 "pcon24cd": "E14001493",
 "name": "South Shropshire",
 "nation": "England",
 "number1": {
  "visible": false,
  "note": "No big wind farm on the national grid is mapped to this constituency. Smaller wind farms here can still be paid to switch off by the local network, but those payments are not visible in national data \u2014 the \u00a3 figure is a floor.",
  "invisible_wind": {
   "mw": 0.0,
   "sites": 0
  }
 },
 "number2": {
  "stuck_mw": 112.2,
  "stuck_mw_int": 112,
  "stuck_sites": 6,
  "homes_equivalent": 41000,
  "homes_vs_seat_households": 0.97,
  "stuck_mw_12m_cut": 148.2,
  "consented_not_built_mw_any_age": 148.5,
  "operational_mw": 77.9,
  "operational_homes_equivalent": 28000,
  "refused_5y_mw": 0.0,
  "withdrawn_5y_mw": 0.0,
  "median_months_to_decision": 5.6,
  "rank": 56,
  "tech_mix": {
   "solar": 112.2
  },
  "tech_summary": "all solar",
  "waiting_vs_running": 1.4,
  "projects": [
   {
    "site_name": "Brick House Farm - Solar Farm",
    "repd_ref_id": 10513,
    "technology": "Solar Photovoltaics",
    "capacity_mw": 49.9,
    "homes_equivalent": 18000,
    "consented": "2022-10-21",
    "months_waiting": 45.4,
    "status": "Awaiting Construction"
   },
   {
    "site_name": "Rock Farm - Solar Farm",
    "repd_ref_id": 10635,
    "technology": "Solar Photovoltaics",
    "capacity_mw": 40.0,
    "homes_equivalent": 15000,
    "consented": "2023-09-25",
    "months_waiting": 34.3,
    "status": "Under Construction"
   },
   {
    "site_name": "Berrington Farm - Solar Array",
    "repd_ref_id": 12266,
    "technology": "Solar Photovoltaics",
    "capacity_mw": 30.0,
    "homes_equivalent": 11000,
    "consented": "2025-05-02",
    "months_waiting": 15.0,
    "status": "Awaiting Construction"
   },
   {
    "site_name": "Kemberton - Solar Farm",
    "repd_ref_id": 11202,
    "technology": "Solar Photovoltaics",
    "capacity_mw": 22.0,
    "homes_equivalent": 8000,
    "consented": "2024-02-22",
    "months_waiting": 29.3,
    "status": "Awaiting Construction"
   },
   {
    "site_name": "Swancote Farm -Solar Panels",
    "repd_ref_id": 17453,
    "technology": "Solar Photovoltaics",
    "capacity_mw": 5.0,
    "homes_equivalent": 1800,
    "consented": "2025-01-21",
    "months_waiting": 18.4,
    "status": "Awaiting Construction"
   },
   {
    "site_name": "The Conery - Wind Turbine",
    "repd_ref_id": 18149,
    "technology": "Wind Onshore",
    "capacity_mw": 1.0,
    "homes_equivalent": 900,
    "consented": "2025-06-20",
    "months_waiting": 13.4,
    "status": "Awaiting Construction"
   },
   {
    "site_name": "Kerry Ingredients & Flavours - Solar Panels",
    "repd_ref_id": 14068,
    "technology": "Solar Photovoltaics",
    "capacity_mw": 0.3,
    "homes_equivalent": 100,
    "consented": null,
    "months_waiting": null,
    "status": "Under Construction"
   },
   {
    "site_name": "Sainsburys Supermarkets, Dun Cow Road - Solar Panels",
    "repd_ref_id": 14831,
    "technology": "Solar Photovoltaics",
    "capacity_mw": 0.2,
    "homes_equivalent": 100,
    "consented": "2023-10-04",
    "months_waiting": 34.0,
    "status": "Awaiting Construction"
   },
   {
    "site_name": "Syspal, Cockshutt Lane - Solar Panels",
    "repd_ref_id": 12879,
    "technology": "Solar Photovoltaics",
    "capacity_mw": 0.2,
    "homes_equivalent": 100,
    "consented": "2023-01-20",
    "months_waiting": 42.4,
    "status": "Awaiting Construction"
   },
   {
    "site_name": "Bridgnorth Garden Centre - Storage Warehouse",
    "repd_ref_id": 12255,
    "technology": "Solar Photovoltaics",
    "capacity_mw": null,
    "homes_equivalent": null,
    "consented": "2023-03-30",
    "months_waiting": 40.1,
    "status": "Awaiting Construction"
   }
  ]
 },
 "number3": {
  "applicable": true,
  "per_household_gbp": 91.96,
  "seat_households": 41990,
  "seat_total_gbp": 3900000,
  "framings": {
   "days_of_home_electricity": 51.0
  },
  "note": "National figure: the per-household cost is the same for every GB seat; only the seat total varies with household count."
 },
 "batteries": {
  "operating_mw": 0.0,
  "building_mw": 12.0,
  "approved_mw": 163.0,
  "approved_24m_mw": 40.0,
  "refused_mw": 0.0,
  "submitted_mw": 100.0,
  "sites": [
   {
    "site_name": "Buildwas - Battery Energy Storage",
    "capacity_mw": 100.0,
    "status": "approved",
    "year": 2026,
    "homes_while_discharging": 350000
   },
   {
    "site_name": "Pelham Road, Upton Magna - Battery Energy Storage System",
    "capacity_mw": 100.0,
    "status": "submitted",
    "year": null,
    "homes_while_discharging": 350000
   },
   {
    "site_name": "Hollydale, Buildwas Road - Battery Storage",
    "capacity_mw": 40.0,
    "status": "approved",
    "year": 2024,
    "homes_while_discharging": 140000
   },
   {
    "site_name": "Steventon Road - Battery Energy Storage",
    "capacity_mw": 23.0,
    "status": "approved",
    "year": 2024,
    "homes_while_discharging": 81000
   },
   {
    "site_name": "Rock Farm - Solar Farm",
    "capacity_mw": 12.0,
    "status": "building",
    "year": 2023,
    "homes_while_discharging": 42000
   }
  ]
 },
 "pipeline_projects": [
  {
   "site_name": "Buildwas - Battery Energy Storage",
   "repd_ref_id": 18395,
   "technology": "Battery",
   "capacity_mw": 100.0,
   "homes_equivalent": null,
   "status": "Awaiting Construction",
   "consented": "2026-04-22",
   "refused": null,
   "planning_authority": "Shropshire",
   "planning_ref": "25/01270/FUL",
   "operator": "Greenfield Energy Developments Limited",
   "reason": {
    "reason": "consented_no_activity",
    "label": "Approved less than a year ago \u2014 nothing has happened since",
    "who": "the developer and the network company",
    "evidence": {
     "consent_date": "2026-04-22",
     "years_since_consent": 0.3
    },
    "all_matches": [
     "consented_no_activity"
    ]
   },
   "earliest": null,
   "tec": null
  },
  {
   "site_name": "Pelham Road, Upton Magna - Battery Energy Storage System",
   "repd_ref_id": 18958,
   "technology": "Battery",
   "capacity_mw": 100.0,
   "homes_equivalent": null,
   "status": "Application Submitted",
   "consented": null,
   "refused": null,
   "planning_authority": "Shropshire",
   "planning_ref": "25/01638/FUL",
   "operator": "Elgin Energy Esco Limited",
   "reason": {
    "reason": "planning_overdue",
    "label": "Waiting 15 months for a planning decision",
    "who": "Shropshire Council",
    "evidence": {
     "submitted": "2025-05-01",
     "months_waiting": 15
    },
    "all_matches": [
     "planning_overdue"
    ]
   },
   "earliest": null,
   "tec": null
  },
  {
   "site_name": "Brick House Farm - Solar Farm",
   "repd_ref_id": 10513,
   "technology": "Solar Photovoltaics",
   "capacity_mw": 49.9,
   "homes_equivalent": 18000,
   "status": "Awaiting Construction",
   "consented": "2022-10-21",
   "refused": null,
   "planning_authority": "Shropshire",
   "planning_ref": "22/02565/FUL",
   "operator": "Bluefield Renewwable Developments Limited",
   "reason": {
    "reason": "consented_no_activity",
    "label": "Approved 4 years ago \u2014 nothing has happened since",
    "who": "the developer and the network company",
    "evidence": {
     "consent_date": "2022-10-21",
     "years_since_consent": 3.8
    },
    "all_matches": [
     "consented_no_activity"
    ]
   },
   "earliest": null,
   "tec": null
  },
  {
   "site_name": "Rock Farm - Solar Farm",
   "repd_ref_id": 10635,
   "technology": "Solar Photovoltaics",
   "capacity_mw": 40.0,
   "homes_equivalent": 15000,
   "status": "Under Construction",
   "consented": "2023-09-25",
   "refused": null,
   "planning_authority": "Shropshire",
   "planning_ref": "22/05424/EIA",
   "operator": "Anglo Renewables",
   "reason": {
    "reason": "building",
    "label": "Under construction",
    "who": "the developer",
    "evidence": {},
    "all_matches": [
     "building"
    ]
   },
   "earliest": "2027 (in construction)",
   "tec": null
  },
  {
   "site_name": "Hollydale, Buildwas Road - Battery Storage",
   "repd_ref_id": 13410,
   "technology": "Battery",
   "capacity_mw": 40.0,
   "homes_equivalent": null,
   "status": "Awaiting Construction",
   "consented": "2024-01-12",
   "refused": null,
   "planning_authority": "Shropshire",
   "planning_ref": "TWC/2023/0144",
   "operator": "Telford Four Limited",
   "reason": {
    "reason": "consented_no_activity",
    "label": "Approved 3 years ago \u2014 nothing has happened since",
    "who": "the developer and the network company",
    "evidence": {
     "consent_date": "2024-01-12",
     "years_since_consent": 2.6
    },
    "all_matches": [
     "consented_no_activity"
    ]
   },
   "earliest": null,
   "tec": null
  },
  {
   "site_name": "Berrington Farm - Solar Array",
   "repd_ref_id": 12266,
   "technology": "Solar Photovoltaics",
   "capacity_mw": 30.0,
   "homes_equivalent": 11000,
   "status": "Awaiting Construction",
   "consented": "2025-05-02",
   "refused": "2024-03-26",
   "planning_authority": "Shropshire",
   "planning_ref": "22/04355/FUL",
   "operator": "Econergy International Limited",
   "reason": {
    "reason": "consented_no_activity",
    "label": "Approved a year ago \u2014 nothing has happened since",
    "who": "the developer and the network company",
    "evidence": {
     "consent_date": "2025-05-02",
     "years_since_consent": 1.3
    },
    "all_matches": [
     "consented_no_activity"
    ]
   },
   "earliest": null,
   "tec": null
  },
  {
   "site_name": "Steventon Road - Battery Energy Storage",
   "repd_ref_id": 16590,
   "technology": "Battery",
   "capacity_mw": 23.0,
   "homes_equivalent": null,
   "status": "Awaiting Construction",
   "consented": "2024-08-30",
   "refused": null,
   "planning_authority": "Shropshire",
   "planning_ref": "24/02223/FUL",
   "operator": "Greenfield Company",
   "reason": {
    "reason": "consented_no_activity",
    "label": "Approved a year ago \u2014 nothing has happened since",
    "who": "the developer and the network company",
    "evidence": {
     "consent_date": "2024-08-30",
     "years_since_consent": 1.9
    },
    "all_matches": [
     "consented_no_activity"
    ]
   },
   "earliest": null,
   "tec": null
  },
  {
   "site_name": "Kemberton - Solar Farm",
   "repd_ref_id": 11202,
   "technology": "Solar Photovoltaics",
   "capacity_mw": 22.0,
   "homes_equivalent": 8000,
   "status": "Awaiting Construction",
   "consented": "2024-02-22",
   "refused": "2023-03-20",
   "planning_authority": "Shropshire",
   "planning_ref": "22/02441/FUL",
   "operator": "Vattenfall",
   "reason": {
    "reason": "consented_no_activity",
    "label": "Approved 2 years ago \u2014 nothing has happened since",
    "who": "the developer and the network company",
    "evidence": {
     "consent_date": "2024-02-22",
     "years_since_consent": 2.4
    },
    "all_matches": [
     "consented_no_activity"
    ]
   },
   "earliest": null,
   "tec": null
  },
  {
   "site_name": "Rock Farm - Solar Farm",
   "repd_ref_id": 15248,
   "technology": "Battery",
   "capacity_mw": 12.0,
   "homes_equivalent": null,
   "status": "Under Construction",
   "consented": "2023-09-25",
   "refused": null,
   "planning_authority": "Shropshire",
   "planning_ref": "22/05424/EIA",
   "operator": "Enviromena",
   "reason": {
    "reason": "building",
    "label": "Under construction",
    "who": "the developer",
    "evidence": {},
    "all_matches": [
     "building"
    ]
   },
   "earliest": "2027 (in construction)",
   "tec": null
  },
  {
   "site_name": "Swancote Farm -Solar Panels",
   "repd_ref_id": 17453,
   "technology": "Solar Photovoltaics",
   "capacity_mw": 5.0,
   "homes_equivalent": 1800,
   "status": "Awaiting Construction",
   "consented": "2025-01-21",
   "refused": null,
   "planning_authority": "Shropshire",
   "planning_ref": "24/04003/FUL",
   "operator": "Swancote Energy Limited",
   "reason": {
    "reason": "consented_no_activity",
    "label": "Approved a year ago \u2014 nothing has happened since",
    "who": "the developer and the network company",
    "evidence": {
     "consent_date": "2025-01-21",
     "years_since_consent": 1.5
    },
    "all_matches": [
     "consented_no_activity"
    ]
   },
   "earliest": null,
   "tec": null
  },
  {
   "site_name": "The Conery - Wind Turbine",
   "repd_ref_id": 18149,
   "technology": "Wind Onshore",
   "capacity_mw": 1.0,
   "homes_equivalent": 900,
   "status": "Awaiting Construction",
   "consented": "2025-06-20",
   "refused": null,
   "planning_authority": "Shropshire",
   "planning_ref": "25/00177/FUL",
   "operator": "Shropshire & Telford Community Energy",
   "reason": {
    "reason": "consented_no_activity",
    "label": "Approved a year ago \u2014 nothing has happened since",
    "who": "the developer and the network company",
    "evidence": {
     "consent_date": "2025-06-20",
     "years_since_consent": 1.1
    },
    "all_matches": [
     "consented_no_activity"
    ]
   },
   "earliest": null,
   "tec": null
  }
 ],
 "projects_withheld_unreferenced": 0,
 "neighbours": [
  "E14001395",
  "E14001579",
  "W07000085",
  "E14001473",
  "W07000102",
  "E14001601",
  "E14001316",
  "E14001541",
  "E14001543"
 ],
 "flags": [
  "curtailment_not_visible"
 ],
 "windows": {
  "curtailment": [
   "2025-08-01",
   "2026-07-31"
  ],
  "repd_as_of": "2026-08-03"
 }
}