 "pcon24cd": "E14001457",
 "name": "Rushcliffe",
 "nation": "England",
 "number1": {
  "visible": false,
  "note": "No big wind farm on the national grid is mapped to this constituency. Smaller wind farms here can still be paid to switch off by the local network, but those payments are not visible in national data \u2014 the \u00a3 figure is a floor.",
  "invisible_wind": {
   "mw": 0.0,
   "sites": 0
  }
 },
 "number2": {
  "stuck_mw": 162.8,
  "stuck_mw_int": 163,
  "stuck_sites": 12,
  "homes_equivalent": 59000,
  "homes_vs_seat_households": 1.4,
  "stuck_mw_12m_cut": 183.0,
  "consented_not_built_mw_any_age": 233.7,
  "operational_mw": 24.5,
  "operational_homes_equivalent": 8900,
  "refused_5y_mw": 49.9,
  "withdrawn_5y_mw": 0.0,
  "median_months_to_decision": 2.4,
  "rank": 29,
  "tech_mix": {
   "solar": 162.8
  },
  "tech_summary": "all solar",
  "waiting_vs_running": 6.7,
  "projects": [
   {
    "site_name": "Church Farm, Kingston On Soar - Solar Photovoltaic Farm",
    "repd_ref_id": 9324,
    "technology": "Solar Photovoltaics",
    "capacity_mw": 49.9,
    "homes_equivalent": 18000,
    "consented": "2022-12-21",
    "months_waiting": 43.4,
    "status": "Awaiting Construction"
   },
   {
    "site_name": "Fair Oaks Renewable Energy Park - Solar farm & Battery energy storage",
    "repd_ref_id": 9795,
    "technology": "Solar Photovoltaics",
    "capacity_mw": 49.9,
    "homes_equivalent": 18000,
    "consented": "2023-10-02",
    "months_waiting": 34.0,
    "status": "Awaiting Construction"
   },
   {
    "site_name": "Old Wood Energy Park - Solar Pv Panel",
    "repd_ref_id": 16012,
    "technology": "Solar Photovoltaics",
    "capacity_mw": 49.9,
    "homes_equivalent": 18000,
    "consented": "2026-06-05",
    "months_waiting": 1.9,
    "status": "Awaiting Construction"
   },
   {
    "site_name": "Highfields Farm -  Solar Farm & Battery Storage",
    "repd_ref_id": 9457,
    "technology": "Solar Photovoltaics",
    "capacity_mw": 42.9,
    "homes_equivalent": 16000,
    "consented": "2023-02-16",
    "months_waiting": 41.5,
    "status": "Awaiting Construction"
   },
   {
    "site_name": "Heron Solar Farm & Battery Storage",
    "repd_ref_id": 15083,
    "technology": "Solar Photovoltaics",
    "capacity_mw": 20.0,
    "homes_equivalent": 7300,
    "consented": "2024-08-27",
    "months_waiting": 23.2,
    "status": "Awaiting Construction"
   },
   {
    "site_name": "Ratcliffe On Soar Power Station - Solar Farm",
    "repd_ref_id": 14507,
    "technology": "Solar Photovoltaics",
    "capacity_mw": 9.0,
    "homes_equivalent": 3300,
    "consented": "2023-07-19",
    "months_waiting": 36.5,
    "status": "Awaiting Construction"
   },
   {
    "site_name": "Sharpley Hill Solar Farm",
    "repd_ref_id": 8851,
    "technology": "Solar Photovoltaics",
    "capacity_mw": 4.2,
    "homes_equivalent": 1500,
    "consented": "2021-12-02",
    "months_waiting": 56.0,
    "status": "Awaiting Construction"
   },
   {
    "site_name": "Radcliffe Road, Holme Pierrepont - Solar Farm",
    "repd_ref_id": 12241,
    "technology": "Solar Photovoltaics",
    "capacity_mw": 4.2,
    "homes_equivalent": 1500,
    "consented": "2022-12-21",
    "months_waiting": 43.4,
    "status": "Awaiting Construction"
   },
   {
    "site_name": "Monarch Education Furniture - Solar panels",
    "repd_ref_id": 15706,
    "technology": "Solar Photovoltaics",
    "capacity_mw": 0.9,
    "homes_equivalent": 300,
    "consented": "2024-03-04",
    "months_waiting": 29.0,
    "status": "Awaiting Construction"
   },
   {
    "site_name": "British Geological, Keywork Solar Panels",
    "repd_ref_id": 8222,
    "technology": "Solar Photovoltaics",
    "capacity_mw": 0.6,
    "homes_equivalent": 200,
    "consented": "2021-01-13",
    "months_waiting": 66.6,
    "status": "Under Construction"
   },
   {
    "site_name": "Rushcliffe arena, Rugby Road - Solar Panels",
    "repd_ref_id": 20624,
    "technology": "Solar Photovoltaics",
    "capacity_mw": 0.5,
    "homes_equivalent": 200,
    "consented": "2026-04-13",
    "months_waiting": 3.7,
    "status": "Awaiting Construction"
   },
   {
    "site_name": "Frontier Agriculture, Ruddington -  Solar PV",
    "repd_ref_id": 11435,
    "technology": "Solar Photovoltaics",
    "capacity_mw": 0.5,
    "homes_equivalent": 200,
    "consented": "2023-03-03",
    "months_waiting": 41.0,
    "status": "Awaiting Construction"
   },
   {
    "site_name": "Wells Agriculture Barn Farm, Flawforth Lane - Solar PV System",
    "repd_ref_id": 13072,
    "technology": "Solar Photovoltaics",
    "capacity_mw": 0.3,
    "homes_equivalent": 100,
    "consented": "2023-03-03",
    "months_waiting": 41.0,
    "status": "Awaiting Construction"
   },
   {
    "site_name": "David Lloyd Leisure Health and Fitness Club, Rugby Road - Solar panels",
    "repd_ref_id": 15805,
    "technology": "Solar Photovoltaics",
    "capacity_mw": 0.3,
    "homes_equivalent": 100,
    "consented": "2024-03-26",
    "months_waiting": 28.3,
    "status": "Awaiting Construction"
   },
   {
    "site_name": "Langley House, Wheatcroft Business Park - Solar Panels",
    "repd_ref_id": 20583,
    "technology": "Solar Photovoltaics",
    "capacity_mw": 0.2,
    "homes_equivalent": 100,
    "consented": "2026-04-14",
    "months_waiting": 3.6,
    "status": "Awaiting Construction"
   },
   {
    "site_name": "John Brooke Sawmills, Fosse Way - Solar Panels",
    "repd_ref_id": 19408,
    "technology": "Solar Photovoltaics",
    "capacity_mw": 0.2,
    "homes_equivalent": 100,
    "consented": "2025-10-03",
    "months_waiting": 10.0,
    "status": "Awaiting Construction"
   },
   {
    "site_name": "Ideagen, Mere Way - Solar Panels",
    "repd_ref_id": 13914,
    "technology": "Solar Photovoltaics",
    "capacity_mw": 0.1,
    "homes_equivalent": 100,
    "consented": "2023-06-28",
    "months_waiting": 37.2,
    "status": "Awaiting Construction"
   },
   {
    "site_name": "Wheatcrofts Business Park, Edwalton - Solar Panels",
    "repd_ref_id": 17335,
    "technology": "Solar Photovoltaics",
    "capacity_mw": 0.1,
    "homes_equivalent": 100,
    "consented": "2024-11-14",
    "months_waiting": 20.6,
    "status": "Awaiting Construction"
   },
   {
    "site_name": "Rushcliffe School, Boundary Road - Solar Panels",
    "repd_ref_id": 20557,
    "technology": "Solar Photovoltaics",
    "capacity_mw": null,
    "homes_equivalent": null,
    "consented": "2026-04-21",
    "months_waiting": 3.4,
    "status": "Awaiting Construction"
   }
  ]
 },
 "number3": {
  "applicable": true,
  "per_household_gbp": 91.96,
  "seat_households": 42128,
  "seat_total_gbp": 3900000,
  "framings": {
   "days_of_home_electricity": 51.0
  },
  "note": "National figure: the per-household cost is the same for every GB seat; only the seat total varies with household count."
 },
 "batteries": {
  "operating_mw": 0.0,
  "building_mw": 0.0,
  "approved_mw": 1487.8,
  "approved_24m_mw": 57.9,
  "refused_mw": 0.0,
  "submitted_mw": 100.0,
  "sites": [
   {
    "site_name": "West Leake Lane, Ratcliffe - Battery Storage",
    "capacity_mw": 1200.0,
    "status": "approved",
    "year": 2025,
    "homes_while_discharging": 4205000
   },
   {
    "site_name": "Gotham - Battery Energy storage",
    "capacity_mw": 100.0,
    "status": "submitted",
    "year": null,
    "homes_while_discharging": 350000
   },
   {
    "site_name": "West Leake Lane, Ratcliffe - Battery Storage",
    "capacity_mw": 99.9,
    "status": "approved",
    "year": 2025,
    "homes_while_discharging": 350000
   },
   {
    "site_name": "Old Wood Energy Park - Battery Energy Storage",
    "capacity_mw": 85.0,
    "status": "approved",
    "year": 2026,
    "homes_while_discharging": 298000
   },
   {
    "site_name": "Fair Oaks Renewable Energy Park - Solar farm & Battery energy storage",
    "capacity_mw": 49.9,
    "status": "approved",
    "year": 2023,
    "homes_while_discharging": 175000
   },
   {
    "site_name": "West Thorpe Church Farm, Willoughby On The Wolds - Battery Energy Storage",
    "capacity_mw": 25.0,
    "status": "approved",
    "year": 2024,
    "homes_while_discharging": 88000
   },
   {
    "site_name": "Heron Solar Farm & Battery Storage",
    "capacity_mw": 20.0,
    "status": "approved",
    "year": 2024,
    "homes_while_discharging": 70000
   },
   {
    "site_name": "Highfields Farm -  Solar Farm & Battery Storage",
    "capacity_mw": 8.0,
    "status": "approved",
    "year": 2023,
    "homes_while_discharging": 28000
   }
  ]
 },
 "pipeline_projects": [
  {
   "site_name": "West Leake Lane, Ratcliffe - Battery Storage",
   "repd_ref_id": 12464,
   "technology": "Battery",
   "capacity_mw": 1200.0,
   "homes_equivalent": null,
   "status": "Awaiting Construction",
   "consented": "2025-02-10",
   "refused": "2024-03-18",
   "planning_authority": "Rushcliffe",
   "planning_ref": "23/01285/FUL",
   "operator": "Sandbrook Capital BES Limited",
   "reason": {
    "reason": "consented_no_activity",
    "label": "Approved a year ago \u2014 nothing has happened since",
    "who": "the developer and the network company",
    "evidence": {
     "consent_date": "2025-02-10",
     "years_since_consent": 1.5
    },
    "all_matches": [
     "consented_no_activity"
    ]
   },
   "earliest": null,
   "tec": null
  },
  {
   "site_name": "Gotham - Battery Energy storage",
   "repd_ref_id": 16458,
   "technology": "Battery",
   "capacity_mw": 100.0,
   "homes_equivalent": null,
   "status": "Application Submitted",
   "consented": null,
   "refused": null,
   "planning_authority": "Rushcliffe",
   "planning_ref": "24/00537/FUL",
   "operator": "Net Zero Energy Development Limited",
   "reason": {
    "reason": "planning_overdue",
    "label": "Waiting 2.3 years for a planning decision",
    "who": "Rushcliffe Council",
    "evidence": {
     "submitted": "2024-05-02",
     "months_waiting": 27
    },
    "all_matches": [
     "planning_overdue"
    ]
   },
   "earliest": null,
   "tec": null
  },
  {
   "site_name": "West Leake Lane, Ratcliffe - Battery Storage",
   "repd_ref_id": 17002,
   "technology": "Battery",
   "capacity_mw": 99.9,
   "homes_equivalent": null,
   "status": "Awaiting Construction",
   "consented": "2025-07-10",
   "refused": null,
   "planning_authority": "Rushcliffe",
   "planning_ref": "24/02179/FUL",
   "operator": "Renewable Energy Systems RES ltd (Beaufort)",
   "reason": {
    "reason": "consented_no_activity",
    "label": "Approved a year ago \u2014 nothing has happened since",
    "who": "the developer and the network company",
    "evidence": {
     "consent_date": "2025-07-10",
     "years_since_consent": 1.1
    },
    "all_matches": [
     "consented_no_activity"
    ]
   },
   "earliest": null,
   "tec": null
  },
  {
   "site_name": "Old Wood Energy Park - Battery Energy Storage",
   "repd_ref_id": 16013,
   "technology": "Battery",
   "capacity_mw": 85.0,
   "homes_equivalent": null,
   "status": "Awaiting Construction",
   "consented": "2026-06-05",
   "refused": "2025-06-19",
   "planning_authority": "Rushcliffe",
   "planning_ref": "24/00161/FUL",
   "operator": "Exagen",
   "reason": {
    "reason": "consented_no_activity",
    "label": "Approved less than a year ago \u2014 nothing has happened since",
    "who": "the developer and the network company",
    "evidence": {
     "consent_date": "2026-06-05",
     "years_since_consent": 0.2
    },
    "all_matches": [
     "consented_no_activity"
    ]
   },
   "earliest": null,
   "tec": null
  },
  {
   "site_name": "Church Farm, Kingston On Soar - Solar Photovoltaic Farm",
   "repd_ref_id": 9324,
   "technology": "Solar Photovoltaics",
   "capacity_mw": 49.9,
   "homes_equivalent": 18000,
   "status": "Awaiting Construction",
   "consented": "2022-12-21",
   "refused": null,
   "planning_authority": "Rushcliffe",
   "planning_ref": "22/00809/FUL",
   "operator": "Renewable Connections Developments Limited",
   "reason": {
    "reason": "consented_no_activity",
    "label": "Approved 4 years ago \u2014 nothing has happened since",
    "who": "the developer and the network company",
    "evidence": {
     "consent_date": "2022-12-21",
     "years_since_consent": 3.6
    },
    "all_matches": [
     "consented_no_activity"
    ]
   },
   "earliest": null,
   "tec": null
  },
  {
   "site_name": "Fair Oaks Renewable Energy Park - Solar farm & Battery energy storage",
   "repd_ref_id": 9795,
   "technology": "Solar Photovoltaics",
   "capacity_mw": 49.9,
   "homes_equivalent": 18000,
   "status": "Awaiting Construction",
   "consented": "2023-10-02",
   "refused": null,
   "planning_authority": "Rushcliffe",
   "planning_ref": "23/00254/FUL",
   "operator": "Ridge Clean Energy Limited / L&G NTR Clean Power",
   "reason": {
    "reason": "consented_no_activity",
    "label": "Approved 3 years ago \u2014 nothing has happened since",
    "who": "the developer and the network company",
    "evidence": {
     "consent_date": "2023-10-02",
     "years_since_consent": 2.8
    },
    "all_matches": [
     "consented_no_activity"
    ]
   },
   "earliest": null,
   "tec": null
  },
  {
   "site_name": "Fair Oaks Renewable Energy Park - Solar farm & Battery energy storage",
   "repd_ref_id": 9796,
   "technology": "Battery",
   "capacity_mw": 49.9,
   "homes_equivalent": null,
   "status": "Awaiting Construction",
   "consented": "2023-10-02",
   "refused": null,
   "planning_authority": "Rushcliffe",
   "planning_ref": "23/00254/FUL",
   "operator": "Ridge Clean Energy Limited / L&G NTR Clean Power",
   "reason": {
    "reason": "consented_no_activity",
    "label": "Approved 3 years ago \u2014 nothing has happened since",
    "who": "the developer and the network company",
    "evidence": {
     "consent_date": "2023-10-02",
     "years_since_consent": 2.8
    },
    "all_matches": [
     "consented_no_activity"
    ]
   },
   "earliest": null,
   "tec": null
  },
  {
   "site_name": "Old Wood Energy Park - Solar Pv Panel",
   "repd_ref_id": 16012,
   "technology": "Solar Photovoltaics",
   "capacity_mw": 49.9,
   "homes_equivalent": 18000,
   "status": "Awaiting Construction",
   "consented": "2026-06-05",
   "refused": "2025-06-19",
   "planning_authority": "Rushcliffe",
   "planning_ref": "24/00161/FUL",
   "operator": "Exagen",
   "reason": {
    "reason": "consented_no_activity",
    "label": "Approved less than a year ago \u2014 nothing has happened since",
    "who": "the developer and the network company",
    "evidence": {
     "consent_date": "2026-06-05",
     "years_since_consent": 0.2
    },
    "all_matches": [
     "consented_no_activity"
    ]
   },
   "earliest": null,
   "tec": null
  },
  {
   "site_name": "Kingston Solar farm",
   "repd_ref_id": 8904,
   "technology": "Solar Photovoltaics",
   "capacity_mw": 49.9,
   "homes_equivalent": 18000,
   "status": "Application Refused",
   "consented": null,
   "refused": "2023-03-13",
   "planning_authority": "Rushcliffe",
   "planning_ref": "22/00319/FUL",
   "operator": "Renewable Energy System Limited",
   "reason": {
    "reason": "refused",
    "label": "Refused by Rushcliffe Council in 2023",
    "who": "Rushcliffe Council",
    "evidence": {
     "refusal_date": "2023-03-13"
    },
    "all_matches": [
     "refused"
    ]
   },
   "earliest": null,
   "tec": null
  },
  {
   "site_name": "EMERGE (East Midlands Energy Re-Generation)",
   "repd_ref_id": 7734,
   "technology": "EfW Incineration",
   "capacity_mw": 49.9,
   "homes_equivalent": null,
   "status": "Awaiting Construction",
   "consented": "2022-03-24",
   "refused": null,
   "planning_authority": "Rushcliffe",
   "planning_ref": "ES/4154",
   "operator": "Uniper UK",
   "reason": {
    "reason": "consented_no_activity",
    "label": "Approved 4 years ago \u2014 nothing has happened since",
    "who": "the developer and the network company",
    "evidence": {
     "consent_date": "2022-03-24",
     "years_since_consent": 4.4
    },
    "all_matches": [
     "consented_no_activity"
    ]
   },
   "earliest": null,
   "tec": null
  },
  {
   "site_name": "Highfields Farm -  Solar Farm & Battery Storage",
   "repd_ref_id": 9457,
   "technology": "Solar Photovoltaics",
   "capacity_mw": 42.9,
   "homes_equivalent": 16000,
   "status": "Awaiting Construction",
   "consented": "2023-02-16",
   "refused": null,
   "planning_authority": "Rushcliffe",
   "planning_ref": "22/00303/FUL",
   "operator": "Boultbee Brooks Renewable Energy Ltd",
   "reason": {
    "reason": "consented_no_activity",
    "label": "Approved 3 years ago \u2014 nothing has happened since",
    "who": "the developer and the network company",
    "evidence": {
     "consent_date": "2023-02-16",
     "years_since_consent": 3.5
    },
    "all_matches": [
     "consented_no_activity"
    ]
   },
   "earliest": null,
   "tec": null
  },
  {
   "site_name": "West Thorpe Church Farm, Willoughby On The Wolds - Battery Energy Storage",
   "repd_ref_id": 15938,
   "technology": "Battery",
   "capacity_mw": 25.0,
   "homes_equivalent": null,
   "status": "Awaiting Construction",
   "consented": "2024-09-24",
   "refused": null,
   "planning_authority": "Rushcliffe",
   "planning_ref": "24/00151/FUL",
   "operator": "Integrum Renewable Energy Limited",
   "reason": {
    "reason": "consented_no_activity",
    "label": "Approved a year ago \u2014 nothing has happened since",
    "who": "the developer and the network company",
    "evidence": {
     "consent_date": "2024-09-24",
     "years_since_consent": 1.9
    },
    "all_matches": [
     "consented_no_activity"
    ]
   },
   "earliest": null,
   "tec": null
  },
  {
   "site_name": "Heron Solar Farm & Battery Storage",
   "repd_ref_id": 15083,
   "technology": "Solar Photovoltaics",
   "capacity_mw": 20.0,
   "homes_equivalent": 7300,
   "status": "Awaiting Construction",
   "consented": "2024-08-27",
   "refused": null,
   "planning_authority": "Rushcliffe",
   "planning_ref": "23/02250/FUL",
   "operator": "JBM Solar Projects 38 Limited",
   "reason": {
    "reason": "consented_no_activity",
    "label": "Approved a year ago \u2014 nothing has happened since",
    "who": "the developer and the network company",
    "evidence": {
     "consent_date": "2024-08-27",
     "years_since_consent": 1.9
    },
    "all_matches": [
     "consented_no_activity"
    ]
   },
   "earliest": null,
   "tec": null
  },
  {
   "site_name": "Heron Solar Farm & Battery Storage",
   "repd_ref_id": 15084,
   "technology": "Battery",
   "capacity_mw": 20.0,
   "homes_equivalent": null,
   "status": "Awaiting Construction",
   "consented": "2024-08-27",
   "refused": null,
   "planning_authority": "Rushcliffe",
   "planning_ref": "23/02250/FUL",
   "operator": "JBM Solar Projects 38 Limited",
   "reason": {
    "reason": "consented_no_activity",
    "label": "Approved a year ago \u2014 nothing has happened since",
    "who": "the developer and the network company",
    "evidence": {
     "consent_date": "2024-08-27",
     "years_since_consent": 1.9
    },
    "all_matches": [
     "consented_no_activity"
    ]
   },
   "earliest": null,
   "tec": null
  },
  {
   "site_name": "Ratcliffe On Soar Power Station - Solar Farm",
   "repd_ref_id": 14507,
   "technology": "Solar Photovoltaics",
   "capacity_mw": 9.0,
   "homes_equivalent": 3300,
   "status": "Awaiting Construction",
   "consented": "2023-07-19",
   "refused": null,
   "planning_authority": "Rushcliffe",
   "planning_ref": "22/01339/LDO",
   "operator": "Rushcliffe Borough Council",
   "reason": {
    "reason": "consented_no_activity",
    "label": "Approved 3 years ago \u2014 nothing has happened since",
    "who": "the developer and the network company",
    "evidence": {
     "consent_date": "2023-07-19",
     "years_since_consent": 3.0
    },
    "all_matches": [
     "consented_no_activity"
    ]
   },
   "earliest": null,
   "tec": null
  },
  {
   "site_name": "Highfields Farm -  Solar Farm & Battery Storage",
   "repd_ref_id": 10761,
   "technology": "Battery",
   "capacity_mw": 8.0,
   "homes_equivalent": null,
   "status": "Awaiting Construction",
   "consented": "2023-02-16",
   "refused": null,
   "planning_authority": "Rushcliffe",
   "planning_ref": "22/00303/FUL",
   "operator": "Boultbee Brooks Renewable Energy Ltd",
   "reason": {
    "reason": "consented_no_activity",
    "label": "Approved 3 years ago \u2014 nothing has happened since",
    "who": "the developer and the network company",
    "evidence": {
     "consent_date": "2023-02-16",
     "years_since_consent": 3.5
    },
    "all_matches": [
     "consented_no_activity"
    ]
   },
   "earliest": null,
   "tec": null
  },
  {
   "site_name": "Radcliffe Road, Holme Pierrepont - Solar Farm",
   "repd_ref_id": 12241,
   "technology": "Solar Photovoltaics",
   "capacity_mw": 4.2,
   "homes_equivalent": 1500,
   "status": "Awaiting Construction",
   "consented": "2022-12-21",
   "refused": null,
   "planning_authority": "Rushcliffe",
   "planning_ref": "22/01511/FUL",
   "operator": "Bassingfield REP Limited",
   "reason": {
    "reason": "consented_no_activity",
    "label": "Approved 4 years ago \u2014 nothing has happened since",
    "who": "the developer and the network company",
    "evidence": {
     "consent_date": "2022-12-21",
     "years_since_consent": 3.6
    },
    "all_matches": [
     "consented_no_activity"
    ]
   },
   "earliest": null,
   "tec": null
  },
  {
   "site_name": "Sharpley Hill Solar Farm",
   "repd_ref_id": 8851,
   "technology": "Solar Photovoltaics",
   "capacity_mw": 4.2,
   "homes_equivalent": 1500,
   "status": "Awaiting Construction",
   "consented": "2021-12-02",
   "refused": null,
   "planning_authority": "Rushcliffe",
   "planning_ref": "21/00703/FUL",
   "operator": "Opdenergy UK 2 Limited",
   "reason": {
    "reason": "consented_no_activity",
    "label": "Approved 5 years ago \u2014 nothing has happened since",
    "who": "the developer and the network company",
    "evidence": {
     "consent_date": "2021-12-02",
     "years_since_consent": 4.7
    },
    "all_matches": [
     "consented_no_activity"
    ]
   },
   "earliest": null,
   "tec": null
  }
 ],
 "projects_withheld_unreferenced": 0,
 "neighbours": [
  "E14001342",
  "E14001357",
  "E14001412",
  "E14001228",
  "E14001410",
  "E14001140",
  "E14001245",
  "E14001404",
  "E14001375"
 ],
 "flags": [
  "curtailment_not_visible"
 ],
 "windows": {
  "curtailment": [
   "2025-08-01",
   "2026-07-31"
  ],
  "repd_as_of": "2026-08-03"
 }
}