 "pcon24cd": "E14001398",
 "name": "North Shropshire",
 "nation": "England",
 "number1": {
  "visible": false,
  "note": "No big wind farm on the national grid is mapped to this constituency. Smaller wind farms here can still be paid to switch off by the local network, but those payments are not visible in national data \u2014 the \u00a3 figure is a floor.",
  "invisible_wind": {
   "mw": 0.0,
   "sites": 0
  }
 },
 "number2": {
  "stuck_mw": 10.6,
  "stuck_mw_int": 11,
  "stuck_sites": 13,
  "homes_equivalent": 3800,
  "homes_vs_seat_households": 0.09,
  "stuck_mw_12m_cut": 12.4,
  "consented_not_built_mw_any_age": 13.3,
  "operational_mw": 79.8,
  "operational_homes_equivalent": 29000,
  "refused_5y_mw": 1.9,
  "withdrawn_5y_mw": 0.0,
  "median_months_to_decision": 1.6,
  "rank": 226,
  "tech_mix": {
   "solar": 10.6
  },
  "tech_summary": "all solar",
  "waiting_vs_running": 0.1,
  "projects": [
   {
    "site_name": "Belton Farm, Belton - Solar Pv System",
    "repd_ref_id": 15591,
    "technology": "Solar Photovoltaics",
    "capacity_mw": 2.2,
    "homes_equivalent": 800,
    "consented": "2024-04-03",
    "months_waiting": 28.0,
    "status": "Under Construction"
   },
   {
    "site_name": "Manor Farm, Crickheath - Solar Array",
    "repd_ref_id": 14573,
    "technology": "Solar Photovoltaics",
    "capacity_mw": 1.8,
    "homes_equivalent": 700,
    "consented": "2023-10-25",
    "months_waiting": 33.3,
    "status": "Awaiting Construction"
   },
   {
    "site_name": "Berllandeg Farm, Rhoswiel -  Solar Panels",
    "repd_ref_id": 18884,
    "technology": "Solar Photovoltaics",
    "capacity_mw": 1.3,
    "homes_equivalent": 500,
    "consented": "2025-06-18",
    "months_waiting": 13.5,
    "status": "Awaiting Construction"
   },
   {
    "site_name": "Cefn-Y-Maes Farm, Rhydycroesau - Solar Park",
    "repd_ref_id": 11859,
    "technology": "Solar Photovoltaics",
    "capacity_mw": 1.2,
    "homes_equivalent": 400,
    "consented": "2022-10-14",
    "months_waiting": 45.6,
    "status": "Awaiting Construction"
   },
   {
    "site_name": "Winston Farm, Ellesmere Road - Solar Array",
    "repd_ref_id": 13997,
    "technology": "Solar Photovoltaics",
    "capacity_mw": 1.1,
    "homes_equivalent": 400,
    "consented": "2023-08-10",
    "months_waiting": 35.8,
    "status": "Awaiting Construction"
   },
   {
    "site_name": "Sansaw Business Park, Hadnall - Solar Panels",
    "repd_ref_id": 11028,
    "technology": "Solar Photovoltaics",
    "capacity_mw": 1.0,
    "homes_equivalent": 400,
    "consented": "2022-05-30",
    "months_waiting": 50.1,
    "status": "Awaiting Construction"
   },
   {
    "site_name": "Wykey Farm, Ruyton Xi Towns - Solar Array",
    "repd_ref_id": 10882,
    "technology": "Solar Photovoltaics",
    "capacity_mw": 1.0,
    "homes_equivalent": 400,
    "consented": "2022-05-13",
    "months_waiting": 50.7,
    "status": "Awaiting Construction"
   },
   {
    "site_name": "Cold Move, Maes-Y-Clawdd",
    "repd_ref_id": 13304,
    "technology": "Solar Photovoltaics",
    "capacity_mw": 0.8,
    "homes_equivalent": 300,
    "consented": "2023-04-05",
    "months_waiting": 39.9,
    "status": "Awaiting Construction"
   },
   {
    "site_name": "Lower Heath Farm, Lower Heath - Solar Panels",
    "repd_ref_id": 18834,
    "technology": "Solar Photovoltaics",
    "capacity_mw": 0.6,
    "homes_equivalent": 200,
    "consented": "2025-06-25",
    "months_waiting": 13.3,
    "status": "Awaiting Construction"
   },
   {
    "site_name": "Highbury Poultry Produce, Manor House Lane - Solar Array",
    "repd_ref_id": 12887,
    "technology": "Solar Photovoltaics",
    "capacity_mw": 0.6,
    "homes_equivalent": 200,
    "consented": "2023-01-13",
    "months_waiting": 42.6,
    "status": "Awaiting Construction"
   },
   {
    "site_name": "Kenwick Lodge, Cockshutt - Solar Array",
    "repd_ref_id": 12358,
    "technology": "Solar Photovoltaics",
    "capacity_mw": 0.3,
    "homes_equivalent": 100,
    "consented": "2022-10-31",
    "months_waiting": 45.1,
    "status": "Awaiting Construction"
   },
   {
    "site_name": "Highbury Poultry Farm Produce, Manor House Lane - Solar Panels",
    "repd_ref_id": 12197,
    "technology": "Solar Photovoltaics",
    "capacity_mw": 0.3,
    "homes_equivalent": 100,
    "consented": "2022-11-10",
    "months_waiting": 44.7,
    "status": "Awaiting Construction"
   },
   {
    "site_name": "Merlot Chitty Farms, Betton - Solar Panels",
    "repd_ref_id": 19547,
    "technology": "Solar Photovoltaics",
    "capacity_mw": 0.3,
    "homes_equivalent": 100,
    "consented": "2025-09-18",
    "months_waiting": 10.5,
    "status": "Awaiting Construction"
   },
   {
    "site_name": "Robert Jones and Agnes Hunt Orthopaedic Hospital, Gobowen - Solar Panels",
    "repd_ref_id": 16330,
    "technology": "Solar Photovoltaics",
    "capacity_mw": 0.3,
    "homes_equivalent": 100,
    "consented": "2024-06-05",
    "months_waiting": 25.9,
    "status": "Awaiting Construction"
   },
   {
    "site_name": "Robert Jones And Agnes Hunt Orthopaedic Hospital, Gobowen - Solar Panels",
    "repd_ref_id": 19180,
    "technology": "Solar Photovoltaics",
    "capacity_mw": 0.2,
    "homes_equivalent": 100,
    "consented": "2025-08-14",
    "months_waiting": 11.6,
    "status": "Awaiting Construction"
   },
   {
    "site_name": "Robert Jones & Agnes Hunt Orthopaedic Hospital, Gobowen - Solar Panels",
    "repd_ref_id": 19203,
    "technology": "Solar Photovoltaics",
    "capacity_mw": 0.2,
    "homes_equivalent": 100,
    "consented": "2025-08-14",
    "months_waiting": 11.6,
    "status": "Awaiting Construction"
   },
   {
    "site_name": "TB Electrics, Sandford - Solar Panels",
    "repd_ref_id": 19196,
    "technology": "Solar Photovoltaics",
    "capacity_mw": 0.2,
    "homes_equivalent": 100,
    "consented": "2025-08-07",
    "months_waiting": 11.9,
    "status": "Awaiting Construction"
   },
   {
    "site_name": "Plas Yolyn - Solar Park",
    "repd_ref_id": 9858,
    "technology": "Solar Photovoltaics",
    "capacity_mw": null,
    "homes_equivalent": null,
    "consented": "2024-05-03",
    "months_waiting": 27.0,
    "status": "Awaiting Construction"
   },
   {
    "site_name": "Robert Jones & Agnes Hunt Orthopaedic Hospital - Solar Panels",
    "repd_ref_id": 16274,
    "technology": "Solar Photovoltaics",
    "capacity_mw": null,
    "homes_equivalent": null,
    "consented": "2024-04-25",
    "months_waiting": 27.3,
    "status": "Awaiting Construction"
   },
   {
    "site_name": "The Beeches, Alkington - Solar Panels",
    "repd_ref_id": 16440,
    "technology": "Solar Photovoltaics",
    "capacity_mw": null,
    "homes_equivalent": null,
    "consented": "2025-04-23",
    "months_waiting": 15.3,
    "status": "Awaiting Construction"
   },
   {
    "site_name": "Robert Jones And Agnes Hunt Orthopaedic Hospital - Solar Panels",
    "repd_ref_id": 18871,
    "technology": "Solar Photovoltaics",
    "capacity_mw": null,
    "homes_equivalent": null,
    "consented": "2025-07-22",
    "months_waiting": 12.4,
    "status": "Awaiting Construction"
   }
  ]
 },
 "number3": {
  "applicable": true,
  "per_household_gbp": 91.96,
  "seat_households": 43469,
  "seat_total_gbp": 4000000,
  "framings": {
   "days_of_home_electricity": 51.0
  },
  "note": "National figure: the per-household cost is the same for every GB seat; only the seat total varies with household count."
 },
 "batteries": {
  "operating_mw": 0.0,
  "building_mw": 0.0,
  "approved_mw": 301.2,
  "approved_24m_mw": 1.2,
  "refused_mw": 0.0,
  "submitted_mw": 0.0,
  "sites": [
   {
    "site_name": "Rednal Airfield, West Felton - Battery Energy Storage",
    "capacity_mw": 300.0,
    "status": "approved",
    "year": 2026,
    "homes_while_discharging": 1051000
   },
   {
    "site_name": "Cold Move, Maes-Y-Clawdd",
    "capacity_mw": 1.0,
    "status": "approved",
    "year": 2023,
    "homes_while_discharging": 3500
   },
   {
    "site_name": "Farr & Harris - Energy Storage Facility",
    "capacity_mw": 0.2,
    "status": "approved",
    "year": 2024,
    "homes_while_discharging": 700
   }
  ]
 },
 "pipeline_projects": [
  {
   "site_name": "Rednal Airfield, West Felton - Battery Energy Storage",
   "repd_ref_id": 18028,
   "technology": "Battery",
   "capacity_mw": 300.0,
   "homes_equivalent": null,
   "status": "Awaiting Construction",
   "consented": "2026-04-16",
   "refused": null,
   "planning_authority": "Shropshire",
   "planning_ref": "25/01250/FUL",
   "operator": "Private Developer",
   "reason": {
    "reason": "consented_no_activity",
    "label": "Approved less than a year ago \u2014 nothing has happened since",
    "who": "the developer and the network company",
    "evidence": {
     "consent_date": "2026-04-16",
     "years_since_consent": 0.3
    },
    "all_matches": [
     "consented_no_activity"
    ]
   },
   "earliest": null,
   "tec": null
  },
  {
   "site_name": "Belton Farm, Belton - Solar Pv System",
   "repd_ref_id": 15591,
   "technology": "Solar Photovoltaics",
   "capacity_mw": 2.2,
   "homes_equivalent": 800,
   "status": "Under Construction",
   "consented": "2024-04-03",
   "refused": null,
   "planning_authority": "Shropshire",
   "planning_ref": "23/05100/FUL",
   "operator": "Conrad Energy (Developments) Limited",
   "reason": {
    "reason": "building",
    "label": "Under construction",
    "who": "the developer",
    "evidence": {},
    "all_matches": [
     "building"
    ]
   },
   "earliest": "2027 (in construction)",
   "tec": null
  },
  {
   "site_name": "Glovers Meadow - Ground Mounted Solar Array",
   "repd_ref_id": 16582,
   "technology": "Solar Photovoltaics",
   "capacity_mw": 2.0,
   "homes_equivalent": 700,
   "status": "Application Submitted",
   "consented": null,
   "refused": null,
   "planning_authority": "Shropshire",
   "planning_ref": "24/02237/FUL",
   "operator": "Shropshire Council",
   "reason": {
    "reason": "planning_overdue",
    "label": "Waiting 2.1 years for a planning decision",
    "who": "Shropshire Council",
    "evidence": {
     "submitted": "2024-06-17",
     "months_waiting": 26
    },
    "all_matches": [
     "planning_overdue"
    ]
   },
   "earliest": null,
   "tec": null
  },
  {
   "site_name": "Robert Jones & Agnes Hunt Orthopaedic Hospital, Gobowen- Solar Array",
   "repd_ref_id": 19722,
   "technology": "Solar Photovoltaics",
   "capacity_mw": 1.9,
   "homes_equivalent": 700,
   "status": "Application Refused",
   "consented": null,
   "refused": "2025-10-07",
   "planning_authority": "Shropshire",
   "planning_ref": "25/02807/FUL",
   "operator": "Robert Jones & Agnes Hunt Orthopaedic Hospital NHSTrust",
   "reason": {
    "reason": "refused",
    "label": "Refused by Shropshire Council in 2025",
    "who": "Shropshire Council",
    "evidence": {
     "refusal_date": "2025-10-07"
    },
    "all_matches": [
     "refused"
    ]
   },
   "earliest": null,
   "tec": null
  },
  {
   "site_name": "Manor Farm, Crickheath - Solar Array",
   "repd_ref_id": 14573,
   "technology": "Solar Photovoltaics",
   "capacity_mw": 1.8,
   "homes_equivalent": 700,
   "status": "Awaiting Construction",
   "consented": "2023-10-25",
   "refused": null,
   "planning_authority": "Shropshire",
   "planning_ref": "23/03062/FUL",
   "operator": "Manor Farm",
   "reason": {
    "reason": "consented_no_activity",
    "label": "Approved 3 years ago \u2014 nothing has happened since",
    "who": "the developer and the network company",
    "evidence": {
     "consent_date": "2023-10-25",
     "years_since_consent": 2.8
    },
    "all_matches": [
     "consented_no_activity"
    ]
   },
   "earliest": null,
   "tec": null
  },
  {
   "site_name": "Berllandeg Farm, Rhoswiel -  Solar Panels",
   "repd_ref_id": 18884,
   "technology": "Solar Photovoltaics",
   "capacity_mw": 1.3,
   "homes_equivalent": 500,
   "status": "Awaiting Construction",
   "consented": "2025-06-18",
   "refused": null,
   "planning_authority": "Shropshire",
   "planning_ref": "25/01572/FUL",
   "operator": "Igreen Energy",
   "reason": {
    "reason": "consented_no_activity",
    "label": "Approved a year ago \u2014 nothing has happened since",
    "who": "the developer and the network company",
    "evidence": {
     "consent_date": "2025-06-18",
     "years_since_consent": 1.1
    },
    "all_matches": [
     "consented_no_activity"
    ]
   },
   "earliest": null,
   "tec": null
  },
  {
   "site_name": "Cefn-Y-Maes Farm, Rhydycroesau - Solar Park",
   "repd_ref_id": 11859,
   "technology": "Solar Photovoltaics",
   "capacity_mw": 1.2,
   "homes_equivalent": 400,
   "status": "Awaiting Construction",
   "consented": "2022-10-14",
   "refused": null,
   "planning_authority": "Shropshire",
   "planning_ref": "22/03447/FUL",
   "operator": "Positech Energy Limited",
   "reason": {
    "reason": "consented_no_activity",
    "label": "Approved 4 years ago \u2014 nothing has happened since",
    "who": "the developer and the network company",
    "evidence": {
     "consent_date": "2022-10-14",
     "years_since_consent": 3.8
    },
    "all_matches": [
     "consented_no_activity"
    ]
   },
   "earliest": null,
   "tec": null
  },
  {
   "site_name": "Tramway Farm, Crickheath - Solar Array",
   "repd_ref_id": 14425,
   "technology": "Solar Photovoltaics",
   "capacity_mw": 1.1,
   "homes_equivalent": 400,
   "status": "Application Submitted",
   "consented": null,
   "refused": null,
   "planning_authority": "Shropshire",
   "planning_ref": "23/02900/FUL",
   "operator": "R & E J Bowker",
   "reason": {
    "reason": "planning_overdue",
    "label": "Waiting 3.1 years for a planning decision",
    "who": "Shropshire Council",
    "evidence": {
     "submitted": "2023-07-04",
     "months_waiting": 37
    },
    "all_matches": [
     "planning_overdue"
    ]
   },
   "earliest": null,
   "tec": null
  },
  {
   "site_name": "Winston Farm, Ellesmere Road - Solar Array",
   "repd_ref_id": 13997,
   "technology": "Solar Photovoltaics",
   "capacity_mw": 1.1,
   "homes_equivalent": 400,
   "status": "Awaiting Construction",
   "consented": "2023-08-10",
   "refused": null,
   "planning_authority": "Shropshire",
   "planning_ref": "23/01898/FUL",
   "operator": "S F Jones Limited",
   "reason": {
    "reason": "consented_no_activity",
    "label": "Approved 3 years ago \u2014 nothing has happened since",
    "who": "the developer and the network company",
    "evidence": {
     "consent_date": "2023-08-10",
     "years_since_consent": 3.0
    },
    "all_matches": [
     "consented_no_activity"
    ]
   },
   "earliest": null,
   "tec": null
  },
  {
   "site_name": "Wykey Farm, Ruyton Xi Towns - Solar Array",
   "repd_ref_id": 10882,
   "technology": "Solar Photovoltaics",
   "capacity_mw": 1.0,
   "homes_equivalent": 400,
   "status": "Awaiting Construction",
   "consented": "2022-05-13",
   "refused": null,
   "planning_authority": "Shropshire",
   "planning_ref": "22/01123/FUL",
   "operator": "W H Gittins & Sons",
   "reason": {
    "reason": "consented_no_activity",
    "label": "Approved 4 years ago \u2014 nothing has happened since",
    "who": "the developer and the network company",
    "evidence": {
     "consent_date": "2022-05-13",
     "years_since_consent": 4.2
    },
    "all_matches": [
     "consented_no_activity"
    ]
   },
   "earliest": null,
   "tec": null
  },
  {
   "site_name": "Sansaw Business Park, Hadnall - Solar Panels",
   "repd_ref_id": 11028,
   "technology": "Solar Photovoltaics",
   "capacity_mw": 1.0,
   "homes_equivalent": 400,
   "status": "Awaiting Construction",
   "consented": "2022-05-30",
   "refused": null,
   "planning_authority": "Shropshire",
   "planning_ref": "22/01658/PSPPA",
   "operator": "Sansaw Properties Limited",
   "reason": {
    "reason": "consented_no_activity",
    "label": "Approved 4 years ago \u2014 nothing has happened since",
    "who": "the developer and the network company",
    "evidence": {
     "consent_date": "2022-05-30",
     "years_since_consent": 4.2
    },
    "all_matches": [
     "consented_no_activity"
    ]
   },
   "earliest": null,
   "tec": null
  },
  {
   "site_name": "Cold Move, Maes-Y-Clawdd",
   "repd_ref_id": 13305,
   "technology": "Battery",
   "capacity_mw": 1.0,
   "homes_equivalent": null,
   "status": "Awaiting Construction",
   "consented": "2023-04-05",
   "refused": null,
   "planning_authority": "Shropshire",
   "planning_ref": "23/00031/FUL",
   "operator": "Cold Move Limited",
   "reason": {
    "reason": "consented_no_activity",
    "label": "Approved 3 years ago \u2014 nothing has happened since",
    "who": "the developer and the network company",
    "evidence": {
     "consent_date": "2023-04-05",
     "years_since_consent": 3.3
    },
    "all_matches": [
     "consented_no_activity"
    ]
   },
   "earliest": null,
   "tec": null
  },
  {
   "site_name": "Harmer Hill, Webscott - Solar Array",
   "repd_ref_id": 20822,
   "technology": "Solar Photovoltaics",
   "capacity_mw": 1.0,
   "homes_equivalent": 400,
   "status": "Application Submitted",
   "consented": null,
   "refused": null,
   "planning_authority": "Shropshire",
   "planning_ref": "26/01242/FUL",
   "operator": "Unknown",
   "reason": {
    "reason": "in_planning",
    "label": "Applied in 2026, still waiting for a decision",
    "who": "Shropshire Council",
    "evidence": {
     "submitted": "2026-04-10",
     "months_waiting": 4
    },
    "all_matches": [
     "in_planning"
    ]
   },
   "earliest": null,
   "tec": null
  }
 ],
 "projects_withheld_unreferenced": 0,
 "neighbours": [
  "E14001473",
  "W07000102",
  "W07000111",
  "E14001543",
  "E14001513",
  "E14001380",
  "E14001164"
 ],
 "flags": [
  "curtailment_not_visible"
 ],
 "windows": {
  "curtailment": [
   "2025-08-01",
   "2026-07-31"
  ],
  "repd_as_of": "2026-08-03"
 }
}