 "pcon24cd": "E14001406",
 "name": "Northampton North",
 "nation": "England",
 "number1": {
  "visible": false,
  "note": "No big wind farm on the national grid is mapped to this constituency. Smaller wind farms here can still be paid to switch off by the local network, but those payments are not visible in national data \u2014 the \u00a3 figure is a floor.",
  "invisible_wind": {
   "mw": 0.0,
   "sites": 0
  }
 },
 "number2": {
  "stuck_mw": 0.5,
  "stuck_mw_int": 0,
  "stuck_sites": 1,
  "homes_equivalent": 200,
  "homes_vs_seat_households": 0.0,
  "stuck_mw_12m_cut": 0.8,
  "consented_not_built_mw_any_age": 0.9,
  "operational_mw": 0.0,
  "operational_homes_equivalent": 0,
  "refused_5y_mw": 0.0,
  "withdrawn_5y_mw": 0.0,
  "median_months_to_decision": 1.2,
  "rank": 486,
  "tech_mix": {
   "solar": 0.5
  },
  "tech_summary": "all solar",
  "waiting_vs_running": null,
  "projects": [
   {
    "site_name": "Edgemead Close - Solar PV Panels",
    "repd_ref_id": 13585,
    "technology": "Solar Photovoltaics",
    "capacity_mw": 0.5,
    "homes_equivalent": 200,
    "consented": "2023-04-27",
    "months_waiting": 39.2,
    "status": "Awaiting Construction"
   },
   {
    "site_name": "Io Centre, Unit 5, 6, 7 & 8, Barn Way - Solar panels",
    "repd_ref_id": 17834,
    "technology": "Solar Photovoltaics",
    "capacity_mw": 0.2,
    "homes_equivalent": 100,
    "consented": "2025-02-05",
    "months_waiting": 17.9,
    "status": "Awaiting Construction"
   },
   {
    "site_name": "Ladys Lane - Solar Panels",
    "repd_ref_id": 19380,
    "technology": "Solar Photovoltaics",
    "capacity_mw": 0.2,
    "homes_equivalent": 100,
    "consented": "2025-09-10",
    "months_waiting": 10.7,
    "status": "Awaiting Construction"
   }
  ]
 },
 "number3": {
  "applicable": true,
  "per_household_gbp": 91.96,
  "seat_households": 52292,
  "seat_total_gbp": 4800000,
  "framings": {
   "days_of_home_electricity": 51.0
  },
  "note": "National figure: the per-household cost is the same for every GB seat; only the seat total varies with household count."
 },
 "batteries": {
  "operating_mw": 0.0,
  "building_mw": 0.0,
  "approved_mw": 0.4,
  "approved_24m_mw": 0.0,
  "refused_mw": 0.0,
  "submitted_mw": 0.0,
  "sites": [
   {
    "site_name": "Octagon Way, Weston Favell Retail Park - Energy Storage System",
    "capacity_mw": 0.2,
    "status": "approved",
    "year": 2025,
    "homes_while_discharging": 700
   },
   {
    "site_name": "Moulton Park Industrial Estate - Micro Energy Storage",
    "capacity_mw": 0.2,
    "status": "approved",
    "year": 2025,
    "homes_while_discharging": 700
   }
  ]
 },
 "pipeline_projects": [],
 "projects_withheld_unreferenced": 0,
 "neighbours": [
  "E14001407",
  "E14001192"
 ],
 "flags": [
  "curtailment_not_visible"
 ],
 "windows": {
  "curtailment": [
   "2025-08-01",
   "2026-07-31"
  ],
  "repd_as_of": "2026-08-03"
 }
}