 "pcon24cd": "E14001388",
 "name": "North Dorset",
 "nation": "England",
 "number1": {
  "visible": false,
  "note": "No big wind farm on the national grid is mapped to this constituency. Smaller wind farms here can still be paid to switch off by the local network, but those payments are not visible in national data \u2014 the \u00a3 figure is a floor.",
  "invisible_wind": {
   "mw": 0.0,
   "sites": 0
  }
 },
 "number2": {
  "stuck_mw": 96.8,
  "stuck_mw_int": 97,
  "stuck_sites": 11,
  "homes_equivalent": 35000,
  "homes_vs_seat_households": 0.88,
  "stuck_mw_12m_cut": 146.4,
  "consented_not_built_mw_any_age": 146.4,
  "operational_mw": 94.3,
  "operational_homes_equivalent": 34000,
  "refused_5y_mw": 0.0,
  "withdrawn_5y_mw": 0.2,
  "median_months_to_decision": 7.2,
  "rank": 69,
  "tech_mix": {
   "solar": 96.8
  },
  "tech_summary": "all solar",
  "waiting_vs_running": 1.0,
  "projects": [
   {
    "site_name": "Fernbrook - Solar farm & Battery storage",
    "repd_ref_id": 8505,
    "technology": "Solar Photovoltaics",
    "capacity_mw": 49.9,
    "homes_equivalent": 18000,
    "consented": "2023-02-13",
    "months_waiting": 41.6,
    "status": "Awaiting Construction"
   },
   {
    "site_name": "Woodlands Manor Farm, Horton - Solar Farm",
    "repd_ref_id": 14287,
    "technology": "Solar Photovoltaics",
    "capacity_mw": 30.0,
    "homes_equivalent": 11000,
    "consented": "2025-05-07",
    "months_waiting": 14.9,
    "status": "Awaiting Construction"
   },
   {
    "site_name": "North Dairy Farm Solar Farm",
    "repd_ref_id": 14508,
    "technology": "Solar Photovoltaics",
    "capacity_mw": 30.0,
    "homes_equivalent": 11000,
    "consented": "2024-01-15",
    "months_waiting": 30.6,
    "status": "Awaiting Construction"
   },
   {
    "site_name": "North Farm, Horton - Solar Farm",
    "repd_ref_id": 11698,
    "technology": "Solar Photovoltaics",
    "capacity_mw": 19.0,
    "homes_equivalent": 6900,
    "consented": "2025-05-07",
    "months_waiting": 14.9,
    "status": "Awaiting Construction"
   },
   {
    "site_name": "Blandford Hill - EV Charging Station & Solar Farm",
    "repd_ref_id": 8461,
    "technology": "Solar Photovoltaics",
    "capacity_mw": 15.0,
    "homes_equivalent": 5400,
    "consented": "2022-01-26",
    "months_waiting": 54.2,
    "status": "Awaiting Construction"
   },
   {
    "site_name": "Merck, The Old Brickyard - Solar Photo-Voltaic Modules",
    "repd_ref_id": 18420,
    "technology": "Solar Photovoltaics",
    "capacity_mw": 0.7,
    "homes_equivalent": 300,
    "consented": "2025-04-22",
    "months_waiting": 15.4,
    "status": "Awaiting Construction"
   },
   {
    "site_name": "Brickfields Business Park, Unit 17 - Solar panels",
    "repd_ref_id": 12399,
    "technology": "Solar Photovoltaics",
    "capacity_mw": 0.6,
    "homes_equivalent": 200,
    "consented": "2023-07-27",
    "months_waiting": 36.2,
    "status": "Under Construction"
   },
   {
    "site_name": "Brickfields Business Park, Unit 35 - Solar Panels",
    "repd_ref_id": 12393,
    "technology": "Solar Photovoltaics",
    "capacity_mw": 0.3,
    "homes_equivalent": 100,
    "consented": "2023-05-17",
    "months_waiting": 38.6,
    "status": "Under Construction"
   },
   {
    "site_name": "Riversmeet, Hardings Lane - Solar Panels",
    "repd_ref_id": 13886,
    "technology": "Solar Photovoltaics",
    "capacity_mw": 0.2,
    "homes_equivalent": 100,
    "consented": "2023-06-22",
    "months_waiting": 37.4,
    "status": "Awaiting Construction"
   },
   {
    "site_name": "Dextra Group, Brickfields Business Park - Solar PV Systems",
    "repd_ref_id": 15990,
    "technology": "Solar Photovoltaics",
    "capacity_mw": 0.2,
    "homes_equivalent": 100,
    "consented": "2024-04-08",
    "months_waiting": 27.8,
    "status": "Awaiting Construction"
   },
   {
    "site_name": "Brickfields Business Park, Unit 16 - Solar Panels",
    "repd_ref_id": 12397,
    "technology": "Solar Photovoltaics",
    "capacity_mw": 0.2,
    "homes_equivalent": 100,
    "consented": "2023-05-25",
    "months_waiting": 38.3,
    "status": "Under Construction"
   },
   {
    "site_name": "Brickfields Business Park, Unit 24 - Solar panels",
    "repd_ref_id": 12398,
    "technology": "Solar Photovoltaics",
    "capacity_mw": 0.2,
    "homes_equivalent": 100,
    "consented": "2023-05-12",
    "months_waiting": 38.7,
    "status": "Under Construction"
   },
   {
    "site_name": "St Giles House, Creech Hill - Solar Panels",
    "repd_ref_id": 15602,
    "technology": "Solar Photovoltaics",
    "capacity_mw": 0.1,
    "homes_equivalent": 100,
    "consented": "2024-01-29",
    "months_waiting": 30.1,
    "status": "Awaiting Construction"
   },
   {
    "site_name": "Hospital Metalcraft, Blandford Heights Industrial Estate - Solar Panels",
    "repd_ref_id": 12834,
    "technology": "Solar Photovoltaics",
    "capacity_mw": null,
    "homes_equivalent": null,
    "consented": "2023-01-17",
    "months_waiting": 42.5,
    "status": "Awaiting Construction"
   }
  ]
 },
 "number3": {
  "applicable": true,
  "per_household_gbp": 91.96,
  "seat_households": 40125,
  "seat_total_gbp": 3700000,
  "framings": {
   "days_of_home_electricity": 51.0
  },
  "note": "National figure: the per-household cost is the same for every GB seat; only the seat total varies with household count."
 },
 "batteries": {
  "operating_mw": 30.0,
  "building_mw": 0.0,
  "approved_mw": 103.0,
  "approved_24m_mw": 103.0,
  "refused_mw": 0.0,
  "submitted_mw": 0.0,
  "sites": [
   {
    "site_name": "Shaftesbury Energy Park - Battery Storage System",
    "capacity_mw": 100.0,
    "status": "approved",
    "year": 2023,
    "homes_while_discharging": 350000
   },
   {
    "site_name": "Hawkers Hill Energy Park",
    "capacity_mw": 20.0,
    "status": "operating",
    "year": 2017,
    "homes_while_discharging": 70000
   },
   {
    "site_name": "South Farm Solar Park",
    "capacity_mw": 10.0,
    "status": "operating",
    "year": 2020,
    "homes_while_discharging": 35000
   },
   {
    "site_name": "Blandford Hill - EV Charging Station & Solar Farm",
    "capacity_mw": 3.0,
    "status": "approved",
    "year": 2022,
    "homes_while_discharging": 11000
   }
  ]
 },
 "pipeline_projects": [
  {
   "site_name": "Shaftesbury Energy Park - Battery Storage System",
   "repd_ref_id": 10626,
   "technology": "Battery",
   "capacity_mw": 100.0,
   "homes_equivalent": null,
   "status": "Awaiting Construction",
   "consented": "2023-03-29",
   "refused": null,
   "planning_authority": "Dorset",
   "planning_ref": "P/FUL/2022/06179",
   "operator": "TagEnergy",
   "reason": {
    "reason": "connection_date",
    "label": "Cannot connect to the grid until 2036, 13 years after it was approved",
    "who": "the grid operator (NESO) and National Grid",
    "evidence": {
     "project": "Shaftesbury Energy Park",
     "connection_date": "2036-12-06",
     "mw": 99.9,
     "stage": null,
     "source": "NESO TEC register"
    },
    "all_matches": [
     "connection_date",
     "consented_no_activity"
    ]
   },
   "earliest": "2036",
   "tec": {
    "project": "Shaftesbury Energy Park",
    "connection_date": "2036-12-06",
    "connection_year": 2036,
    "mw": 99.9,
    "stage": null,
    "who": "the grid operator (NESO) and National Grid",
    "gate2_outcome": null,
    "source": "NESO TEC register"
   }
  },
  {
   "site_name": "Fernbrook - Solar farm & Battery storage",
   "repd_ref_id": 8505,
   "technology": "Solar Photovoltaics",
   "capacity_mw": 49.9,
   "homes_equivalent": 18000,
   "status": "Awaiting Construction",
   "consented": "2023-02-13",
   "refused": "2022-01-25",
   "planning_authority": "Dorset",
   "planning_ref": "P/FUL/2021/02046",
   "operator": "Low Carbon UK Solar Investment Company Limited",
   "reason": {
    "reason": "consented_no_activity",
    "label": "Approved 3 years ago \u2014 nothing has happened since",
    "who": "the developer and the network company",
    "evidence": {
     "consent_date": "2023-02-13",
     "years_since_consent": 3.5
    },
    "all_matches": [
     "consented_no_activity"
    ]
   },
   "earliest": null,
   "tec": null
  },
  {
   "site_name": "Woodlands Manor Farm, Horton - Solar Farm",
   "repd_ref_id": 14287,
   "technology": "Solar Photovoltaics",
   "capacity_mw": 30.0,
   "homes_equivalent": 11000,
   "status": "Awaiting Construction",
   "consented": "2025-05-07",
   "refused": null,
   "planning_authority": "Dorset",
   "planning_ref": "P/FUL/2023/03415",
   "operator": "BayWa r.e. UKLimited / Gr\u00fcne Energien Projekt UG",
   "reason": {
    "reason": "consented_no_activity",
    "label": "Approved a year ago \u2014 nothing has happened since",
    "who": "the developer and the network company",
    "evidence": {
     "consent_date": "2025-05-07",
     "years_since_consent": 1.2
    },
    "all_matches": [
     "consented_no_activity"
    ]
   },
   "earliest": null,
   "tec": null
  },
  {
   "site_name": "North Dairy Farm Solar Farm",
   "repd_ref_id": 14508,
   "technology": "Solar Photovoltaics",
   "capacity_mw": 30.0,
   "homes_equivalent": 11000,
   "status": "Awaiting Construction",
   "consented": "2024-01-15",
   "refused": null,
   "planning_authority": "Dorset",
   "planning_ref": "P/FUL/2021/01018",
   "operator": "British Solar Renewables",
   "reason": {
    "reason": "consented_no_activity",
    "label": "Approved 3 years ago \u2014 nothing has happened since",
    "who": "the developer and the network company",
    "evidence": {
     "consent_date": "2024-01-15",
     "years_since_consent": 2.5
    },
    "all_matches": [
     "consented_no_activity"
    ]
   },
   "earliest": null,
   "tec": null
  },
  {
   "site_name": "North Farm, Horton - Solar Farm",
   "repd_ref_id": 11698,
   "technology": "Solar Photovoltaics",
   "capacity_mw": 19.0,
   "homes_equivalent": 6900,
   "status": "Awaiting Construction",
   "consented": "2025-05-07",
   "refused": null,
   "planning_authority": "Dorset",
   "planning_ref": "P/FUL/2023/02829",
   "operator": "North Farm Mannington Solar Limited / BayWa r.e.",
   "reason": {
    "reason": "consented_no_activity",
    "label": "Approved a year ago \u2014 nothing has happened since",
    "who": "the developer and the network company",
    "evidence": {
     "consent_date": "2025-05-07",
     "years_since_consent": 1.2
    },
    "all_matches": [
     "consented_no_activity"
    ]
   },
   "earliest": null,
   "tec": null
  },
  {
   "site_name": "Blandford Hill - EV Charging Station & Solar Farm",
   "repd_ref_id": 8461,
   "technology": "Solar Photovoltaics",
   "capacity_mw": 15.0,
   "homes_equivalent": 5400,
   "status": "Awaiting Construction",
   "consented": "2022-01-26",
   "refused": null,
   "planning_authority": "Dorset",
   "planning_ref": "P/FUL/2021/02622",
   "operator": "Naturalis Energy Developments Limited",
   "reason": {
    "reason": "consented_no_activity",
    "label": "Approved 5 years ago \u2014 nothing has happened since",
    "who": "the developer and the network company",
    "evidence": {
     "consent_date": "2022-01-26",
     "years_since_consent": 4.5
    },
    "all_matches": [
     "consented_no_activity"
    ]
   },
   "earliest": null,
   "tec": null
  },
  {
   "site_name": "Motcombe Road, Motcombe - Solar Pv Arrays",
   "repd_ref_id": 16914,
   "technology": "Solar Photovoltaics",
   "capacity_mw": 12.0,
   "homes_equivalent": 4400,
   "status": "Application Submitted",
   "consented": null,
   "refused": null,
   "planning_authority": "Dorset",
   "planning_ref": "P/FUL/2025/03674",
   "operator": "Enviromena",
   "reason": {
    "reason": "planning_overdue",
    "label": "Waiting 12 months for a planning decision",
    "who": "Dorset Council",
    "evidence": {
     "submitted": "2025-07-29",
     "months_waiting": 12
    },
    "all_matches": [
     "planning_overdue"
    ]
   },
   "earliest": null,
   "tec": null
  },
  {
   "site_name": "Blandford Hill - EV Charging Station & Solar Farm",
   "repd_ref_id": 8462,
   "technology": "Battery",
   "capacity_mw": 3.0,
   "homes_equivalent": null,
   "status": "Awaiting Construction",
   "consented": "2022-01-26",
   "refused": null,
   "planning_authority": "Dorset",
   "planning_ref": "P/FUL/2021/02622",
   "operator": "Naturalis Energy Developments Limited",
   "reason": {
    "reason": "consented_no_activity",
    "label": "Approved 5 years ago \u2014 nothing has happened since",
    "who": "the developer and the network company",
    "evidence": {
     "consent_date": "2022-01-26",
     "years_since_consent": 4.5
    },
    "all_matches": [
     "consented_no_activity"
    ]
   },
   "earliest": null,
   "tec": null
  }
 ],
 "projects_withheld_unreferenced": 0,
 "neighbours": [
  "E14001363",
  "E14001171",
  "E14001460",
  "E14001498",
  "E14001374",
  "E14001485",
  "E14001575",
  "E14001247"
 ],
 "flags": [
  "curtailment_not_visible"
 ],
 "windows": {
  "curtailment": [
   "2025-08-01",
   "2026-07-31"
  ],
  "repd_as_of": "2026-08-03"
 }
}