    "technology": "Solar Photovoltaics",
    "capacity_mw": 0.2,
    "homes_equivalent": 100,
    "consented": "2023-11-08",
    "months_waiting": 32.8,
    "status": "Awaiting Construction"
   },
   {
    "site_name": "Millers Court Farm, Birts Street - Solar Photovoltaic Array",
    "repd_ref_id": 18459,
    "technology": "Solar Photovoltaics",
    "capacity_mw": 0.2,
    "homes_equivalent": 100,
    "consented": "2025-05-07",
    "months_waiting": 14.9,
    "status": "Awaiting Construction"
   },
   {
    "site_name": "The Malvern Splash, Priory Road - Solar panels",
    "repd_ref_id": 16407,
    "technology": "Solar Photovoltaics",
    "capacity_mw": 0.2,
    "homes_equivalent": 100,
    "consented": "2024-07-18",
    "months_waiting": 24.5,
    "status": "Awaiting Construction"
   }
  ]
 },
 "number3": {
  "applicable": true,
  "per_household_gbp": 91.96,
  "seat_households": 43397,
  "seat_total_gbp": 4000000,
  "framings": {
   "days_of_home_electricity": 51.0
  },
  "note": "National figure: the per-household cost is the same for every GB seat; only the seat total varies with household count."
 },
 "batteries": {
  "operating_mw": 0.0,
  "building_mw": 0.0,
  "approved_mw": 40.0,
  "approved_24m_mw": 40.0,
  "refused_mw": 0.0,
  "submitted_mw": 60.0,
  "sites": [
   {
    "site_name": "The Waddings, Knighton-On-Teme - Battery Energy Storage System",
    "capacity_mw": 60.0,
    "status": "submitted",
    "year": null,
    "homes_while_discharging": 210000
   },
   {
    "site_name": "Whitehouse Farm Energy Barn",
    "capacity_mw": 40.0,
    "status": "approved",
    "year": 2017,
    "homes_while_discharging": 140000
   }
  ]
 },
 "pipeline_projects": [
  {
   "site_name": "The Waddings, Knighton-On-Teme - Battery Energy Storage System",
   "repd_ref_id": 17849,
   "technology": "Battery",
   "capacity_mw": 60.0,
   "homes_equivalent": null,
   "status": "Application Submitted",
   "consented": null,
   "refused": null,
   "planning_authority": "Malvern Hills",
   "planning_ref": "M/24/01660/FUL",
   "operator": "Integrum SPV 22298 Limited",
   "reason": {
    "reason": "planning_overdue",
    "label": "Waiting 20 months for a planning decision",
    "who": "Malvern Hills Council",
    "evidence": {
     "submitted": "2024-12-04",
     "months_waiting": 20
    },
    "all_matches": [
     "planning_overdue"
    ]
   },
   "earliest": null,
   "tec": null
  },
  {
   "site_name": "Chapel Hill - Solar Arrays",
   "repd_ref_id": 14620,
   "technology": "Solar Photovoltaics",
   "capacity_mw": 49.9,
   "homes_equivalent": 18000,
   "status": "Application Refused",
   "consented": null,
   "refused": "2025-11-10",
   "planning_authority": "Malvern Hills",
   "planning_ref": "M/24/01781/FUL",
   "operator": "JBM Solar Projects Limited",
   "reason": {
    "reason": "refused",
    "label": "Refused by Malvern Hills Council in 2025",
    "who": "Malvern Hills Council",
    "evidence": {
     "refusal_date": "2025-11-10"
    },
    "all_matches": [
     "refused"
    ]
   },
   "earliest": null,
   "tec": null
  },
  {
   "site_name": "Whitehouse Farm Energy Barn",
   "repd_ref_id": 7987,
   "technology": "Battery",
   "capacity_mw": 40.0,
   "homes_equivalent": null,
   "status": "Awaiting Construction",
   "consented": "2017-11-29",
   "refused": null,
   "planning_authority": "Malvern Hills",
   "planning_ref": "17/01504/FUL",
   "operator": "Bluefield Solar Income Fund",
   "reason": {
    "reason": "consented_no_activity",
    "label": "Approved 9 years ago \u2014 nothing has happened since",
    "who": "the developer and the network company",
    "evidence": {
     "consent_date": "2017-11-29",
     "years_since_consent": 8.7
    },
    "all_matches": [
     "consented_no_activity"
    ]
   },
   "earliest": null,
   "tec": null
  },
  {
   "site_name": "Home Farm",
   "repd_ref_id": 14304,
   "technology": "Solar Photovoltaics",
   "capacity_mw": 25.0,
   "homes_equivalent": 9100,
   "status": "Awaiting Construction",
   "consented": "2025-05-16",
   "refused": null,
   "planning_authority": "Wychavon",
   "planning_ref": "23/00499/FUL",
   "operator": "Canadian Solar / Novergy",
   "reason": {
    "reason": "consented_no_activity",
    "label": "Approved a year ago \u2014 nothing has happened since",
    "who": "the developer and the network company",
    "evidence": {
     "consent_date": "2025-05-16",
     "years_since_consent": 1.2
    },
    "all_matches": [
     "consented_no_activity"
    ]
   },
   "earliest": null,
   "tec": null
  },
  {
   "site_name": "Sinton Green Solar Farm",
   "repd_ref_id": 9133,
   "technology": "Solar Photovoltaics",
   "capacity_mw": 21.0,
   "homes_equivalent": 7600,
   "status": "Application Refused",
   "consented": null,
   "refused": "2023-01-25",
   "planning_authority": "Malvern Hills",
   "planning_ref": "21/01846/FUL",
   "operator": "BRL Solar UK Limited",
   "reason": {
    "reason": "refused",
    "label": "Refused by Malvern Hills Council in 2023",
    "who": "Malvern Hills Council",
    "evidence": {
     "refusal_date": "2023-01-25"
    },
    "all_matches": [
     "refused"
    ]
   },
   "earliest": null,
   "tec": null
  },
  {
   "site_name": "Fitcher Brook Solar Farm",
   "repd_ref_id": 14037,
   "technology": "Solar Photovoltaics",
   "capacity_mw": 19.0,
   "homes_equivalent": 6900,
   "status": "Application Submitted",
   "consented": null,
   "refused": null,
   "planning_authority": "Malvern Hills",
   "planning_ref": "M/23/01698/FUL",
   "operator": "Tyler Hill Renewables Limited",
   "reason": {
    "reason": "planning_overdue",
    "label": "Waiting 2.6 years for a planning decision",
    "who": "Malvern Hills Council",
    "evidence": {
     "submitted": "2023-12-19",
     "months_waiting": 31
    },
    "all_matches": [
     "planning_overdue"
    ]
   },
   "earliest": null,
   "tec": null
  },
  {
   "site_name": "Stockton Court farm",
   "repd_ref_id": 5713,
   "technology": "Solar Photovoltaics",
   "capacity_mw": 5.0,
   "homes_equivalent": 1800,
   "status": "Awaiting Construction",
   "consented": "2017-04-05",
   "refused": "2016-04-13",
   "planning_authority": "Malvern Hills",
   "planning_ref": "15/01017/FUL",
   "operator": "Renewable Power Exchange",
   "reason": {
    "reason": "consented_no_activity",
    "label": "Approved 9 years ago \u2014 nothing has happened since",
    "who": "the developer and the network company",
    "evidence": {
     "consent_date": "2017-04-05",
     "years_since_consent": 9.3
    },
    "all_matches": [
     "consented_no_activity"
    ]
   },
   "earliest": null,
   "tec": null
  },
  {
   "site_name": "Hangmans Lane",
   "repd_ref_id": 6258,
   "technology": "EfW Incineration",
   "capacity_mw": 5.0,
   "homes_equivalent": null,
   "status": "Under Construction",
   "consented": "2016-10-11",
   "refused": "2015-12-22",
   "planning_authority": "Malvern Hills",
   "planning_ref": "15/000025/CL",
   "operator": "Private Developer",
   "reason": {
    "reason": "building",
    "label": "Under construction",
    "who": "the developer",
    "evidence": {},
    "all_matches": [
     "building"
    ]
   },
   "earliest": "2027 (in construction)",
   "tec": null
  }
 ],
 "projects_withheld_unreferenced": 0,
 "neighbours": [
  "E14001542",
  "E14001203",
  "E14001240",
  "E14001395",
  "E14001597",
  "E14001601",
  "E14001493"
 ],
 "flags": [
  "curtailment_not_visible"
 ],
 "windows": {
  "curtailment": [
   "2025-08-01",
   "2026-07-31"
  ],
  "repd_as_of": "2026-08-03"
 }
}