 "pcon24cd": "E14001254",
 "name": "Gravesham",
 "nation": "England",
 "number1": {
  "visible": false,
  "note": "No big wind farm on the national grid is mapped to this constituency. Smaller wind farms here can still be paid to switch off by the local network, but those payments are not visible in national data \u2014 the \u00a3 figure is a floor.",
  "invisible_wind": {
   "mw": 0.0,
   "sites": 0
  }
 },
 "number2": {
  "stuck_mw": 0.8,
  "stuck_mw_int": 1,
  "stuck_sites": 2,
  "homes_equivalent": 300,
  "homes_vs_seat_households": 0.01,
  "stuck_mw_12m_cut": 0.8,
  "consented_not_built_mw_any_age": 0.8,
  "operational_mw": 0.0,
  "operational_homes_equivalent": 0,
  "refused_5y_mw": 0.0,
  "withdrawn_5y_mw": 0.0,
  "median_months_to_decision": 2.1,
  "rank": 453,
  "tech_mix": {
   "solar": 0.8
  },
  "tech_summary": "all solar",
  "waiting_vs_running": null,
  "projects": [
   {
    "site_name": "Kimberly Clark Limited, Northfleet Mill - Solar Pv System",
    "repd_ref_id": 14865,
    "technology": "Solar Photovoltaics",
    "capacity_mw": 0.4,
    "homes_equivalent": 200,
    "consented": "2023-11-20",
    "months_waiting": 32.4,
    "status": "Awaiting Construction"
   },
   {
    "site_name": "Morrisons, Coldharbour Road - Solar Photovoltaics Panels",
    "repd_ref_id": 12579,
    "technology": "Solar Photovoltaics",
    "capacity_mw": 0.3,
    "homes_equivalent": 100,
    "consented": "2022-12-12",
    "months_waiting": 43.7,
    "status": "Awaiting Construction"
   }
  ]
 },
 "number3": {
  "applicable": true,
  "per_household_gbp": 91.96,
  "seat_households": 41724,
  "seat_total_gbp": 3800000,
  "framings": {
   "days_of_home_electricity": 51.0
  },
  "note": "National figure: the per-household cost is the same for every GB seat; only the seat total varies with household count."
 },
 "batteries": {
  "operating_mw": 0.0,
  "building_mw": 0.0,
  "approved_mw": 0.0,
  "approved_24m_mw": 0.0,
  "refused_mw": 0.0,
  "submitted_mw": 100.0,
  "sites": [
   {
    "site_name": "Thames Way, Northfleet - Battery Energy Storage",
    "capacity_mw": 100.0,
    "status": "submitted",
    "year": null,
    "homes_while_discharging": 350000
   }
  ]
 },
 "pipeline_projects": [
  {
   "site_name": "Thames Way, Northfleet - Battery Energy Storage",
   "repd_ref_id": 18128,
   "technology": "Battery",
   "capacity_mw": 100.0,
   "homes_equivalent": null,
   "status": "Application Submitted",
   "consented": null,
   "refused": null,
   "planning_authority": "Gravesham",
   "planning_ref": "20250730",
   "operator": "Speedgreen Limited",
   "reason": {
    "reason": "in_planning",
    "label": "Applied in 2025, still waiting for a decision",
    "who": "Gravesham Council",
    "evidence": {
     "submitted": "2025-08-14",
     "months_waiting": 12
    },
    "all_matches": [
     "in_planning"
    ]
   },
   "earliest": null,
   "tec": null
  },
  {
   "site_name": "Northfleet Mill, Crete Hall Road - Green Hydrogen Electrolyser",
   "repd_ref_id": 18566,
   "technology": "Hydrogen",
   "capacity_mw": 15.0,
   "homes_equivalent": null,
   "status": "Awaiting Construction",
   "consented": "2025-09-25",
   "refused": null,
   "planning_authority": "Gravesham",
   "planning_ref": "20250251",
   "operator": "HYRO Energy Limited (Octopus & RES)",
   "reason": {
    "reason": "consented_no_activity",
    "label": "Approved less than a year ago \u2014 nothing has happened since",
    "who": "the developer and the network company",
    "evidence": {
     "consent_date": "2025-09-25",
     "years_since_consent": 0.9
    },
    "all_matches": [
     "consented_no_activity"
    ]
   },
   "earliest": null,
   "tec": null
  }
 ],
 "projects_withheld_unreferenced": 0,
 "neighbours": [
  "E14001549",
  "E14001157",
  "E14001447",
  "E14001191"
 ],
 "flags": [
  "curtailment_not_visible"
 ],
 "windows": {
  "curtailment": [
   "2025-08-01",
   "2026-07-31"
  ],
  "repd_as_of": "2026-08-03"
 }
}